Luca D’Acierno et al., Int. J. Transp. Dev. Integr., Vol. 3, No. 3 (2019), 232–244
A SIMULATION-BASED APPROACH FOR
ESTIMATING RAILWAY CAPACITY
LUCA D’ACIERNO, MARILISA BOTTE & GIUSEPPE PIGNATIELLO
Department of Civil, Architectural and Environmental Engineering,
Federico II University of Naples, Italy
ABSTRACT
The article proposes a simulation-based approach for supporting a threshold analysis aimed at identifying the maximum number of trains to be operated on a line, given the related infrastructural and
operational constraints. The method addresses an intermediate case between the theoretical and practical capacity conditions (i.e. simulated capacity). Moreover, the evaluated capacity represents an upper-bound value and, therefore, it is independent of the involved demand flows which, hence, have
been neglected in the provided discussion. In particular, against an initial effort for building the rail
micro-simulation model, which requires the modelling of infrastructure layout, signalling system, rolling stock and planned timetable, the presented methodology allows infrastructure managers to properly
direct the decision-making process by providing information on the effects of any intervention, in advance of its effective implementation. In order to show the feasibility and usefulness of the proposed
approach, it has been applied in the case of a real rail network context in the south of Italy.
Keywords: Railway systems, rail simulation models, railway capacity estimation, threshold analysis,
timetabling design process.
1 INTRODUCTION
The properties of sustainability and efficiency which railway systems offer make them a key
transport option in a context affected by congestion and pollution issues. Indeed, in the literature, several matters related to the management and optimisation of metro/rail networks have
been addressed, such as timetabling and rescheduling tasks [1–5], the interactions with travel
demand [6–12], the implementation of energy-saving policies ([13–17] and the impacts on
the territories [18–21].
The timetabling process of a railway line consists in establishing the departure and arrival
times of each convoy at each station being served, respecting the limits imposed by safety,
law, infrastructure, signalling system and the necessity to guarantee a certain number of transfers. Such a planning phase is crucial for the entire railway operation as it influences, directly
or indirectly, system performance, the degree of use of the infrastructure capacity, service
quality, the management of rolling stock and the crew scheduling. While, at the operational
level, rescheduling tasks are aimed at properly reacting to system failure and re-establishing
ordinary service conditions as rapidly as possible, so as to minimise the inconvenience. In
particular, as shown by [22], it is possible to distinguish between disturbance and disruption:
disturbances are generally considered as small perturbations influencing the system; while,
disruptions indicate large external incidents which can lead to the cancellation of runs within
the timetable or even to the interruption of the whole service. Clearly, the greater the severity
of the failure, the greater the impact of the corrective measures to be adopted.
Rail transport, just as any other transport system, is not finalised to itself, but its task is to
move people or goods around, and, therefore, a realistic and accurate analysis cannot ignore
passenger/freight flows features. In this context, [23] provides an analysis of the rail system
in the European framework where different network layouts are linked to a set of key parameters affecting the rail service and the main cost drivers are critically discussed. Hence, the
© 2019 WIT Press, www.witpress.com
ISSN: 2058-8305 (paper format), ISSN: 2058-8313 (online), http://www.witpress.com/journals
DOI: 10.2495/TDI-V3-N3-232-244
Luca D’Acierno et al., Int. J. Transp. Dev. Integr., Vol. 3, No. 3 (2019)
233
time-spatial distribution of involved demand flows needs to be evaluated and, for instance,
the behaviour of passengers in the different phases of the trip (turnstile access, transfer from
the turnstiles to the platform, waiting on platform, boarding and alighting process, etc.) needs
to be accurately modelled. In particular, as shown by [24], a key issue to be addressed is
the dynamic interaction between passengers and rail service at the interface train-platform.
Finally, transport modes based on railway technology present a favourable ratio between
operational costs (including energy consumption) and transport capacity with respect to other
mobility systems. Therefore, in order to maximise such energy efficiency, several eco-driving
measures [25–28] and energy-recovery strategies [29–31] have been proposed.
This article, instead, deals with capacity issues related to the degree of infrastructural utilisation in railway contexts. The concept of capacity is rather articulate to be addressed, since
it can be considered by different perspectives. First, as shown by [32], it is necessary to make
a distinction between theoretical capacity and practical capacity. The theoretical capacity of
a line is the number of trains that can circulate in a specific time interval assuming minimum
distancing values between trains and the absence of disturbances. It represents the upper
limit as it describes the ideal operating conditions, ignoring the effects caused by eventual
unforeseen events or disturbances that occur in reality. Practical capacity is the actual limit of
the volume of traffic that can be managed on a line or in a node at certain levels of regularity,
reflecting the actual heterogeneous composition of traffic. However, an intermediate condition can be identified, which represents the maximum number of trains to be operated in a
line, not in ideal conditions, but considering a series of operational constraints such as buffer
times, inversion manoeuvres and terminal stations organisation. From this point forward, this
kind of capacity is referred to as simulated capacity.
Moreover, as shown by [33], capacity is based on the relations between the following
parameters:
•
•
•
•
The number of trains. In fact, the more trains are, the less capacity is left for traffic quality;
The average speed. The braking distance increases proportionally more than the average
speed;
The stability. In order to avoid the propagation of minor delays, margins and buffers have
to be added to the running time of trains and between paths;
The heterogeneity. The more are the differences between the train running times, the more
capacity will be consumed.
The relation between these parameters is shown in the so-called capacity balance depicted
in Fig. 1. As can be seen, a chord links the points on the axes, expressing the value for each
parameter, and the length of the chord corresponds to the capacity. The capacity utilisation is
then defined by the positions of the chord on the four axes.
As said, capacity can be viewed differently according to the subject considered. Indeed,
while from a market point of view capacity demands are oriented to satisfy peak values, infrastructure planning is interested in a definition of capacity which guarantees a profitable utilisation of the infrastructure. From a timetable standpoint, by contrast, capacity considerations
are necessary to define train paths trying to fulfil travel demand needs on a given infrastructure. Finally, from an operational point of view, capacity evolves continuously and depends
on current infrastructure availability, delays, diversion and number of additional trains.
In this framework, our goal is to perform a preliminary threshold analysis providing the
upper bound of the number of trains that can be operated on a line, given infrastructural and
operational constraints (i.e. simulated capacity). Such an evaluation is clearly independent of
234
Luca D’Acierno et al., Int. J. Transp. Dev. Integr., Vol. 3, No. 3 (2019)
No. of trains
(capacity)
Train speed
Robustness
Heterogeneity
Figure 1: Capacity balance [33].
the number of passengers who effectively use the analysed rail services and, for this reason,
although the importance of considering involved demand flows stated above, they have been
neglected in the provided discussion.
According to the literature, three main approaches can be identified for estimating railway
capacity: (i) analytical methods [34–38]; (ii) optimisation methods [33, 39] and (iii) simulation methods [32, 40]. In particular, simulation models can be classified based on different
criteria. First, according to the assumption on the level of detail considered for the network
representation, it is possible to have macroscopic [41, 42], mesoscopic [43, 44] and microscopic [45, 46] simulation models. Moreover, based on the assumption made on the involved
variables, it is possible distinguishing deterministic [47, 48] and stochastic [49, 50] models.
The deterministic case deals with parameters characterised by a steady value equal to their
average; on the other hand, in the case of stochastic simulations, involved parameters are
considered as random variables and, therefore, they are modelled by means of their probability density function (pdf), as well as the mean and the standard deviation of the pdf itself.
Finally, according to the adopted processing techniques, we can have synchronous [51, 52]
and asynchronous [53] simulation models. In particular, synchronous approaches simulate
the events as they occur in reality; therefore, a chronological progression is followed, with
no chance of returning to previous states. In asynchronous models, on the other hand, the
convoys are simulated according to their class of priority. Specifically, we adopted a what-if
design method, based on a microscopic model of the railway infrastructure; while, the simulation of rail service follows a deterministic/synchronous approach.
The remainder of the article is structured as follows: Section 2 outlines the provided methodology for estimating the maximum performance of the network in terms of simulated
capacity; Section 3 presents an application of the proposed approach in the case of a real rail
line; finally, Section 4 summarises conclusions and research prospects.
2 THE PROPOSED METHODOLOGY
The proposed approach (described in Fig. 2) represents a simulation-based method aimed
to perform a preliminary evaluation on the maximum performance of a railway network in
terms of number of trains that can be operated on a given line, so as to carry out a threshold
analysis of the available potentiality. In particular, we proposed a what-if methodology consisting in identifying a certain set of scenarios to be modelled and tested, thus evaluating the
related performance indexes and selecting the best option according to the target pursued.
Luca D’Acierno et al., Int. J. Transp. Dev. Integr., Vol. 3, No. 3 (2019)
Model formualtion
Infrastructure
Rolling stock
Signalling
Model calibration
Scenario definition
Current scenario
Scenario #1
Timetable model
Scenario #2
...
Simulation
model
calibration
Scenario #n
Scenario #(n+1)
235
Scenario simulation
KPIs scenario #1
KPIs scenario #2
...
KPIs scenario #n
KPIs scenario #(n+1)
Figure 2: Flow chart of the proposed methodology.
The first step is to reproduce in a micro-simulation tool the infrastructure layout of the
analysed line, which includes nodes, links, stations and signalling system functions, as well
as available rolling stock and the adopted timetable. After that, the basic scenario is ready to
be calibrated and validated, by comparing simulation results with the real planned service.
After checking that the simulation model accurately reproduces the effective operational conditions of the line, a set of alternative scenarios have to be modelled.
In particular, key issues to be addressed for creating each simulation scenario are related
to the assumptions on the implemented timetable structure and, consequently, on the identification of a feasible train-set circulation plan. Obviously, such two phases (i.e. timetabling
process and definition of train-set circulation plan) are rather articulate since several variables
are involved. As regards the timetable, different time rates need to be considered, i.e. running
times, dwell times, inversion times, buffer times and layover times. Running times result by
the simulation process, given the infrastructure layout and rolling stock performance, while
dwell times (generally calculated as shown by [24]) are preliminary set as input simulation
values. As regards the inversion times, they derive by the simulation process. In this respect,
it is worth noting that, although our aim consists in estimating line capacity, rather than station capacity, the representation of terminal stations layout turns out to be fundamental in the
estimation of inversion times and, therefore, in the cycle time to be considered in the timetabling process. Buffer times are generally set up during the design phase in order to address
possible delays or, simply, eventual fluctuations which can occur during the service, given
the stochasticity of the phenomenon being examined. Obviously, the lower the level of automation, the higher the relevance of the stochastic nature of the involved factors. With a high
value of buffer times, the timetable presents greater flexibility and, thus, an increased chance
of absorbing delays, avoiding their propagation; however, this could lead to an under-usage
of system capacity. Therefore, it is necessary to identify the right balance between the use of
railway capacity and the stability of timetable. For this reason, different values of buffer times
have to be tested in the simulation procedure. Finally, the layover time is a time spent by the
convoy at the terminus until the planned departure time dictated by the timetable and, hence,
it derives from the link between train-sets and trip tasks identified in the following phase.
Indeed, after having defined the timetable structure, a feasible set-circulation plan needs to
be assumed on the basis of rolling stock availability. More in detail, as already said, the corresponding relationship between train-sets and trip tasks in the timetable has to be identified,
according to specific routes and maintenance issues.
236
Luca D’Acierno et al., Int. J. Transp. Dev. Integr., Vol. 3, No. 3 (2019)
After having built each scenario as explained above, the simulation can be run and key performance indexes (KPIs) can be computed. Finally, one or more design strategies which maximise
network performance in terms of number of trains to be operated on the line are identified.
3 REAL NETWORK APPLICATION
In order to show the feasibility of the proposed method, it has been applied in the case of a real
railway network which includes Cumana and Circumflegrea regional lines, operated by ‘Ente
Autonomo Volturno’ company in Italy. Both involved lines have the same terminal stations
(i.e. Montesanto and Torregaveta): Circumflegrea connects Naples city centre with the northwest area of the city and the towns in the Phleghrean Fields, and Cumana runs a southern route
along the Bay of Naples. Moreover, an infrastructural improvement, consisting in building a
short branch connecting the Soccavo station of Circumflegrea with the Edenlandia station of
Cumana, has been approved by the Transport Ministry of the Italian government. Specifically,
according to the project, the stretch, except for the connection with terminus stations (i.e.
Soccavo and Edenlandia), will run underground and go through four stations, namely Monte
Sant’Angelo, Parco San Paolo, Terracina and Giochi del Mediterraneo (Fig. 3).
In this context, the proposed simulation-based approach has been applied with the aim of
performing a threshold analysis for identifying the maximum performance achievable on the
network, thanks to this infrastructural improvement. Specifically, we adopt the commercial
software OpenTrack® [54].
Therefore, both Circumflegrea and Cumana lines, as well as the connection branch, need to
be accurately modelled with related infrastructure layouts, signalling systems, rolling stock
and timetable structures. Clearly, in a timetable design perspective, the layout of terminal/
connection stations needs to be accurately reproduced. Indeed, as already mentioned, such
a layout determines inversion manoeuvres allowed and, therefore, planned inversion times
which, in turn, affect the cycle time to be considered and the number of required convoys.
Tested scenarios have been built according to the design stages foreseen in the project of
the branch. More in detail, the construction is planned to be implemented in three subsequent
phases: (i) until Monte Sant’Angelo station, (ii) until Giochi del Mediterraneo station and
(iii) until Edenlandia station (planned to be re-named as Kennedy station).
Licola
Soccavo
Monte Sant’Angelo
Parco S. Paolo
Terracina
Torregaveta
Giochi del Mediterraneo
Bagnoli
Cumana line
Montesanto
Edenlandia/Kennedy
Circumflegrea line
Figure 3: The analysed network context.
New line (branch)
237
Luca D’Acierno et al., Int. J. Transp. Dev. Integr., Vol. 3, No. 3 (2019)
In this framework, a key factor to be addressed is represented by the connection scheme
adopted for linking the branch with the Cumana line in the Edenlandia/Kennedy station. Specifically, two alternative schemes have been analysed: (i) indirect connection (i.e. terminus
station of the branch and Edenlandia station of Cumana line coincide planimetrically but offset
altimetrically); (ii) direct connection (i.e. the terminus station of the branch coincides with the
Edenlandia station of Cumana line, since they are built at the same level). Clearly, a direct infrastructure connection allows a direct service, which becomes, instead, unfeasible in the second
case. In particular, an indirect connection, beyond a different infrastructure design implies a
two-side effect. On one hand, by an operational point of view, no interactions between trains
on the branch and on the Cumana line occur; while, by a passengers’ perspective, an interruption in the service occurs, since intermediate reloading is required for continuing the trip.
Moreover, according to the planned service, the infrastructure can be fully exploited or partially utilised. In particular, in the provided application, only combinations of infrastructure/
service which make full use of the available infrastructure are considered.
Therefore, the following configurations have been identified:
I.
II.
III.
Soccavo–Monte Sant’Angelo (shuttle service);
Soccavo–Monte Sant’Angelo–Giochi del Mediterraneo (shuttle service);
Soccavo–Monte Sant’Angelo–Edenlandia/Kennedy (shuttle service in the case of indirect connection);
IV. Soccavo–Monte Sant’Angelo–Edenlandia/Kennedy (shuttle in the case of direct connection);
V.
Montesanto–Soccavo–Monte Sant’Angelo (direct service via Circumflegrea);
VI. Montesanto–Soccavo–Monte Sant’Angelo–Giochi del Mediterraneo (direct service
via Circumflegrea);
VII. Montesanto–Soccavo–Monte Sant’Angelo–Edenlandia/Kennedy (direct service via
Circumflegrea in the case of indirect connection);
VIII. Montesanto–Soccavo–Monte Sant’Angelo–Edenlandia/Kennedy (direct service via
Circumflegrea in the case of direct connection);
IX. Soccavo–Monte Sant’Angelo–Edenlandia/Kennedy–Montesanto (direct service via
Cumana in the case of direct connection);
X.
Circular line: Montesanto–Soccavo–Monte Sant’Angelo–Edenlandia/Kennedy–Montesanto.
Table 1: Timetable structures.
Line
Services
Service headways [min]
Scenario 2010 Scenario 2019
Cumana
Montesanto–Torregaveta
Montesanto–Bagnoli (simple service)
Montesanto–Bagnoli (cumulate service)
Circumflegrea Montesanto–Torregaveta
Montesanto–Licola (simple service)
Montesanto–Licola (cumulate service)
Degraded service for the reduction in public subsidies occurred in 2011.
*
20
20
10
40
40
20
20
0
20
3 runs per day*
20
20
Scenario Configuration
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
Track
Timetable Headway on the Daily runs
framework structure branch [min]
on the branch
(I) Soccavo –Monte Sant’Angelo (shuttle service)
Single/
double
(II) Soccavo–Monte Sant’Angelo–Giochi del
Single/
Mediterraneo (shuttle service)
double
(III) Soccavo–Monte Sant’Angelo–Edenlandia/Kennedy Single/
(shuttle service and indirect connection)
double
(IV) Soccavo–Monte Sant’Angelo–Edenlandia/Kennedy Single/
(shuttle service and direct connection)
double
(V) Montesanto–Soccavo–Monte Sant’Angelo (direct
service via Circumflegrea)
Single
Double
(VI) Montesanto–Soccavo–Monte Sant’Angelo–Giochi Single
del Mediterraneo (direct service via Circumflegrea)
Double
(VII) Montesanto–Soccavo–Monte Sant’Angelo–
Edenlandia/Kennedy (direct service via
Circumflegrea and indirect connection)
Single
(VIII) Montesanto–Soccavo–Monte Sant’Angelo–
Edenlandia/Kennedy (direct service via
Circumflegrea and direct connection)
Single
Double
Double
Required
rail convoys
2010/2019
4
480
4
2010/2019
4
480
7
2010/2019
4
480
8
2010
2019
2010
2019
2010
2019
2010
2019
2010
2019
2010
2019
2010
2019
2010
2019
2010
2019
20
20
40
40
20
20
60
60
20
20
60
60
20
20
n.f.*
60
n.f.*
20
98
98
50
50
96
96
34
34
96
96
34
34
96
96
n.f.*
34
n.f.*
96
3
3
2
2
2
2
2
2
3
3
2
2
3
3
n.f.*
2
n.f.*
3
(Continued)
Luca D’Acierno et al., Int. J. Transp. Dev. Integr., Vol. 3, No. 3 (2019)
1
238
Table 2: Simulation results.
Scenario Configuration
Track
Timetable Headway on the Daily runs
framework structure branch [min]
on the branch
22
Single/
double
2010
20
98
3
2019
20
98
3
Single
2010
2019
2010
2019
n.f.*
40
20
20
n.f.*
48
96
96
n.f.*
3
4
4
23
24
25
26
27
(IX) Soccavo–Monte Sant’Angelo–Edenlandia/
Kennedy–Montesanto (direct service via Cumana
and direct connection)
(X) Circular line
*n.f. = not feasible.
Double
Required
rail convoys
Luca D’Acierno et al., Int. J. Transp. Dev. Integr., Vol. 3, No. 3 (2019)
Table 2: (Continued)
239
240
Luca D’Acierno et al., Int. J. Transp. Dev. Integr., Vol. 3, No. 3 (2019)
Such scenarios have been analysed by considering two different infrastructure layouts
between Montesanto and Soccavo on the Circumflegrea line, that is, single-track (current
condition) and double-track frameworks. The idea behind this to point out that such a singletrack section can represent a stringent limit for the improvement of line capacity.
Finally, in addition to the current timetable referred to 2019, which results strongly
degraded because of the reduction in public subsidies occurred in 2011, the timetable dated
2010 has been simulated (see Table 1). The aim is to consider an operational service suitably
optimised for the line, independent of exogenous reasons such as funding reductions.
Hence, by combining the 10 configurations identified above with the infrastructure layouts
between Montesanto and Soccavo (i.e. single- and double-track frameworks) and the different adopted timetables (i.e. 2010 and 2019), a total of 27 scenarios have been simulated
and compared on the basis of KPIs shown in Table 2. In particular, service headways, daily
number of runs and number of convoys to be operated on the branch have been computed for
each analysed scenario.
The alternatives maximising service frequency on the branch and the degree of infrastructure utilisation are highlighted in grey and, in particular, they are:
•
•
Scenario 3 identifying a shuttle-service Soccavo-Edenlandia which fully exploits the
branch and does not interfere with the existing lines (i.e. Circumflegrea and Cumana). This
solution, by a passengers’ point of view, presents a discomfort issue which is represented
by the necessity of intermediate reloading in the terminal stations for continuing the trip
on the existing lines;
Scenarios 26 and 27 which differ exclusively for the timetable adopted on the existing
lines. Such an option allows a duty fully exploiting the infrastructure and offers a service
with no intermediate reloadings by means of a circular line. In addition, it generates synergies with the already existing runs on Circumflegera and Cumana lines, which are entirely
to the benefit of users.
Moreover, the presence of three unfeasible scenarios (i.e. 18, 20 and 24) highlights the necessity of implementing doubling infrastructure measures as priority interventions.
4 CONCLUSIONS AND RESEARCH PROSPECTS
The article presents a simulation-based approach for performing a threshold analysis and,
thus, providing the maximum number of trains to be operated on a line. The aim is to provide
a decision support system for properly leading every successive evaluation. In particular,
critical issues and strengths of such an approach have been identified and its feasibility has
been shown by applying it to a real regional rail network. The methodology required an initial
effort for suitably modelling infrastructure, signalling systems, rolling stock and timetable,
but offers a proper basis for an accurate evaluation of effects due to the implementation of different intervention strategies. For example, in the case of the analysed context, the proposed
method allowed identifying in the section Montesanto–Soccavo a bottleneck which could
nullify any attempt of improving service quality. Moreover, the provided results allowed
identifying a set of best measures to be implemented. In particular, in the light of the simulation outcome, authors propose to plan a service integrating the two alternatives identified
(i.e. shuttle service and circular line), thus taking advantages from the synergies generated
by the overlapping between these two configurations and, additionally, by the overlapping of
them with existing runs on the Circumflegrea and Cumana lines (Fig. 4). In this way, on the
241
Luca D’Acierno et al., Int. J. Transp. Dev. Integr., Vol. 3, No. 3 (2019)
Cumana line service (6 runs/h)
Shuttle service (9-12 runs/h)
Circumflegrea line service (3 runs/h)
Circular line service (3 runs/h)
Licola
Soccavo
Cumulative frequency
Monte Sant’Angelo
6 runs/h
Cumulative frequency
Torregaveta
12-15 runs/h
Giochi del Mediterraneo
Montesanto
Cumulative frequency
9 runs/h
Bagnoli
Edenlandia/Kennedy
Figure 4: Integrated services.
branch, it is possible to reach a minimum headway of 4 min, while, on the existing lines, it
occurs that:
•
•
Montesanto–Soccavo section reaches a cumulative frequency of 6 runs per hour. This
means that the headway goes from the current 20 min to 10 min, with a reduction in user
waiting times of 50%.
Montesanto–Edenlandia section reaches a cumulative frequency of 9 runs per hour. This
means that the headway goes from 10 min of the 2010 service to 6.7 min, with a reduction
in user waiting times of more than 33%.
Moreover, in terms of user-generalised cost, by considering prudentially the current travel
demand, the two above mentioned cases provide a reduction of, respectively, 156 M€ and
52 M€ per year, against a total investment of around 50 M€ required for the doubling of the
section Montesanto–Soccavo.
What was said confirms the potentialities of the proposed method in supporting a
cost–benefit analysis; however, as research prospects, the authors propose to perform additional tests in the case of other network contexts (e.g. high-speed lines) and non-ordinary
operational conditions (i.e. disturbance/disruption scenarios), thus further validating the provided methodology.
REFERENCES
[1] Goverde, R.M.P., Punctuality of railway operations and timetable stability analysis.
Ph.D. dissertation, Delft University of Technology, The Netherlands, 2005.
[2] Corman, F., D’Ariano, A. & Hansen, I.A., Disruption handling in large railway networks. WIT Transactions on The Built Environment, 114, pp. 629–640, 2010.
[3] Cadarso, L., Marín, Á. & Maróti, G., Recovery of disruptions in rapid transit networks.
Transportation Research Part E, 53, pp. 15–33, 2013.
[4] Binder, S., Maknoon, Y. & Bierlaire, M., Passenger-oriented railway disposition timetables in case of severe disruptions. Proceedings of the 15th Swiss Transport Research
Conference (STRC 2015), Ascona, Switzerland, 2015.
242
Luca D’Acierno et al., Int. J. Transp. Dev. Integr., Vol. 3, No. 3 (2019)
[5] Botte, M. & D’Acierno, L., Dispatching and rescheduling tasks and their interactions
with travel demand and the energy domain: Models and algorithms. Urban Rail Transit,
4(4), pp. 163–197, 2018.
[6] Kepaptsoglou, K. & Karlaftis, M.G., A model for analyzing metro station platform
conditions following a service disruption. Proceedings of the13th International IEEE
Annual Conference on Intelligent Transportation Systems (IEEE ITSC 2010), Funchal,
Portugal, pp. 1789–1794, 2010.
[7] Cascetta, E., Cartenì, A. & Henke, I., Stations quality, aesthetics and attractiveness of
rail transport: empirical evidence and mathematical models. Ingegneria Ferroviaria,
69(4), pp. 307–324, 2014.
[8] Di Mauro, R., Botte, M. & D’Acierno, L., An analytical methodology for extending
passenger counts in a metro system. International Journal of Transport Development
and Integration, 1(3), pp. 589–600, 2017.
[9] Xu, W., Zhao, P. & Ning, L., A passenger-oriented model for train rescheduling on an
urban rail transit line considering train capacity constraint. Mathematical Problems in
Engineering, 2017, article no. 1010745, pp. 1–9, 2017.
[10] Zhu, Y. & Goverde R.M.P., Dynamic passenger assignment during disruptions in railway systems. Proceedings of the 5th IEEE International Conference on Models and
Technologies for Intelligent Transportation Systems (IEEE MT-ITS 2017), Naples, Italy,
pp. 146–151, 2017.
[11] D’Acierno, L., Botte, M. & Montella, B., Assumptions and simulation of passenger
behaviour on rail platforms. International Journal of Transport Development and Integration, 2(2), pp. 123–135, 2018.
[12] Gallo, M., Improving equity of urban transit systems with the adoption of origin-destination based taxi fares. Socio-Economic Planning Sciences, 64, pp. 38–55, 2018.
[13] Kim, K.M., Kim, K.T. & Han, M.S., A model and approaches for synchronized energy
saving in timetabling. Proceedings of 9th World Congress on Railway Research (WCRR
2011), Lille, France, 2011.
[14] Chevrier, R., Pellegrini, P. & Rodriguez, J., Energy saving in railway timetabling: A
bi-objective evolutionary approach for computing alternative running times. Transportation Research Part C, 37, pp. 20–41, 2013.
[15] D’Acierno, L., Botte, M., Gallo, M. & Montella, B., Defining reserve times for metro
systems: An analytical approach. Journal of Advanced Transportation, 2018, art. no.
5983250, pp. 1–15, 2018.
[16] D’Acierno, L. & Botte, M., Passengers’ satisfaction in the case of energy-saving strategies: A rail system application. Proceedings of the 18th IEEE International Conference
on Environment and Electrical Engineering (IEEE EEEIC 2018) and 2nd Industrial and
Commercial Power Systems Europe (I&CPS 2018), Palermo, Italy, pp. 795–799, 2018.
[17] D’Acierno, L. & Botte, M., A passenger-oriented optimization model for implementing
energy-saving strategies in railway contexts. Energies, 11(11), art. no. 2946, pp. 1–25,
2018.
[18] Cartenì, A., Accessibility indicators for freight transport terminals. Arabian Journal for
Science and Engineering, 39(11), pp. 7647–7660, 2014.
[19] Cartenì, A., Urban sustainable mobility. Part 1: Rationality in transport planning. Transport Problems, 9(4), pp. 39–48, 2014.
[20] Cartenì, A., Urban sustainable mobility. Part 2: Simulation models and impacts estimation. Transport Problems, 10(1), pp. 5–16, 2015.
Luca D’Acierno et al., Int. J. Transp. Dev. Integr., Vol. 3, No. 3 (2019)
243
[21] Gallo, M., The impact of urban transit systems on property values: A model and some
evidences from the city of Naples. Journal of Advanced Transportation, 2018, art. no.
1767149, pp. 1–22, 2018.
[22] Cacchiani, V., Huisman, D., Kidd, M., Kroon, L., Toth, P., Veelenturf, L. & Wagenaar,
J., An overview of recovery models and algorithms for real-time railway rescheduling.
Transportation Research Part B, 63, pp. 15–37, 2014.
[23] Guglielminetti, P., Piccioni, C., Fusco, G., Licciardello, R. & Musso, A., Single wagonload traffic in Europe: Challenges, prospects and policy options. Ingegneria Ferroviaria,
70(11), pp. 927–948, 2015.
[24] D’Acierno, L., Botte, M., Placido, A., Caropreso, C. & Montella, B., Methodology for
determining dwell times consistent with passenger flows in the case of metro services.
Urban Rail Transit, 3(2), pp. 73–89, 2017.
[25] Miyatake, M. & Matsuda, K., Energy saving speed and charge/discharge control of a
railway vehicle with on-board energy storage by means of an optimization model. IEEJ
Transactions on Electrical and Electronic Engineering, 4(6), pp. 771–778, 2009.
[26]Albrecht, A., Howlett, P., Pudney, P. & Vu, X., Energy-efficient train control: from local convexity to global optimization and uniqueness. Automatica, 49(10), pp. 3072–3078, 2013.
[27] De Martinis, V., Weidmann, U. & Gallo, M., Towards a simulation-based framework for
evaluating energy-efficient solutions in train operation, WIT Transactions on the Built
Environment, 135, pp. 721–732, 2014.
[28] D’Acierno, L., Botte, M. & Montella, B., An analytical approach for determining reserve times on metro systems. Proceedings of the 17th IEEE International Conference
on Environment and Electrical Engineering (IEEE EEEIC 2017) and 1st Industrial and
Commercial Power Systems Europe (I&CPS 2017), Milan, Italy, pp. 722–727, 2017.
[29] Cornic, D., Efficient recovery of braking energy through a reversible dc substation.
Proceedings of Electrical Systems for Aircraft, Railway and Ship Propulsion (ESARS
2010), Bologna, Italy, 2010.
[30] Ibaiondo, H. & Romo, A., Kinetic energy recovery on railway systems with feedback to
the grid. Proceedings of the 14th International Power Electronics and Motion Control
Conference (EPE-PEMC 2010), Ohrid, Macedonia, pp. 94–97, 2010.
[31] Domínguez, M., Fernández-Cardador, A., Cucala, A.P. & Pecharromán, R.R., Energy
savings in metropolitan railway substations through regenerative energy recovery and
optimal design of ATO speed profiles. IEEE Transactions on Automation Science and
Engineering, 9(3), pp. 496–504, 2012.
[32] Prencipe, F.P. & Petrelli, M., Analytical methods and simulation approaches for determining the capacity of the Rome-Florence “Direttissima” line. Ingegneria Ferroviaria,
73(7–8), pp. 599–633, 2018.
[33] International Union of Railways (UIC), UIC Code 406: Capacity. 2nd ed., 2013.
[34] Schwanhäusser, W., Die Bemessung der Pufferzeiten im Fahrplangefüge der Eisenbahn, Ph.D. Dissertation, RWTH Aachen University, Germany, 1974.
[35] Bonora, G. & Giuliani, L., I criteri di calcolo di potenzialità delle linee ferroviarie.
Ingegneria Ferroviaria, 37(7), 1982.
[36] International Union of Railways (UIC), UIC Leaflet 405-1: Method to be used for the
determination of the capacity of Lines, 1983.
[37] Rete Ferroviaria Italiana – RFI (Italian National Railway Infrastructure Manager), Metodi di calcolo della capacità delle linee ferroviarie, Technical Report, 2011.
[38] Schultze, K., Gast, I. & Schwanhäusser, W., Sls plus – Einführung, Koblenz, Berlin,
Germany, 2015.
244
Luca D’Acierno et al., Int. J. Transp. Dev. Integr., Vol. 3, No. 3 (2019)
[39] Gonzalez, J., Rodriguez, C., Blanquer, J., Mera, J.M., Castellote, E. & Santos, R., Increase of metro line capacity by optimisation of track circuit length and location: In a
distance to go system. Journal of Advanced Transportation, 44(2), pp. 53–71, 2010.
[40] Lindfeldt, A., Railway capacity analysis: Methods for simulation and evaluation of
timetables, delays and infrastructure. Ph.D. Dissertation, KTH Royal Institute of Technology, Sweden, 2015.
[41] Middelkoop, D. & Bouwman, M., SIMONE: Large scale train network simulations.
Proceedings of the 2001 Winter Simulation Conference, Piscataway (NJ), USA, pp.
1042–1047, 2001.
[42] Sewcyk, B. & Kettner, M., Network Evaluation Model NEMO. Proceedings of the 5th
World Congress on Rail Research (WCRR 2001), Cologne, Germany, 2001.
[43] Marinov, M. & Viegas, J., A mesoscopic simulation modelling methodology for analyzing and evaluating freight train operations in a rail network. Simulation Modelling
Practice and Theory, 19(1), pp. 516–539, 2011.
[44] De Fabris, S., Longo, G., Medeossi, G. & Pesenti, R., Automatic generation of railway
timetables based on a mesoscopic infrastructure model. Journal of Rail Transport Planning & Management, 4(1-2), pp. 2–13, 2014.
[45] Radtke, A. & Bendfeldt, J., Handling of railway operation problems with RailSys. Proceedings of the 5th World Congress on Rail Research (WCRR 2001), Cologne, Germany, 2001.
[46] Quaglietta, E., A Microscopic Simulation Model for supporting the design of railway
systems: development and applications. Ph.D. dissertation, University of Naples Federico II, Italy, 2011.
[47] Quaglietta, E., Punzo, V., Montella, B., Nardone, R. & Mazzocca, N., Towards a hybrid mesoscopic-microscopic railway simulation model. Proceedings of the 2nd IEEE
International Conference on Models and Technologies for Intelligent Transportation
Systems (IEEE MT-ITS 2011), Leuven, Belgium, 2011.
[48] Botte, M., Di Salvo, C., Placido, A., Montella, B. & D’Acierno, L., A Neighbourhood
Search Algorithm for determining optimal intervention strategies in the case of metro
system failures. International Journal of Transport Development and Integration, 1(1),
pp. 63–73, 2017.
[49] Quaglietta, E., Corman, F. & Goverde, R.M.P., Impact of a stochastic and dynamic setting on the stability of railway dispatching solutions. Proceedings of the 16th International IEEE Conference on Intelligent Transportation Systems (IEEE ITSC 2013), The
Hague, The Netherlands, pp. 1035–1040, 2013.
[50] Quaglietta, E. & Punzo, V., Supporting the design of railway systems by means of a Sobol
variance-based sensitivity analysis. Transportation Research Part C, 34, pp. 38–54, 2013.
[51] D’Acierno, L., Placido, A., Botte, M., Gallo, M. & Montella, B. Defining robust recovery solutions for preserving service quality during rail/metro systems failure. International Journal of Supply and Operations Management, 3(3), pp. 1351–1372, 2016.
[52] D’Acierno, L., Placido, A., Botte, M. & Montella B., A methodological approach for
managing rail disruptions with different perspectives. International Journal of Mathematical Models and Methods in Applied Sciences, 10, pp. 80–86, 2016.
[53] Jacobs, J. Reducing delays by means of computer-aided ‘on-the-spot’ rescheduling,
WIT Transactions on The Built Environment, 74, pp. 603–612, 2004.
[54] Nash, A. & Huerlimann, D., Railroad simulation using OpenTrack. WIT Transactions
on The Built Environment, 74, pp. 45–54, 2004.