456
IEEE TRANSACTIONS ON ENGINEERING MANAGEMENT, VOL. 53, NO. 3, AUGUST 2006
Are Construction Disputes Inevitable?
Sai On Cheung and Tak Wing Yiu
Abstract—Many construction projects are of long-duration
and high value and foreseeing and planning for every eventuality
may be impossible. Engineers and managers are expected to
solve problems surfacing during the execution stage. Moreover,
problems blended with conflict are damaging and manifest as
disputes. The authors suggested that construction dispute can
be conceptualized as having three basic components: contract
provisions, triggering events and conflict. This conceptualization
fits nicely with fault tree (FT) framework that is used to evaluate
system failures. Furthermore, through the use of a hypothetical
case, a fuzzy FT model was employed to analyze the likelihood
of construction dispute. This research suggested that complex
project delivered in the traditional design then build approach,
construction dispute are bound to appear.
Index Terms—Construction disputes, fault tree model.
I. INTRODUCTION
EALING with dispute is part of portfolio of engineering
managers. In construction, due to the quantum involved
and disruption so caused, several industry reviews have raised
concern over the dispute “epidemic.” The voluminous publication on construction dispute is a good evidence of its significance. Newey [1] provided the invaluable data illustrating the
rising number of construction dispute reaching the court in the
United Kingdom. He advocated that prevention is better than
cure. Prevention of dispute can be achieved through cogent management such as prudent staffing policy, vigorous quality assurance plan, and realistic tender preparation and separating duties of design from contract administration. Engineers and managers can expect problems regularly in construction operations.
In fact, problem solving skill is one of the core skills required of
engineers and managers. Technical problems may be complex
but usually manageable. Disputes are different because of the
legal ramifications and personalities involved. As such, managing construction dispute is akin to conflict resolution. Despite its wide publicity, construction disputes are seldom defined, possibly because of its complex nature and intertwinted
underlying causes. This paper describes a conceptual model to
identify construction dispute. This conceptualization nicely fits
in a fault tree (FT) framework, an instrumental tool to analyze
system failure. Through the use of a hypothetical case, the likelihood of dispute occurrence is assessed.
D
II. IDENTIFICATION OF CONSTRUCTION DISPUTES
Dispute in construction can be attributed to the conflicting interest of the large number of participants. A more generalized
Manuscript received May 1, 2005; revised August 1, 2005. Review of this
manuscript was arranged by Department Editor J. K. Pinto. This work was
supported by the City University of Hong Kong Research Grant (Project No.
7001686).
The authors are with the Construction Dispute Resolution Research Unit,
Department of Building and Construction, City University of Hong Kong,
Kowloon, Hong Kong (e-mail:
[email protected]).
Digital Object Identifier 10.1109/TEM.2006.877445
treatment was forwarded by Diekmann [2] who suggested that
people, process and product are the main sources of construction
disputes. Rhys Jones [3] further identified ten main sources: 1)
management; 2) culture; 3) communications; 4) design; 5) economics; 6) tendering pressure; 7) law; 8) unrealistic expectations; 9) contracts; 10) workmanship. Mururu [4] described that
dispute is the formation of a position to maintain in conflict.
Brown [5] suggested that dispute can be viewed as a class or
kind of conflict that require resolution. Furthermore, according
to Hellard [6], construction dispute is the opposition of interests, values or objectives. While Spittler [7] added that construction dispute is linked with difference in perspectives, interests,
and agenda of human beings. Yate [8] examined construction
process in the light of transaction cost economics with the aim
to explain the high incidences of claims and dispute. He argued
that complex contracts are invariably incomplete due to bounded
rationality and uncertainty [9]. As a consequence of contractual
incompleteness, whenever events/contingencies occur ex post
which are not fully specified ex ante, one or both of the parties
may behave opportunistically. Such behavior predictably results
in conflict and disputes. Tillet [10] defined construction dispute
as the incompatibility of two (or more) people’s (or groups’) interests, needs, or goals. As they seek to maximize fulfillment of
their own interests, or needs, or achievement of their own bargaining or negotiating through compromise, one party may yield
to the other on that which is less important. When this happens,
the dispute is usually settled.
This was consistent with the view of Fenn [11] who described
that dispute requires resolution and is associated with distinct
justifiable issues. Similar proposition is also suggested by
Burton [12] who maintained that dispute is always negotiable.
Bristow [13] and Sykes [14] are also concerned with personality
and suggested that disputes are due to unrealistic expectation,
lack of team spirit and misunderstandings. Apparently, these
studies suggested that conflict is a prime driver of dispute.
Another line of analysis points to the subject matters that
are in dispute. Hewit [15] identified six types of construction
dispute; change of scope, change conditions, delay, disruption,
acceleration, and termination. Based on a review on the construction disputes that reached the Supreme Courts of New
South Wales and Victoria, Australia, in 1989 and 1990, Watts
and Scrivener [16] identified 59 categories of dispute with 117
sources. The 59 categories of dispute fall into the following
generic types; 1) Determination of the agreement; 2) Payment
related; 3) The site and execution of work; 4) Time related; 5)
Final certificate and final payment; 6) Tort related. Through
survey and case studies, Heath [17] identified seven main types
of construction dispute: 1) contract terms; 2) payments; 3) variations; 4) extensions of time; 5) nomination; 6) re-nomination;
7) availability of information. Similarly, Conlin [18] identified
payment, performance, delay, negligence, quality, and admin-
0018-9391/$20.00 © 2006 IEEE
CHEUNG AND YIU: ARE CONSTRUCTION DISPUTES INEVITABLE?
istration as headings of construction disputes. Kumaraswamy
[19] classified construction claims basing on their relative
significance in terms of magnitude and frequency. As such he
advocated that dispute causes were interwoven and could not be
isolated and controlled. Based on a literature review, interviews
and a questionnaire survey, the general types of construction
dispute were categorized in the order of perceived significance
as follows: 1) variation due to site conditions; 2) variations due
to client changes; 3) variations due to design errors; 4) unforeseen ground conditions; 5) ambiguities in contract documents;
6) variations due to external events; 7) interferences with utility
lines; 8) exceptional inclement weather; (9) delayed design
information; 10) delayed site possession.
On the other hand, Totterdill [20] focused specifically on the
contractual basis under which claims are submitted. The types of
technical, legal, and managerial dispute issues must have a contractual reference. Similarly, Semple [21] examined the types
of construction disputes with specific reference to the construction contract. The findings of that study suggested that site overhead, loss of productivity, loss of revenue, and financing costs
are the main types of construction dispute. Yate [8] pinpointed
that the main types of construction dispute arising from the contract document include: 1) variations; 2) ambiguities in contract documents; 3) inclement weather; 4) late issue of design
information/drawings; 5) delayed possession of site; 6) delay
by other contractors employed by the client (e.g. utility companies); 7) postponement of part of the project. Moreover, the
types of construction dispute source are also examined in specific areas such as adjudication and mediation. Sheridan [22]
conducted a survey for the Adjudication Reporting Centre and
categorizing dispute types settled by adjudication. The statistics showed that “valuation of variations,” “valuation of final account,” and “failure to comply with payment provisions” are the
major subject matters of dispute in adjudication. Brooker [23]
examined the types of disputes where mediation had been used.
A total of 233 construction mediations in U.K. were reported.
Disputes involving payment, delay, defect/quality and professional negligence occurred most often, which contributed 72%
of the reported cases. A similar study on construction mediation conducted in Hong Kong also found that variation, delay in
work progress, parties’ expectations and intraparties’ problem
were the significant types of dispute source [24].
While Spittler [7] showed that ambiguous contract documents, competitive/adversarial attitude and dissimilar perceptions of fairness by the participants are the main sources of
construction dispute, it is further suggested that if the interests
of the participants can be satisfied, disputes can be resolved
by managing the time, cost, and quality factors. Semple [21]
suggested that contract provision is an ingredient of dispute.
This study found that the most commonly encountered sources
of construction contract dispute are increase in work scope,
weather, restricted access, and acceleration. Furthermore,
Sykes [14] identified that construction disputes originate from
two main interrelated sources; construction contracts and
unpredictable events. It is a fact that construction works are
subject to many uncertainties. The daunting task in planning
for these uncertainties within the contract laid the seeds for
dispute. This may be the result of failing to address sources
457
of the uncertainties. More commonly though is the inclusion of contradicting provisions in an attempt to deal with
them. Mitropoulos [25] developed a model to illustrate the
development of disputes in construction industry. This model
applied the framework of Williamson [26] which combined the
effect of project uncertainty, contract, working relations and
problem solving effectiveness on the development of disputes
and explained how the combination of “environmental” and
“behavioral” factors had led to contractual problem. Finally,
the basic factors that drive the development of disputes are
identified; these include: 1) project uncertainty; 2) contractual
problems; 3) opportunistic behavior. Moreover, factors such as
contractors’ financial position, cost of conflict, and culture are
also identified as determining factors for dispute development.
Table I summarizes the identification of construction dispute
from literature as described.
III. CONSTRUCTION DISPUTE: TOWARD A CONCEPTUALIZATION
The above summarizes previous efforts in identifying construction disputes, moreover it is also noted that this is a lack
of a conceptual framework to describe construction dispute. It
is, therefore, proposed that construction dispute include three
basic ingredients: 1) Contract Provisions, 2) Triggering Events,
and 3) Conflict [57]. This is presented as a conceptual model
called “dispute triangle” as shown in Fig. 1. The details of these
three ingredients of construction disputes are described in the
following sections.
A. Relevant Contract Provision
Defining dispute typically emphasizes the existence of incompatibilities of need and value. This formulation of position
has to be somehow explicit and typically achieved by referencing to a provision in the contract (at least one). The existence
of a dispute is often crystallized through invoking the contract
machinery. Based on these theoretical definitions of construction dispute, its main source can broadly be regarded as the formation of clashes among the contractual parties. However, the
issue of “when a dispute is crystallized” seems not to be being
addressed. This can be recognized by referencing to the contract
machinery. In most forms of contract commonly used in Hong
Kong [27], [28], if the contractor is dissatisfied with the decision of the contract administrator, the contractor must convey
his dissatisfaction and assert his case. The assertion serves as
a declaration of a dispute in existence. Similarly in the U.K.,
under Clause 41 of the JCT 98 Conditions of Contract, a “dispute or difference” is triggered by serving a request for resolution by either one of the contractual parties. In Australia, the
Australian Standard form AS4000 [29] requires similar notice
of dispute under Clause 42.1:
“If a difference or dispute (together called a “dispute”) between the parties arises in connection with the subject matter
of the Contract, including a dispute concerning a Superintendent’s direction or a claim (in tort, under statue, for restitution
based on unjust enrichment or other quantum meruit or for rectification or frustration) or like claim available under the law
governing the Contract, then either party shall by hand or by
certified mail, give the other and the Superintendent a written
458
IEEE TRANSACTIONS ON ENGINEERING MANAGEMENT, VOL. 53, NO. 3, AUGUST 2006
TABLE I
IDENTIFICATION OF CONSTRUCTION DISPUTES
notice of dispute adequately identifying and provided details of
the dispute.” Hence, a dispute is evidenced by such a request.
B. Triggering Event
A construction problem manifests itself when errors are revealed. Changes and ineffective communication create bottlenecks and thereby inefficiency. Claims are the inevitable and
eventual outlet. The instigation of claims is typically upon certain happenings, called triggering events. The fundamental purpose of construction contract is to record a commercial agreement. This includes the delineation of the parties’ responsibility,
risk ownership, the performance required, and the approval procedures. Provisions for making adjustments are now a standard
feature in every construction contract, likewise, provisions for
adjudication.
CHEUNG AND YIU: ARE CONSTRUCTION DISPUTES INEVITABLE?
459
Fig. 1. The conceptual model of construction disputes: the dispute triangle
[57].
C. Sufficient Level of Conflict
In construction, the words dispute and conflict have been
used fairly loosely and almost as synonymous. However,
as discussed in the previous section, conflict is in fact an
underlying cause of dispute. In other words, dispute is the
manifestation of the underlying conflict(s). People are the principal resource of all construction projects [30]. Construction
professionals such as project managers, architects, engineers,
and quantity surveyors and the like are the key participants
of every construction project. They are typically drawn from
different organizations to form a project team. Each project
team is, thus, a mini-society with a complex set of interrelated
relationships requiring cooperation and collaboration from
conception to completion of the construction project. They
have different goals and needs, and each expect to maximize
their own benefits [31]–[33]. Because of these differences, an
environment flooded with conflict becomes inevitable [34],
[35]. Indeed, Conflict is a ubiquitous phenomenon, arising in all
aspects of social life [3]. It refers to the existence of a clash of
interests, values, actions, or direction [36], which arises when
two people or groups perceive their values are incompatible.
Tillet [10], in supporting this general depiction, relates conflicts
to deep human needs and values. Sometimes they are expressed
in problems or disputes, which may only be the superficial
manifestation of a conflict. In addition, the potential for conflict
is inherent in any contractual situation [37]. The use of standard
forms of contract is often criticized. Since many construction
projects are complex in nature, it is inevitable that contracts
governing each project are also complicated. The distinction
between conflict and dispute can also be discussed in the light
of their resolution. Burton [12] describes dispute as situation
where issues involved are negotiable, in which there can be
compromise, and which, therefore, do not involve consideration
of altered institutions and structures as in the case of conflict
resolution.
IV. OCCURRENCE OF DISPUTE AS A SYSTEM FAILURE
Construction projects are highly complex, involving interrelated activities like planning site operations, control, safety, and
management. Any major events or a series of minor events in the
project operation may create problems that could become construction disputes. A construction project can be described as
“in dispute” if a claim or assertion made by one party is rejected
by the other and that rejection is not accepted [5], [38]. Occurrence of construction dispute can be identified as a fault in the
construction process because it affects project performance. The
adversarial atmosphere between the owner and the contractor
Fig. 2. Illustration of an FT.
[3], [18], [39]–[43], undermines the cooperative environment
necessary for accomplishing project objectives [44]. It is a well
accepted view that dispute is detrimental as it often leads to program delay, increased tension, and damaging long-term business
relationships [45]. Resolving dispute through litigation is costly
in terms of the consumption of valuable human and financial
resources [46]. For example, professionally qualified staff will
need to contribute their time for the preparation of supporting
documents for the case. Such works may disrupt their normal
schedule. Hence, the associated hidden or consequential costs
will seriously disrupt the whole development project [47].
Notwithstanding that a number of studies reported [48]–[54]
that the use of appropriate contractual method and equitable risk
allocation can prevent the occurrence of costly disputes, the general consensus view remains that total elimination of dispute is
virtually impossible [6], [30], [35], [45], [55]. In the Section V,
the three ingredients of a construction dispute are presented in
an FT framework, an evaluation of the fuzzy likelihood of construction dispute is also described.
V. AN ASSESSMENT OF LIKELIHOOD: FT ANALYSIS (FTA)
FTA is a technique developed in the early 1960s to analyze the
safety of electro-mechanical system [56]. It is a “top-down” or
“backward” approach of finding the causes of an undesired result. FT models can be graphically presented to show the parallel
and sequential causes or events that contribute to a predefined
top undesired event. FTA, thus, depicts the logical inter-relationships of basic events that lead to a hazard. In an FT model,
a hazard is first specified, and the system is then analyzed in
the context of its environment and operation to find credible sequences of events that can lead to this hazard. A simple diagram
of an FT is shown in Fig. 2.
In an FT, the failure event, the “top event” is decomposed
into subevents that can further be decomposed if necessary until
“basic events” are reached. “Basic events” are events that require no further development. The top or head event is the loss,
460
IEEE TRANSACTIONS ON ENGINEERING MANAGEMENT, VOL. 53, NO. 3, AUGUST 2006
TABLE II
COMMON SYMBOLS USED IN FTA [57]
accident, or unwanted event, while the subevents are its contributors. The links in the FT identify the sequences that lead
to the top events. The tree permits the thinking through of the
possible causes of a loss and quantifies its probability of occurrence. The relationships between the events are represented by
logic gates—OR gates for union and AND gates of intersecor
can contribute
tion. For example in Fig. 2, either event
and
must be present if
to event , while both events
is to occur. Basic events can further be subgrouped
event
into events that requires no further development; events that are
evaluated separately and events that no further development is
possible because of the necessary information is unavailable.
Table II explains the common symbols used in an FTA.
VI. AN FT MODEL FOR CONSTRUCTION DISPUTES
Fig. 3. FT for occurrence of construction disputes [57].
In this paper, the top event is defined as construction dispute
and three subtrees are Contract Provisions, Triggering Events,
and Conflict, respectively. Fig. 3 shows the basic form of an FT
model of construction disputes [57].
A. Contract Provisions
Contract Provision is indicated as a basic event not to be developed further as almost all disputes have a contractual reference. Otherwise, the dispute resolution clause cannot be triggered. Triggering Events and Conflict are more complicated and
warrant further analyses with each considered in a subtree. The
event relationships of this FT model can be reduced to a logically equivalent form as follows:
(1)
where Construction Dispute is the intersection of Conflict, Contract Provisions, and Triggering Events.
B. Triggering Events
In the search for a list of Triggering Events that could be
used in the FT model, review of the causes of disputes is a
logical start. The studies by Heath [17], Conlin [18], and Rhys
Jones [3] in United Kingdom, Diekmann [2] in the USA, Watts
and Scrivener [16] in Australia, and Semple [21] in Canada had
been instrumental. These studies provided excellent groundwork for the identification of Triggering Events for the present
study. Through summarizing these inputs in a Hong Kong
context, Kumaraswamy [19], [58] investigated the root causes
of construction disputes based on data collected from 61 construction projects and 46 responses to a questionnaire survey
administered by him. The relative significance of the dispute
sources in Hong Kong was aligned accordingly. In addition,
Kumaraswamy [59] extended his study by studying the causes
and consequences of construction disputes. The study was
based on an opinion survey with 88 responses in Hong Kong. In
view of the comprehensiveness of the studies and the fact that
CHEUNG AND YIU: ARE CONSTRUCTION DISPUTES INEVITABLE?
461
TABLE III
THE TRIGGERING EVENTS
the evaluation of dispute likelihood planned for this study was
to be done in Hong Kong, the list of dispute causes provided
by Kumaraswamy [19], [58], [59] was used in the FT model.
Notwithstanding, to improve the conceptual underpinnings
of Kumaraswamy’s work, a structured framework suggested
by Watts and Scrivener [16] was adopted. In their study, by
reviewing the disputes in 56 cases, 59 different categories
of dispute are recognized within a total of 117 sources of
dispute. Kumaraswamy [19], [58], [59] further suggested that
the most frequent sources of dispute were generally related to
the nonperformance of contractual parties, payment and time.
The list of dispute causes were grouped in these three main
groups summarized in Table III. Its subtree is developed and
presented in Fig. 4. Their relationships can also be reduced to
the following mathematical format:
(2)
where Triggering Events are the union of Nonperformance, Payment, and Time.
Similarly, the mathematical format of each of the three subtrees is as follows.
1)
2)
3)
Fig. 4. Subtree of Triggering Events.
where
to
(Table III).
are the basic events of Triggering Events
462
IEEE TRANSACTIONS ON ENGINEERING MANAGEMENT, VOL. 53, NO. 3, AUGUST 2006
TABLE IV
THE CONFLICT
C. Conflict
People are the principal resources of all construction projects
[30]. Construction project team members, typically drawn
from different organizations, are likely to have different goals
and needs respective to their own positions. The presence of
conflicts is, therefore, not unusual in a project team. These
conflicts may eventually be expressed in the form of problems
or disputes. In construction industry, a dedicated study of
causes of conflict can be found in the work of Gardiner [60].
In this study, data was collected from construction projects to
investigate the causes, occurrence and effect of dysfunctional
conflicts within construction projects. It was concluded that the
role of people, rather than procedures or systems, is critical to
the germination and manifestation of dysfunctional conflicts in
construction projects. In sum, Gardiner [60] suggested that task
interdependency, differentiations of organizational background
and goals, communication obstacles, tensions, and personality traits are the most typical causes of conflict. With these
five branches, the “Conflict” subtree was formed. Pretorius
[61] also examined interpersonal and intrapersonal conflicts
within construction industry. Different psychological coping
techniques of professional personnel were available respective
to the organization structure. Furthermore, the relationships
between owners and contractors were examined by Harmon
[44] who suggested that owners and contractors form a social
group intertwisted with complex relationships, which require
cooperation and collaboration to coordinate time, resources
and communication. The existence of conflict will increase
the adversarial atmosphere between them. Several intervention
processes were proposed for breaking the conflict vicious cycle.
The study of Walton and Mckersie [62] also provided valuable
insight that helped to explain Personality Traits as a cause of
conflict. In this study, a model of organizational conflict and its
management that highlights the contextual determinants of organizational conflict is proposed. Similar concepts can also be
found in the fields of sociology and social psychology. Walton
and Mckersie [62] further suggested that certain personality
attributes, such as high authoritarianism, high dogmatism and
low self-esteem, can increase conflict behavior. Moreover,
constructive handling of these attributes would increase job
interest and reduce conflict level.
Table IV consolidates these findings within the five subsubtree. Fig. 5 gives the subtree of Conflict. Their relationships can
also be reduced to the following (3):
(3)
where Conflict is the union of Task Interdependency, Differentiations, Communication Obstacles, Tensions, and Personality
Traits.
Similarly, the mathematical format of each sub-subtree is as
follows.
1)
2)
3)
4)
5)
–
are the basic events of Conflict (Table IV).
VII. LIKELIHOOD OF CONSTRUCTION DISPUTES
Disputes are inevitable in construction as many would agree
[6], [30], [35], [45]. Proving this generally accepted view remains a challenge. The lack of data perhaps is the key stum-
CHEUNG AND YIU: ARE CONSTRUCTION DISPUTES INEVITABLE?
463
Fig. 5. Subtree of conflict.
which corresponds to the membership function as follows:
(5)
(6)
Fig. 6. Fuzzy probability—a trapezoidal representation.
bling block. The FT model of construction dispute accorded an
opportunity for a quantitative treatment on the likelihood of construction dispute. Once the probabilities of the events of the FT
become available, the occurrence of the top event, i.e. construction disputes can be computed. Very often, these probabilities
assessment can only be provided by project personnel and expressed in imprecise linguistic terms. The use of fuzzy sets evaluation in this study is, therefore, more amenable than discrete
probabilities [63].
Fuzzy probability may be viewed as a fuzzy set defined on
a probability space which expresses the subjective notion that
the probability of occurrence of an event is approximately equal
to certain value. The membership function is assumed to be a
trapezium as shown in Fig. 6.
Trapezoidal fuzzy sets are effective for modeling approximation concepts and facilitating the computation of fuzzy probabilities. Fuzzy probability attempts to capture the notion that the
value assigned to a probability is a fuzzy number, expressed as
a fuzzy set. A trapezoidal probability can be represented by
(4)
Tanaka [64] and Misra [65], [66] proposed the use of fuzzy
sets to analyze an FT for handling various uncertainties in data.
With respect to this concept, a degree of uncertainty can be allocated to each probability of failure. Similarly, the three ingredients of construction dispute, as analyzed in an FT model,
can be expressed as a fuzzy likelihood based on the assessment of project participants. Correspondingly, the logic gates
allow the computation of the fuzzy probability of dispute occurrence. Fuzzy Sets Theory offers a frame of analysis which could
model imprecision in input failure probabilities to be used in an
FTA. The estimation of top event probability (TEP) in fuzzy sets
would be termed as fuzzy top event probability (FTEP) and such
analysis would be termed as fuzzy FT analysis (FFTA) [67].
be the trapeTo assess the FTEP in the present study, let
zoidal fuzzy probability. For an event
being an output of
AND gate, with inputs
, the fuzzy probability of
an event
is given by
(7)
where
is a multiplication operator.
464
IEEE TRANSACTIONS ON ENGINEERING MANAGEMENT, VOL. 53, NO. 3, AUGUST 2006
Hence, the fuzzy probability for OR gate is
(8)
where
VIII. FUZZY LIKELIHOOD OF CONSTRUCTION DISPUTE
OCCURRENCE—AN ILLUSTRATION
A hypothetical case was developed and based on which the
fuzzy probabilities of occurrence of the basic events were solicited from construction professionals. The particulars of the
case used are as follows.
1) Procurement method: Lump sum fixed price contract.
2) Conditions of Contract: form of contract for use in private
developments in Hong Kong.
3) Project Duration: 28 mo.
4) Thirty-four storey commercial building with two levels of
basement.
5) The building is in reinforced concrete structure.
6) External walls are curtain walling.
7) Roofs are covered with waterproofing lining and concrete
tiling.
8) Internal wall finishes are generally cement/lime plaster
with painting and reconstituted granite; floor finishes are
generally of cement paving, granite, and mosaic tiling.
9) Building service installations are to be carried out by nominated subcontractors.
10) The design of the project had been completed sufficient for
the preparation of tender documents.
11) The tender had been awarded and the Main Contractor shall
be given possession of site in two weeks time.
This hypothetical project is chosen to reflect the typical complex projects delivered in Hong Kong. To assess the likelihood
of construction dispute, the respondents were asked to assess the
fuzzy probabilities of occurrence of the basic events. For trapezoidal fuzzy sets as indicated in (4), four assessments on the
probability of occurrence are required for each event. For ease
of apprehension by the respondents, the probability assessments
required are given as shown in Fig. 7. This figure was included
in the questionnaire to improve clarity.
Fig. 7 illustrates the four assessments required from each reand
refer to the lowest and the highest probaspondent.
bility that a particular basic event will occur, respectively.
and
are the most likely range of probability within which
the particular basic event will occur. A total of 24 Triggering
Events and 17 Conflict as shown in Tables III and IV were enlisted for the assessment of fuzzy probabilities. A total of 100
questionnaires were sent to construction professionals holding
senior positions in Hong Kong. The list was compiled by identifying key personnel from the government and professional
directories and web sites of companies. Fifty-six of them responded and returned the questionnaire. The response rate was
56%. Furthermore, 64% of the respondents have more than ten
years experience in construction. As for employing organization, 40% of the respondents work for Clients while the other
60% are employees of contracting organizations.
The average fuzzy probabilities of occurrence of Triggering
Events and Conflict are presented in Tables V and VI. The
Fig. 7. The probability assessment.
next task is to calculate the FTEP of the construction dispute
. Similar to (7), the FTEP for construction
dispute is given by
(9)
where
is a multiplication operator, where
FTEP of Construction Dispute;
FTEP of Triggering Events;
FTEP of Conflict.
To achieve this, the FTEP of Triggering Events and Conflict are
firstly calculated. Following the concept indicated in (8), the
equation is given by
(10)
where
is a multiplication operator; and
FTEP of Triggering Events;
FTEP of “Nonperformance;”
FTEP of “Payment;”
FTEP of “Time;”
–
fuzzy probabilities of basic events
of Triggering Events as described in
Table III.
CHEUNG AND YIU: ARE CONSTRUCTION DISPUTES INEVITABLE?
465
TABLE V
FUZZY PROBABILITIES OF OCCURRENCE OF TRIGGERING EVENTS
With the fuzzy probabilities of occurrence obtained in
Table V, the FTEP of the three basic events of Triggering
Events can be calculated as follows:
Hence
(11)
Based on the same concept, the equation for the calculation
of FTEP of Conflict is given in similar manner
(12)
(13)
(14)
466
IEEE TRANSACTIONS ON ENGINEERING MANAGEMENT, VOL. 53, NO. 3, AUGUST 2006
TABLE VI
FUZZY PROBABILITIES OF OCCURRENCE OF CONFLICT
where
is a multiplication operator; and
FTEP of Conflict;
FTEP of “Tensions;”
FTEP of “Task Interdependency;”
FTEP of “Personality Traits;”
FTEP of “Differentiations;”
FTEP of “Communication
Obstacles;”
to
Fuzzy probabilities of basic
events of Conflict as described in
Table IV.
CHEUNG AND YIU: ARE CONSTRUCTION DISPUTES INEVITABLE?
467
Fig. 8. Fuzzy probabilities of construction dispute occurrence.
Based on Table VI, the FTEP of the five basic events of Conflict can be calculated in the similar manner
(18)
(15)
(19)
Hence
(16)
(17)
Finally, the computational procedure for the top event
in FFTA can be started. The fuzzy prob-
468
IEEE TRANSACTIONS ON ENGINEERING MANAGEMENT, VOL. 53, NO. 3, AUGUST 2006
abilities of the basic events, Triggering Events and Conflict are
combined according to (9).
The Personality Traits group appears t be an area that would
cause more concern from an engineering management perspective. Personality Traits are inherent with the disputants and may
not be moulded easily. Furthermore, this attitudinal dimension
coupled with the divergence in interest can be damaging. As a
matter of fact, research on attitudes in relation to conflict resolution has been topical [71]–[74].
X. CONCLUSION
IX. DISCUSSION
Based on the above calculations, the probability of occurrence of the top event, i.e., construction dispute, is between
0.997 and 1.000 with the most likely range as [1.000, 1.000].
This likelihood assessment is based on a hypothetical construction project that exemplifies the complex developments delivered in a traditional design then build approach in Hong Kong.
Therefore, the finding that construction dispute is inevitable for
complex construction project has to be read in the light of these
assumptions. The literal interpretation of this finding is that construction dispute will inevitably occur in the project. In the beginning sections of this study, it is highlighted that although
most participants in the construction industry share the view that
construction disputes will occur in complex project [6], [30],
[35], [45]. This study provides an ample empirical support that
built on a well-established analytical framework, the FT model,
to develop a widely accepted view.
The inevitability of construction disputes is in fact gives a
positive direction to construction practitioners. This suggests
that they should be proactive in dispute management. Having
an efficient dispute management approach is essential to prevent dispute from escalating. This study would provide the necessary theoretical basis for construction dispute studies. Practitioners and academics shall highlight the concept of “prevention
is better than cure” in terms of two main issues: 1) The development of innovative dispute resolution mechanisms to be used
to achieve effective settlement; 2) The use of appropriate contractual method and equitable risk allocation to prevent the occurrence of costly disputes.
In addition, Fig. 8 presents the fuzzy probabilities of occurrence of the three groups of Triggering Events are all fairly high.
Even the lowest probability of happening for all three groups is
above 0.80. Nevertheless, an interesting observation is that Payment related Triggering Events give the highest probability of
occurrence with “Argument on the prolongation costs claimed
by main contractor” topped the contributor list (Table V). This
is very true in Hong Kong and seemingly also common in other
part of the world [59], [68].
The Conflict subtree also provided some inspiring research
pointers. In this subtree, Differentiations and Personality Traits
mark the highest fuzzy probabilities of occurrence. Differentiations highlight the divergence in interests of the project
team members. To this ends, the construction industry has
initiated the use of cooperative contracting such as partnering
and strategic alliancing as means to align the interest of project
team members. Some success stories have been reported in
Hong Kong [69]–[71].
Researchers in construction dispute have largely focused on
the legal dimension of the subject. In the study presented in
this paper, an analytical approach was advocated for the conceptualization of construction disputes. Construction disputes
are characterized by the co-existent of three ingredients; Contract Provision, Triggering Events, and Conflict. By considering
the occurrence of construction dispute analogically as a system
failure, the three dispute ingredients are framed in an FT model,
with which a fuzzy probabilities evaluation of construction dispute occurrence was completed basing on a hypothetical project
with features commonly founded in complex project delivered
in a traditional design then build approach in Hong Kong. The
results indicated that the occurrence likelihood of construction
disputes lies within the range of 0.997 to 1.000. This result supports the general accepted views that in complex construction
project, disputes are inevitable. This points to the need for construction professionals to exercise proactive dispute management. This would include developing skills to avoid dispute and
where dispute materializes, to resolve them through assisted or
unassisted negotiations. This is because negotiation is considered to be the Best Alternative To a Negotiated Agreement. In
addition, payment related triggering events, divergence in interest and personality traits are found to be the three key contributors to dispute occurrence.
ACKNOWLEDGMENT
The authors would like to express their appreciations to the
constructive comments of the reviewers.
REFERENCES
[1] J. Newey, “The construction industry,” in Proc. 1st Int. Construction
Conflict Management and Resolution Conf., 1992, pp. 21–24.
[2] J. Diekmann, M. Girard, and N. Abdul-Hadi, “Disputes potential index:
a study into the predictability of contract disputes,” in Construction
Industry Institute, Source Document 101. Austin, TX: Univ. Texas,
1994.
[3] S. Rhys Jones, “How constructive is construction law?,” Construction
Law J., vol. 10, no. 1, pp. 28–38, 1994.
[4] N. Mururu, “Anatomy of a dispute,” Arbitration, pp. 262–264, Nov.
1991.
[5] H. Brown and A. Marriott, ADR Principles and Practice. London,
U.K.: Sweet and Maxwell, 1999.
[6] R. B. Hellard, Managing Construction Conflict. Harlow, U.K.:
Longman Scientific Tech., 1987.
[7] J. R. Spittler and G. H. Jentzen, “Dispute resolution: managing construction conflict with step negotiations,” AACE Int. Trans., pp. D.9.
1–D.9.10, 1992.
[8] D. J. Yates, Conflict and Dispute in the Development Process:
A Transaction Cost Economic Perspective [Online]. Available:
http://business2.unisa.edu.au/prres/Proceedings/Proceedings1998/Papers/Yates3Ai.PDF 1998
CHEUNG AND YIU: ARE CONSTRUCTION DISPUTES INEVITABLE?
[9] O. E. Williamson, Markets and Hierarchies: Analysis and Antitrust Implication. New York: Free Press, 1975.
[10] G. Tillet, Resolving Conflict: A Practical Approach. Sydney, Australia: Sydney Univ. Press, 1991.
[11] P. Fenn, D. Lowe, and C. Speck, “Conflict and dispute in construction,”
Construction Manag. Econ., vol. 15, no. 6, pp. 513–518, 1997.
[12] J. Burton, Conflict: Resolution and Prevention. New York: St.
Martin’s Press, 1990.
[13] D. Bristow and R. Vasilopoulos, “The new CCDC2: facilitating dispute
resolution of construction projects,” Construction Law J., vol. 11, no.
2, pp. 95–117, 1995.
[14] J. Sykes, “Claims and disputes in construction,” Construction Law J.,
vol. 12, no. 1, pp. 3–13, 1996.
[15] Hewit, Winning Construction Disputes—Strategic Planning for Major
Litigation. London, U.K.: Ernst and Young, 1991.
[16] V. M. Watts and J. C. Scrivener, “Review of Australian building disputes settled by litigation,” Building Res. Inf., vol. 21, no. 1, pp. 59–63,
1993.
[17] B. C. Heath, B. Hills, and M. Berry, “The nature and origin of conflict
within the construction process,” in Proc. CIB TG15 Conf., 1994, pp.
35–48.
[18] J. Conlin, D. A. Lanford, and P. Kennedy, The sources, Causes, and
Effects of Construction Disputes: A Research Project Construction Industry Board, London, U.K., CIB Rep. 0254-4083, 1996.
[19] M. M. Kumaraswamy, “Common categories and causes of construction
claims,” Construction Law J., vol. 13, no. 1, pp. 21–34, 1997.
[20] B. W. Totterdill, “Does the construction industry need alternative dispute resolution? The opinion of an engineer,” Construction Law J., vol.
7, no. 3, pp. 189–199, 1991.
[21] C. Semple, F. Hartman, and G. Jergas, “Construction claims and disputes: cause and cost/time overruns,” J. Construction Eng. Manag., vol.
120, no. 4, pp. 785–795, 1994.
[22] P. Sheridan, “Claims and disputes in construction,” Construction Law
J., vol. 12, no. 1, pp. 3–13, 2003.
[23] P. Brooker, “Construction lawyers’ attitudes and experience with
ADR,” Construction Law J., vol. 18, no. 2, pp. 97–116, 2002.
[24] T. W. Yiu and S. O. Cheung, “Significant dispute sources of construction mediation,” in Proc. 1st Int. Conf. World of Construction Project
Management, Toronto, ON, Canada, 2004, pp. 596–604.
[25] P. Mitropoulos and G. Howell, “Model for understanding, preventing
and resolving project disputes,” J. Construction Eng. Manag., vol. 127,
no. 3, pp. 223–231, 2001.
[26] O. E. Williamson, “Transaction cost economics: the governance of contractual relations,” J. Law Econ., vol. 56, pp. 73–104, 1979.
[27] Hong Kong Institute of Architects, “Agreement & schedule of conditions of building contract for use in Hong Kong,” Standard Form of
Building Contract, Private Edition—With Quantities 1978.
[28] Hong Kong Government General Conditions of Contract for Use in
Building Works 1999 edition.
[29] General Conditions of Contract, Australian Standard, AS 4000—1997,
1997.
[30] D. A. Langford, P. Kennedy, and J. Somerville, “Contingency management of conflict: analysis of contract interfaces,” in Proc. !st Int.
Construction Conflict Management and Resolution Conf., U.K., 1992,
pp. 151–161.
[31] A. R. Cherns and D. T. Bryant, “Studying the client’s role in construction management,” Construction Manag. Econ., vol. 2, pp. 177–184.
[32] R. Newcombe, “Empowering the construction project team,” Int. J.
Project Manag., vol. 14, no. 2, pp. 75–80, 1996.
[33] A. Walker, Project Management in Construction, 2nd ed. Oxford,
U.K.: Blackwell Scientific, 1989.
[34] A. G. Butler, “Project management: a study in organizational conflict,”
Acad. Manag. J., vol. 16, pp. 84–101, 1973.
[35] M. Smith, “Facing up to conflict in construction,” in Proc. UMIST
Conf., 1992, pp. 120–125.
[36] E. De Bono, Conflicts: A Better Way to Resolve Them. New York:
Penguin Books, 1991.
[37] P. Hibberd and P. Newman, ADR and Adjudication in Construction
Disputes. Malden, MA: Blackwell, Oxford, 1999.
[38] M. M. Kumaraswarmy and K. Yogeswaren, “Encouraging conflicts,
discouraging disputes and managing claims,” NICMAR J. Construction
Manag., vol. 12, pp. 15–30, 1997.
[39] G. J. Conlin, D. A. Langford, and P. Kennedy, “The relationship between construction procurement strategies and construction contract
disputes,” in Proc. CIB W92 ’North meet south‘ Procurement Systems
Symp., R. G. Taylor, Ed., Durban, South Africa, 1996, pp. 66–82.
469
[40] D. Max, “ADR in the construction industry: continuing the development of a more efficient dispute resolution mechanism,” Ohio State J.
Dispute Resolution, vol. 12, p. 463, 1997.
[41] D. Arditi, F. E. Oksay, and O. B. Tokdemir, “Predicting the outcome
of construction litigation using neutral networks,” Comput.-Aided Civil
Infrastructure Eng., vol. 13, pp. 75–81, 1998.
[42] R. H. Steen and R. J. McPherson, “Resolving construction disputes out
of court through ADR,” J. Property Manag., vol. 65, no. 5, 2000.
[43] J. Lewis, D. W. Cheetham, and D. J. Carter, “Avoiding conflict by risk
management—the role of the client’s project manager,” in Proc. 1st Int.
Construction Manag. Technol., P. Fenn and R. Gameson, Eds., 1992,
pp. 72–94.
[44] K. M. Harmon, “Conflicts between owner and contractors: proposed
intervention process,” J. Manag. Eng., vol. 19, no. 3, pp. 121–125.
[45] S. O. Cheung and C. H. Suen, “A multi-attribute utility model for dispute resolution strategy selection,” Construction Manag. Econ., vol.
20, pp. 557–568, 2002.
[46] G. Xavier, “Construction claims and related disputed—a Malaysian
perspective,” Construction Law J., vol. 16, no. 3, pp. 172–186, 2000.
[47] R. F. Fellows, “Karming conflict,” in Proc. 1st Int. Construction Management Technology Conf., P. Fenn and R. Gameson, Eds., 1992, pp.
122–127.
[48] T. B. Treacy, “Use of alternative dispute resolution in the construction
industry,” J. Manag. Eng., pp. 58–63, Jan./Feb. 1995.
[49] J. A. Fisher, “Prevention is better than cure, or how to avoid costly
mistakes in Hong Kong construction contracts,” Int. Construction Law
Rev., pp. 342–348, Jul./Oct. .
[50] R. H. Turner, “Avoidance and resolution of construction disputes- prior
to and during the construction process,” Int. Construction Law Rev.,
vol. 11, pp. 384–394, 1994.
[51] O. A. Currie, “Avoiding, managing and winning construction disputes,”
Int. Construction Law Rev., vol. 8, no. 3, pp. 344–369, 1991.
[52] M. O. Jannadia, S. Assaf, A. A. Bubshait, and A. Naji, “Contractual
methods for dispute avoidance and resolution (DAR),” Int. J. Project
Manag., vol. 18, pp. 41–49, 2000.
[53] L. S. Jones, “Zero-based contracts for dispute avoidance,” in Proc. Construction Congr., 1991, pp. 710–714.
[54] R. K. Allen, “Dispute avoidance and resolution for consulting engineers. American Society of Civil Engineers,” Manuals and Reports on
Engineering Practice 43314, pp. 1–81, 1993.
[55] S. O. Cheung and C. H. Suen, “The contribution of the third party neutral towards amicable construction dispute resolution,” Int. Construction Law Rev., vol. 19, no. 1, pp. 79–86, 2002.
[56] W. E. Vesely, F. F. Goldberg, N. H. Roberts, and D. F. Haasl, Fault
Tree Handbook U.S. Nuclear Regulatory Commission nureg-0492 ed.
, 1981.
[57] S. O. Cheung, “Project dispute resolution satisfaction of construction
clients in Hong Kong,” Ph.D. thesis, Univ. Wolverhampton, Wolverhampton, U.K., 1998.
[58] M. H. Kumaraswamy, “Conflicts, claims and disputes in construction,”
Eng., Construction, Architectural Manag., vol. 4, no. 2, pp. 95–111,
1997.
[59] ——, “Consequences of construction conflict: a Hong Kong perspective,” J. Manag. Eng., vol. 14, no. 3, pp. 66–74, 1998.
[60] D. P. Gardiner and J. E. L. Simmons, “Conflict in small and medium
sized projects: case of partnering to the rescue,” J. Manag. Eng., vol.
14, no. 1, pp. 35–40, 1998.
[61] F. I. H. Pretorius and R. G. Taylor, “Conflict and individual coping
behaviour in informal matrix organizations within the construction industry,” Construction Manag. Econ., vol. 4, pp. 87–104, 1986.
[62] R. E. Walton and R. B. McKersie, A Behavioral Theory of Labor Negotiations. New York: McGraw-Hill, 1965.
[63] J. J. Buckley, Fuzzy Probabilities—New Approach and Applications.
New York: Physica-Verlag, 2003.
[64] H. Tanaka, L. T. Fan, F. S. Lai, and K. Toguchi, “Fault tree analysis
by fuzzy probability,” IEEE Trans. Reliability, vol. R-32, no. 5, pp.
455–457, Dec. 1983.
[65] K. B. Misra and G. G. Weber, “Use of fuzzy set theory for level-I
studies in probabilistic risk assessment,” Fuzzy Set Theory Syst., vol.
37, pp. 139–160, 1990.
[66] ——, “A new method for fuzzy fault tree analysis,” Microelectron. Reliability, vol. 29, pp. 195–216, 1989.
[67] A. W. Deshpande and P. Khanna, “Fuzzy fault tree analysis: case
studies,” in Reliability and Safety Analyses Under Fuzziness, T. Onisawa and J. Kacprzyk, Eds. Heidelberg, Germany: Physica-Verlag,
1995.
470
IEEE TRANSACTIONS ON ENGINEERING MANAGEMENT, VOL. 53, NO. 3, AUGUST 2006
[68] S. O. Cheung, S. T. Ng, and W. S. Sin, “A fuzzy set model for construction dispute evaluation,” Construction Innovation, vol. 1, pp. 117–127,
2001.
[69] S. P. Wong and S. O. Cheung, “Trust in construction partnering: views
from parties of the partnering dance,” Int. J. Project Manag., vol. 22,
no. 6, pp. 437–446, 2004.
[70] R. Bayliss, S. O. Cheung, C. H. Suen, and S. P. Wong, “Effective partnering tools in construction: a case study on MTRC TKE contract 604
in Hong Kong,” Int. J. Project Manag., vol. 22, no. 3, pp. 253–263,
2004.
[71] S. P. Wong and S. O. Cheung, “Structural equation model of trust and
partnering success,” J. Manag. Eng., vol. 21, no. 2, pp. 70–80, 2005.
[72] J. H. Ock and S. H. Han, “Lessons learned from rigid conflict resolution
in an organization: construction conflict case study,” J. Manag. Eng.,
vol. 19, no. 2, pp. 83–89, 2003.
[73] P. Awakul and S. O. Ogunlana, “The effect of attitudinal differences on
interface conflict on large construction projects the case of the Pak Mun
Dam project,” Environ. Impact Assessment, vol. 22, no. 4, pp. 311–335,
2002.
[74] T. W. Yiu and S. O. Cheung, “A catastrophe model of construction
conflict behavior,” Building Environ., to be published.
Sai On Cheung received the Ph.D. degree from
the University of Wolverhampton, Wolverhampton,
U.K., in 1998
He has extensive practical experience in handling
contractual matters and claims. Building on these,
he has been actively conducting research studies in
construction contracting. These include: 1) investigating ways to avoid disputes; 2) evaluating project
dispute status; 3) assessing dispute resolution satisfaction level of disputants; 4) assessing the project
dispute resolution satisfaction level of disputants;
View publication stats
5) designing dispute resolution processes; 6) developing selection models for
dispute resolution process; 7) investigating the relationship between negotiation style and negotiation outcome; and 8) investigating the effectiveness of
mediators’ tactics. He has published extensively, in the area of construction
dispute resolution.
Tak Wing Yiu received the Ph.D. degree from the
City University of Hong Kong, Hong Kong, in 2005.
He is actively involved in construction dispute
resolution researches. His current research interests
are construction negotiation and mediation. These
includes: investigating the dynamic change in
dispute resolution behavior; investigating the most
common dispute resolution method—negotiation;
developing models for construction mediation.