We are IntechOpen,
the world’s leading publisher of
Open Access books
Built by scientists, for scientists
4,800
123,000
135M
Open access books available
International authors and editors
Downloads
Our authors are among the
154
TOP 1%
12.2%
Countries delivered to
most cited scientists
Contributors from top 500 universities
Selection of our books indexed in the Book Citation Index
in Web of Science™ Core Collection (BKCI)
Interested in publishing with us?
Contact
[email protected]
Numbers displayed above are based on latest data collected.
For more information visit www.intechopen.com
3
Mechanising, Robotising and Automating
Construction Processes
Frans van Gassel and Ger Maas
Eindhoven University of Technology
The Netherlands
1. Introduction
Building objects are produced by people who perform the necessary tasks using equipment.
On the basis of preconditions, the process designer can have a particular task performed by
a specific combination of a worker and equipment. The worker performs a number of tasks
and the equipment does the rest.
Nowadays, newer, more suitable technologies are becoming available. In order to use these
technologies successfully, it is essential to have a good understanding of the work processes
of an object that is to be built.
The terms mechanising, robotising and automating are defined in order to be able to
describe the physical, cognitive and organising tasks in relation to the possible use of
human-machine technologies. It sometimes makes more sense to redesign the building
products to achieve a more effective and efficient building process using workers and
additional tools or machines.
Mechanising, robotising and automating construction processes is necessary in order to
reduce production times and costs, improve working conditions, avoid dangerous work,
allow work to be performed that people cannot do and increase performance. For the
construction industry, more and more human-machine technologies are becoming available,
but their use does not automatically lead to more effective and efficient construction
processes.
Building expertise is the domain of the professional builder and not of the process engineers
who look to apply the technologies in the construction industry. The implicit know-how of
the builders and construction process designers regarding the execution of construction
processes has to be made explicit. The builder’s implicit know-how comprises knowing how
to choose the sequence of the building elements, how to join the elements, where the
elements fit in the construction as a whole and how they have to be positioned.
This chapter contains a systematic definition of the terms mechanising, robotising and
automating and explains an analysis method with which a worker-equipment system that
produces better performance can be designed.
2. An automated construction system
In Japan, construction process designers have upscaled the worker-equipment system into a
cohesive building production system to find solutions to problems such as the aging of
www.intechopen.com
44
Robotics and Automation in Construction
workers, a higher training level for employees and the low numbers of young people
looking for jobs in construction (Obayashi, 1999). A building production system can be
defined as a technical installation that assembles construction elements into a building. In
this context, an installation can be seen as a collection of people, tools and machines,
computers and telecommunications equipment that may all be working together. If we
couple this definition to the various tasks required for the performance of a building activity
– physical, cognitive and organising tasks – we see production systems subdivided into
traditional, mechanised, robotised and automated building production systems. Table 1
shows the relationships between the different parameters using human-machine
technologies.
Construction
system type
Physical tasks
Cognitive tasks
Organising tasks
Traditional
Workers
Equipment
Workers
Workers
Equipment
Workers
Workers
Equipment
Computers and software.
Means of communication.
Workers
Computers and software.
Means of communication.
Computers and
software.
Means of
communication.
Mechanised
Robotised
Automated
Equipment
Table 1. Types of construction systems in relation to various tasks (Van Gassel, 2003).
An automated construction system consists of an assembly area where building work can be
carried out regardless of the weather, an automatic hoisting system for the assembly area, an
automatic vertical and horizontal conveyor system and a centralised information system to
execute and manage organisation tasks (see Fig. 1).
Fig. 1. An automated construction system in Japan.
3. Developments in construction processes
Developments in construction processes are the result of a set of changing circumstances
and conditions, such as enormous migration into the cities. The forecast is that in 2015, 55%
of the world’s population will live in urban areas. These metropolises impose their own
www.intechopen.com
45
Mechanising, Robotising and Automating Construction Processes
requirements on construction management and production systems. These changes
encourage the development of technologies to ensure the creation of a process that leads to
improved performance for the client. These developments are based on an analysis of the
Status Report issued in 2001 by the CIB Task Group TG27 ‘Human-Machine Technologies
for Construction Sites’ (Maas & Van Gassel, 2001) and of the proceedings of the ISARC2003
Symposium: The Future Site (Maas & Van Gassel, 2003).
When all building production is ultimately designed to lead to improved performance and a
satisfied client, it is always difficult to keep sight of the overall picture and this final goal.
The overview in Fig. 2 shows the relationship between the various aspects of automation in
construction: construction management, construction engineering and performance
management help the process designers to meet the needs of the client and society.
Construction
Management
• Risk management
• Failure costs
• Value
management
• Danger work and
processes
• Uncertainty
• Benchmarking
• Safety and health
Construction Engineering
• Industrial production
• Sustainable
construction
• Constructability
• Mass customisation
• Modular construction
• Renovation
Performance
Management
• Co-oporation and
partnering
• Strategic planning
• Collaborative design
and engineering
• Supply chain
management
• Design and build
• Lean construction
management
Applying Human Machine Technologies
Performances for client and society
• Satisfaction
• Total cost of ownership
• Available information
• Communication
• Waste and reuse
• Deconstruction
Fig. 2. Relationship between management, engineering and performance (based on Maas &
Van Gassel, 2005).
The building assignment will focus on metropolises, which sets specific requirements for
performance management, construction management and construction engineering.
Clients need individual treatment and a specific approach designed to solve their problem and
meet their demands. They are less concerned with the size of the investment, but are becoming
more and more interested in the total cost of ownership and life cycle costs. Nowadays, clients
are less concerned with the structure itself. They pay more attention to its functional use,
primarily encouraged by the use of information and communication technology in the projects.
www.intechopen.com
46
Robotics and Automation in Construction
Construction engineering has been changed by the application of more industrial
production, sustainable construction, mass customisation, and modular construction to
improve constructability.
Construction management has to deal with health and safety, uncertainty and danger.
Developments are taking place in risk management and value management, supported by
partnering, collaborative design and supply chain management.
These developments demonstrate that there is plenty of room for improvement in all
process elements of construction projects in metropolises (Maas & Van Gassel, 2005).
4. Worker-equipment system
To produce a building object, three types of task have to be performed: (i) provide strength
and energy (physical tasks), (ii) receive and issue information (cognitive tasks) and (iii)
make decisions (organising tasks). The human body has a number of suitable parts and
society has developed equipment designed to perform the tasks more effectively (see Table
2). As human beings, our speed and power are limited to what equipment can do, but
people are far more sensitive to input and have a large, versatile memory.
Tasks
Provide strength and
energy
Human body
Movement system:
muscles
lungs
Senses:
eyes
ears
voice
hands
Receive and issue
Information
Make decisions
Thought system:
brain
memory
Equipment
Power tools:
energy sources
transmissions
Telecommunications tools:
scanner
microphone
monitor
keyboard
Computer equipment:
computer
software
artificial intelligence
Table 2. Human body parts and equipment to fulfil tasks.
To perform specific tasks, the process designer chooses the right combination of worker and
equipment. Describing such a combination is possible using the basic diagrams of the
worker-equipment system (see Fig. 3 and 4).
Control
Initial
stage
Production
tasks
Workers &
Equipment
Fig. 3. Basic diagram of the process.
www.intechopen.com
Final
stage
47
Mechanising, Robotising and Automating Construction Processes
Initial
stage
Tasks
Worker
Tasks
Equipment
Final
stage
Fig. 4. Basic diagram of the worker-equipment system.
The diagrams used here are based on system analysis. Materials are transformed by the
worker-equipment system from an initial to a final situation (Maas, 1991). That part of the
tasks to be performed by the equipment and that by the worker are represented by the size of
the surface of the rectangle. The rectangles can be divided into activities that can take place in
sequence and/or at the same time, so a building activity can be divided into subactivities.
5. Mechanisation and robotisation concepts
The mechanisation concept is defined on the basis of the diagram in Fig. 4: ‘Mechanisation is
the shift of tasks from worker to equipment’. The concept is shown in a diagram in Fig. 5.
Tasks Worker
Initial
stage
Tasks
Equipment
Mechanisation
Tasks
Worker
Final
stage
Mechanising
brick laying
Tasks Equipment
Fig. 5. The mechanisation concept.
Robotisation is a special type of mechanisation in which all tasks are shifted from the
worker to the equipment (see Fig. 6). Control and support activities are not included in these
tasks, because they are not directly related to the specific production activity.
6. The mechanisation graph
The tasks that workers and equipment carry out can be divided into energy tasks and
control tasks.
Three situations are considered for the performance of energy tasks:
www.intechopen.com
48
1.
2.
3.
Robotics and Automation in Construction
the equipment does not supply energy
the equipment supplies a certain amount of driving energy
the equipment supplies all the driving energy and the worker only has to operate the
controls.
Tasks
Worker
Initial
stage
Tasks
Equipment
Robotization
Final
stage
Robotising building
blocks
Tasks Equipment
Fig. 6. The robotisation concept.
Driving energy means, for example, the rotating and linear motion of a drill and the supply
of energy necessary to hold the equipment in a steady position. The latter can be achieved
by placing the equipment on a stand.
The classification of control tasks is based on Guo and Tucker’s machine line arrangement
(Guo & Tucker 1993). This classification comprises the following levels: hand tools,
manually controlled devices, telecontrolled devices, pre-programmed devices and cognitive
robots. At the beginning of the line, all tasks are carried out by people, and at the end of the
line by machines.
On a graph, energy tasks are placed on the vertical axis and control tasks on the horizontal
axis, resulting in a mechanisation graph (see Fig. 7).
A worker-equipment system or elements of such a system can be placed in the squares of
the graph.
Examples:
A. The laying of bricks with the aid of a mason’s trowel.
B. The drilling of a hole in a wall with an electric drill.
C. The drilling of a hole in a wall with an electric drill that has been placed on a guide and
that is started electrically.
D. The riding of an operator on an excavator.
E. The moving of loads with a crane that is remotely controlled.
F. The laying of bricks by a robot that places bricks and mortar according to instructions.
G. The digging of a trench in the ground by an intelligent excavator that can make
decisions on the basis of observations.
www.intechopen.com
49
Mechanising, Robotising and Automating Construction Processes
Energy task
equipment
Equipment
supplies all
energy
D
100%
Equipment
supplies a
certain
amount of
driving
energy
E
F
G
C
B
0%
Equipment
does not
supply
energy
Control task
equipment
A
Hand
tools
Manually
controlled
devices
Tele
controlled
devices
Pre programmed
devices
Cognitive
robots
Fig. 7. Mechanisation graph.
7. Mechanisation phases
It is now possible to indicate the mechanisation phases on the mechanisation graph.
The following phases can be distinguished:
1. optimisation of tools
2. use of drives
3. use of guides
4. use of control equipment
5. use of remote control
6. use of computers
7. use of artificial intelligence
The mechanisation phases are represented in the mechanisation graph in Figure 8. The
phases above are based on the mechanisation of existing situations. Entirely new production
processes, however, can be designed as well. Here, it is only possible to represent the end of
the mechanisation phase on the graph.
An increasing degree of technology is necessary in order to complete the mechanisation
phases. This requires knowledge of:
•
Materials and construction products
•
What workers can do (ergonomics)
•
Drive technology, guides and manipulators
•
Machine controls, remote controls and programming technologies
•
Sensors and artificial intelligence
www.intechopen.com
50
Robotics and Automation in Construction
A chain of mechanisation phases can also be represented on the graph. The smoothing of a
poured concrete floor is used as an example. Traditionally, these concrete floors were
smoothed with a hand trowel, which involved manually moving the power trowel over the
floor. The next mechanisation phase enabled the floor-layer to sit on the machine, so that
only operation of the controls was necessary. Next, the machine was equipped with remote
control. The machine was then provided with computer controls that can finish the floor
according to programmed instructions. The subsequent step would be to provide computer
controls that make observations and a number of decisions on the basis of these
observations.
Energy task
equipment
Use of remote
control
Use of
computers
Use of artificial
intelligence
Equipment
supplies all
energy
Use of control
equipment
100%
Equipment
supplies a
certain
amount of
driving
energy
Use of
guides
Use of
drives
0%
Equipment
does not
supply
energy
Optimization
of tools
Hand
tools
Manually Tele
Pre procontrolled controlled grammed
devices
devices
devices
Control task
equipment
Cognitive
robots
Fig. 8. Mechanisation phases.
A distinction can be made between the mechanisation of production processes of existing
products and those of modified or new products. Mechanisation of existing products is the
mechanisation of traditional production processes carried out by craftsmen, such as
masonry, plastering and carpentry. Generally it is quite possible to mechanise the energy
task, while the mechanisation of control tasks is highly complex.
Just analyse the laying of bricks by a bricklayer and try to put these activities in the
operating program of a machine. The mechanisation of modified or new products has more
of a chance of being put into practice.
8. Example
As an example, the basic diagram is applied to a production process in which large, heavy
wall elements are taken from a lorry and mounted on a façade. This can be divided into a
number of constituent processes: attachment of the element to the hoisting hook,
www.intechopen.com
51
Mechanising, Robotising and Automating Construction Processes
transportation to the location where it is to be mounted and turning the element to the
desired position (see Fig. 9). The tasks performed by equipment and those performed by
people can be described (see Fig. 10).
Crane
Transportation to the
assembly
location
Turning the
element
Building
Worker B
Worker A
Rope
Attachment of
element to the
hoisting hook
Wall element
on lorry
Wall element
on a facade
Fig. 9. The mounting of large wall elements.
With the help of technologies, some tasks of worker A and B can be done by equipment (see
Fig. 10). For instance, the wall element can be guided automatically by equipment between
the hoist hook and the wall element (see Fig. 11 and 12).
Wall element
on lorry
Tasks
Worker
Worker A
task 1
task 2
Tasks
Equipment
Crane:
task 1
task 2
Worker B
task 1
task 2
Fig. 10. Analysing the tasks before mechanising.
www.intechopen.com
Wall element
on a facade
52
Robotics and Automation in Construction
Wall element
on lorry
Tasks
Worker
Tasks
Equipment
Worker A
task 1
task 2
Crane
task 1
task 2
Worker B
task 1
task 2
Machine
task 1
task 2
task 3
Wall element
on a facade
Fig. 11. Desired situation after mechanising.
Fig. 12. Mechanizing the position of a wall element by special equipment.
9. References
Van Gassel, F. and G. Maas, (2001) International Status Report on Aspects of Future Sites, CIB TG27 ‘HumanMachine Technologies for Construction Sites.’ CIB 265. ISBN 90-6814-119-8. CD-ROM.
Van Gassel, Frans, 2003, Bouwproductiesystemen in Japan in Bouwen in Japan (Building
Production Systems in Japan) in Building in Japan. ARKO, The Netherlands.
Guo, S. and Tucker, R. (1993) Automation needs determination using the AHP approach, in the
proceedings of the 10th International Symposium on Automation and Robotics in
Construction (ISARC) , Elsevier Amsterdam.
Maas, G.J. Modernisation by considering the total building process. De Ingenieur, (Engineer) no.
3 (March 1991).
Maas, G. and F. van Gassel (editors), 2003, Proceedings The Future Site ISARC2003,
Bouwstenen 75, 675 p. Eindhoven University of Technology, The Netherlands.
Maas, G. and F. van Gassel (2005) The influence of automation and robotics on the performance
construction. Automation in Construction 14 435 – 441.
Obayashi, Shigeyuki, 1999, Construction Robot System Catalogue, Council for Construction
Robot Research, Tokyo.
www.intechopen.com
Robotics and Automation in Construction
Edited by Carlos Balaguer and Mohamed Abderrahim
ISBN 978-953-7619-13-8
Hard cover, 404 pages
Publisher InTech
Published online 01, October, 2008
Published in print edition October, 2008
This book addresses several issues related to the introduction of automaton and robotics in the construction
industry in a collection of 23 chapters. The chapters are grouped in 3 main sections according to the theme or
the type of technology they treat. Section I is dedicated to describe and analyse the main research challenges
of Robotics and Automation in Construction (RAC). The second section consists of 12 chapters and is
dedicated to the technologies and new developments employed to automate processes in the construction
industry. Among these we have examples of ICT technologies used for purposes such as construction
visualisation systems, added value management systems, construction materials and elements tracking using
multiple IDs devices. This section also deals with Sensorial Systems and software used in the construction to
improve the performances of machines such as cranes, and in improving Human-Machine Interfaces (MMI).
Authors adopted Mixed and Augmented Reality in the MMI to ease the construction operations. Section III is
dedicated to describe case studies of RAC and comprises 8 chapters. Among the eight chapters the section
presents a robotic excavator and a semi-automated façade cleaning system. The section also presents work
dedicated to enhancing the force of the workers in construction through the use of Robotic-powered
exoskeletons and body joint-adapted assistive units, which allow the handling of greater loads.
How to reference
In order to correctly reference this scholarly work, feel free to copy and paste the following:
Frans van Gassel and Ger Maas (2008). Mechanising, Robotising and Automating Construction Processes,
Robotics and Automation in Construction, Carlos Balaguer and Mohamed Abderrahim (Ed.), ISBN: 978-9537619-13-8, InTech, Available from:
http://www.intechopen.com/books/robotics_and_automation_in_construction/mechanising__robotising_and_au
tomating_construction_processes
InTech Europe
InTech China
University Campus STeP Ri
Unit 405, Office Block, Hotel Equatorial Shanghai
No.65, Yan An Road (West), Shanghai, 200040, China
Slavka Krautzeka 83/A
51000 Rijeka, Croatia
Phone: +385 (51) 770 447
Fax: +385 (51) 686 166
www.intechopen.com
Phone: +86-21-62489820
Fax: +86-21-62489821
www.intechopen.com
© 2008 The Author(s). Licensee IntechOpen. This chapter is distributed
under the terms of the Creative Commons Attribution-NonCommercialShareAlike-3.0 License, which permits use, distribution and reproduction for
non-commercial purposes, provided the original is properly cited and
derivative works building on this content are distributed under the same
license.