Hironori Kato, Crispin Emmanuel D. Diaz, and Marie Onga
The Impact of Foreign Aid on Local Institutional Systems: Case Study of Institutional
Spillover Effect on the Batangas Port Development Project in the Philippines
Hironori Kato
Department of Civil Engineering, University of Tokyo
7-3-1, Hongo, Bunkyo-ku, Tokyo 113-8656, Japan
Phone: +81-3-5841-7451; Fax: +81-3-5841-7496
E-mail:
[email protected]
Crispin Emmanuel D. Diaz
School of Urban and Regional Planning, University of the Philippines
Diliman, Quezon City 1101, Philippines
Phone/Fax: +63-2-9206854
E-mail:
[email protected]
Marie Onga
Department of Civil Engineering, University of Tokyo
7-3-1, Hongo, Bunkyo-ku, Tokyo 113-8656, Japan
Phone: +81-3-5841-8506; Fax: +81-3-5841-7496
E-mail:
[email protected]
1
Hironori Kato, Crispin Emmanuel D. Diaz, and Marie Onga
Abstract. This paper examines the institutional spillover effect, as observed in a port development project
funded by foreign aid, using the Batangas Port Development Project in the Philippines as a case study. First, we
examined the project purposes, processes, and results by reviewing literature and interviewing local actors. Next,
we focused on the key single event—i.e., a demolition—to identify institutional impact. In the project planning
process, the local executing agency experienced difficulty in finding suitable relocation sites for affected
residents. Together with some non-governmental organizations (NGOs), local residents started to oppose the
project. The donor requested that the executing agency find a peaceful solution in negotiations with opposition
groups. Although the executing agency made great efforts to build consensus with the local opposition groups,
including the introduction of an Inter-agency Committee, it finally conducted the demolition without notifying
the donor. We examine in detail the behavior of the donor and recipient, to understand the reasons as to why the
demolition happened as it did. Finally, the role of the Inter-agency Committee and its limitations are discussed.
Keywords. Port development project, institutional spillover effect, official development assistance, conflict
management
2
Hironori Kato, Crispin Emmanuel D. Diaz, and Marie Onga
INTRODUCTION
A number of empirical studies have recently shown that infrastructure development contributes to economic
growth and poverty reduction in developing countries (1, 2, 3); however, most studies into aid effectiveness
have focused on the beginning and end of this causality chain (4). Intermediate processes therein have often
been referred to as a kind of “black box” (5), and it has been argued that further progress in aid effectiveness
requires that that box be opened. To date, the mechanisms and processes by which aid-funded infrastructure
projects produce successful development outcomes have not been examined. Jerve and Nissanke (4) hypothesize
that the success or sustainability of such investments depends, to a large extent, on institutional spillover effects.
This depends upon the intermediary and institutional outcomes of the project—e.g., impacts in terms of human
resource development, capacity-building, and institutional and policy reform. These, in turn, depend upon what
takes place within the “black box.” In response to such concerns, this paper aims to analyze, empirically, the
indirect effects of infrastructure projects by focusing on the institutional spillover effects. The research involved
observing institutional spillover effects and the processes therein, during the implementation of infrastructure
projects funded by foreign aid. For this paper, conflict management in the execution of the Batangas Port
Development Project in the Philippines was examined as a case study.
The paper is organized as follows. The next chapter provides a project overview. Chapter 3 reviews the
project implementation process and the project results, by reviewing pertinent literature and interviewing local
stakeholders; the focus therein is on the single key event of the case study. Chapter 4 examines spillover effects
by identifying the major actors, mapping the institutional mechanisms/organizations involved, and relating these
to the key event. Finally, Chapter 5 summarizes the analytical findings and presents further research issues.
BATANGAS PORT DEVELOPMENT PROJECT
The principal aim of the Batangas Port Development Project (BPDP) was to improve freight transportation
conditions between Luzon Island and Mindoro Island. The BPDP aimed also to develop the regional economy in
the hinterlands, and also to complement the Manila Port as one of the major international ports serving Luzon
Island in the Philippines. The Batangas Port is located 110 km south of Metro Manila, on the northeast coast of
Batangas Bay, which is in the southwestern portion of Luzon Island (see FIGURE 1). Before BPDP, Batangas
Port was used mainly for the Ro-Ro vessel service, as a gateway to Mindoro Island.
The Philippine government and the Japan International Cooperation Agency (JICA) formulated the
Batangas Port Expansion Program in 1984. In December 1985, JICA conducted a feasibility study (F/S) for the
development of Batangas Port, upon the request of the Philippine government. The F/S envisioned the Batangas
Port as the main gateway to and from the islands of MIMAROPA (Mindoro, Marinduque, Romblon, and
Palawan), the Visayas, and Mindanao. The F/S report also included both short- and long-term plans; the former
aimed to improve and expand the existing dilapidated facilities, to increase the port’s distribution efficiencies,
FIGURE 1 Location of Batangas Port in the Philippines
3
Hironori Kato, Crispin Emmanuel D. Diaz, and Marie Onga
whereas the latter aimed to expand Batangas into a large-scale port. The intention was that, in the future, the
Batangas Port would be fully capable of handling foreign cargo and supplementing the service capacity of the
Port of Manila. The first phase of BPDP—which corresponded to the short-term plan—covered a 22-ha area at a
cost of 1.6 billion pesos (about 76.9 million US dollars). The first phase aimed to solve the problems of the time
and meet further growth in shipping demand. The BPDP Engineering Service was appraised by the Japan Bank
of International Cooperation (JBIC) between May and June 1987, and its loan agreement was signed in 1988.
In 1989, the Philippine government formally requested that the Japanese government create the
CALABARZON Development Master Plan. (“CALABARZON” comes from the first letters of the names of
five provinces—CAvite, LAguna, BAtangas, Rizal, and QueZON—which are just east and south of Metro
Manila and comprise the best places, logistically, for industry to site their factories.) The JICA started its study,
to create the Master Plan; during that study, President Corazon Aquino announced the CALABARZON
Development Plan. The BPDP was appraised by the JBIC in 1990, and its loan agreement for the project was
signed in July 1991. The JICA submitted “The Master Plan Study of Project CALABARZON, Final Report” to
the Philippine government in February 1992; it touched upon the Expansion Plan of the Batangas Port and the
Development Plan, covering the five provinces in the eastern and southern parts of Metro Manila.
The BPDP was also included in the “Philippines 2000 Plan,” proposed by President Fidel Ramos. The
President spoke in 1993 that the “Philippines 2000 Plan” aimed to make the country a new member of the
Newly Industrializing Economies (NIES) group, before the end of the century. Under the “Philippines 2000
Plan,” the National Economic and Development Authority (NEDA) formally set up the “Medium-Term
Philippine Development Plan, 1993–1998” (MTPDP), which emphasized “Sustainable Agri-Industrial
Development, Infrastructure Development” as part of the basic framework of the Philippines’ developmental
strategy. All the departments of both the central and local levels of government were required to take account of
the balance of development between the agricultural and industrial sectors, when making developmental plans.
It was the Department of Trade and Industry (DTI) that was responsible for the CALABARZON Plan, which
was regarded as one of the most important development plans in the country at that time. Main port construction
started in 1995.
CASE DESCRIPTION
Conflict was encountered during the process of resettling affected local residents, during the development and
expansion of Batangas Port (6). This conflict was the main contributor to delays in project completion—i.e.,
three years and seven months behind schedule—and to a compensation package four times larger than that
originally offered (7, 8, 9). For a more detailed description of the BPDP implementation, readers are referred to
Kato et al. (10).
The area occupied by settlers was part of the foreshore land, and it was first settled prior to 1900.
Members of the community found a variety of livelihoods as vendors, stevedores, and the like when the port
was constructed in the mid-1930s. Since 1969, many of these settlers had tried to secure formal ownership of the
land; most of them had failed, however, partly because foreshore land cannot be titled. In the time leading to the
development and expansion of the port, land ownership was very loosely regulated. Following the completion of
feasibility studies, but prior to the signing of loan agreements between JBIC and the Philippine government visà-vis construction and engineering services, initiatives were put in place by the Batangas City government to
identify resettlement areas. Several committees were also formed, including an Ad-Hoc Coordinating
Committee for Sta. Clara, a civil society group of the Barangay Sta. Clara. (A “Barangay” is the smallest
political administration unit in local government in the Philippines.) Also, a Special Committee for Sta. Clara
was also established, comprising representatives from the Batangas City, the Philippine Port Authority (PPA),
the Department of Social Welfare and Development (DSWD), the Catholic Church, and the aforementioned AdHoc Coordinating Committee for Sta. Clara. These committees also worked with other government agencies
like the National Housing Authority (NHA) and the Presidential Commission for the Urban Poor (PCUP) during
the entire process. It should be noted that prior to the project, processes to deal with resettlement had not been
very well established, and this partly contributed to the problems that were encountered. When the project was
still in the process of being implemented, a law, Republic Act No. 7279—also known as the Urban
Development Housing Act—was enacted. This law secures compensation for squatters and specifies processes
for conducting demolitions and relocations. The passage of this law affected the negotiation processes, and the
BPDP was the first national project to which this law was applicable. Also, during the project implementation
period, the territorial jurisdiction of Batangas Port was re-delineated by law, and the area occupied by residents
of Sta. Clara was included in this territorial jurisdiction. This re-delineation effectively induced a restart of the
process of selecting a resettlement site, because it effectively redefined the “ownership” of the land in question.
TABLE 1 summarizes the key activities related to resettlement, their respective durations, and short
remarks on the process. From these events, several observations can be made regarding the overall process. First,
the method used to identify affected households led to likely changes in the recorded number of households,
4
Hironori Kato, Crispin Emmanuel D. Diaz, and Marie Onga
TABLE 1 Key Activities Related to Resettlement in the Batangas Port Development Project
Activities
Identifying affected
residents
Duration
From – To (Number of months)
1986 June – 1993 October
(89 months)
Deciding the location of 1986 June – 1991 May
(59 months)
resettlement site
Development of
resettlement site
1991 May – 1992 November
(18 months)
Clearing the project site 1993 January – 1994 June
(17 months)
Deciding the
1986 June – 2000 December
compensation package (168 months)
Remarks on the process
In June 1986, the tally by Batangas City government was
718 families living 606 structures. A survey by PCUP in
1992 revealed identified 971 families, 80% of which were
“illegal settlers”. PCUP and NHA revalidation survey in
1993 showed 1467 families. Final tally was 1,465 families.
The proposals went back and forth many times, involving
committees composed of government and nongovernment organizations. Reasons for rejection of the
proposals included:
For PPA – too expensive
For residents – site is flood prone, site is too far
from employment
Even when the (Balete) site was finally purchased, a
number still were unsatisfied with the choice.
Includes a clinic for Balete and Sico resettlement sites.
The road to Sico was also repaired using funds from JBIC
loan and completed by November 1997.
Starts with first notice to vacate. Several subsequent
issuance of to notice were ignored by residents. JBIC
requests a “peaceful” resolution. Further dialogues
between GOP and residents are unfruitful. GOP finally
decided to forcibly eject the residents and demolish the
structures. Actual demolition only takes 6 days.
PPA and the residents could not agree on the package
thru direct negotiation. The PPA lost court cases at the
Regional Trial Court and the Court of Appeals.
following the initial count; the number should have been determined, with finality, prior to project
implementation. The second observation is that the method for determining compensation did not initially have
legal support and therefore was subject to “unreasonable” demands by either the affected households or the PPA.
The new law that emerged during the project implementation period was not well understood or accepted by the
parties involved, and so its stipulations were not initially addressed; however, towards the end, the execution of
the eviction and demolition procedures did align with Republic Act No. 7279. The third observation is that the
PPA prioritized the immediate implementation of the project over the “humane” treatment of the affected
households; as a result, it may have been convenient to consider the affected households as generally having no
legal rights to the land. While it is accepted that a number of the households of the area were “illegal settlers,” it
is also accepted that others had occupied the land long before the port development and expansion project was
conceived. In any case, the project had a weak framework for mitigating the social and environmental impacts
of the project. This framework has since been addressed by the new guidelines of foreign funding agencies like
JBIC and the Asian Development Bank.
ACTOR STRATEGY ANALYSIS IN THE PROCESS
We examine the details of the decision-making process in relation to the conflict between the opposing residents
groups and the PPA. We also focus on the interactions between the PPA and the JBIC/Japanese government.
The PPA’s Strategy
We start our analysis by examining the PPA’s behavior. When the residents started to oppose the relocation
project, the PPA tried to create agreements with them by reviewing the relocation site selection process several
times. However, the PPA found it difficult to find a relocation site that satisfied the increasing demands of the
opposing residents. Finally, the PPA gave up negotiating with the opposing residents and decided to conduct
demolition without announcing it to the Japanese contingent.
Why did the PPA make such a decision? What other options were available? To answer these questions,
we list here all the hypothetical options available to the PPA:
z (P-i) Keep negotiating with the local opposition group, mainly with regards to compensation, under the
condition that the PPA fixes the relocation sites;
5
Hironori Kato, Crispin Emmanuel D. Diaz, and Marie Onga
z
z
z
z
(P-ii) Continue searching for other relocation sites, until it found sites that satisfied the affected residents;
(P-iii) Request that the JBIC support the assistance package for the affected residents, without conducting
the demolition;
(P-iv) Conduct demolition after receiving approval from the JBIC; and
(P-v) Conduct demolition without approval from the JBIC.
To choose an option from among those listed above, we should examine the objectives of the PPA in
the context of the BPDP. These are as follows:
z (P-1) Implement the project at the lowest possible cost;
z (P-2) Complete the project on schedule;
z (P-3) Build consensus among stakeholders; and
z (P-4) Maintain a good relationship with the JBIC/Japan.
Given the lists above of possible options and objectives, how can one explain the PPA’s behavior with
respect to the BPDP’s implementation process? First, did the PPA respect objective (P-3), to “build consensus
among the stakeholders”? The answer is partly yes, but mostly no. Unfortunately, it is difficult to say whether
PPA put the highest priority on objective (P-3) during project implementation. It is true that the PPA searched a
variety of relocation sites with the other stakeholders, including the NHA and the City Mayor. It is also true that
the PPA tried to build consensus with the local residents in an early stage of the project. However, after they
found it difficult to obtain acceptance of the relocation site from the local residents, they immediately created
the Inter-agency Committee. According to the discussions of the Inter-agency Committee, the PPA apparently
did not respect the local residents, and only had respect for the public or official organizations in the Interagency Committee. The PPA may not have invited true representatives of the affected residents as members of
the Inter-agency Committee, when the time came to examine detailed studies of the candidate relocation areas.
Instead of dealing directly with local residents, the committee considered Barangay Council members
representatives of the affected residents; this was likely a matter of expediency, as the committee probably
expected longer discussions and higher costs in negotiating with local residents. This is problematic, since no
direct validation (such as through a survey) with the affected residents was conducted. It appears that the PPA’s
decision to exclude residents from the decision-making process may have given rise to a series of serious
conflicts during the project. Thus, it seems that the PPA accorded more importance to the objective (P-1),
“implement the project at the lowest possible cost” and/or the objective (P-2), “complete the project on
schedule.” As far as objective (P-4) (“maintain a good relationship with the JBIC/Japan”) is concerned, the PPA
only accorded it importance in relation to receiving project funds.
Next, we examine why the PPA gave up negotiations with the local opposition group. The PPA thought
that they had already tried to search for relocation sites many times and that they did not need to make any
additional effort in negotiating with local residents and/or searching for new candidate sites. Actually, in the
public hearing, the PPA said that it was impossible to reselect the site, since a huge amount of money had
already been spent on site development and other options were unavailable. This reflects their objectives (P-1)
“implement the project at the lowest possible cost” and (P-2) “complete the project on schedule.”
We then look at why the PPA conducted the demolition without notifying the Japanese contingent.
There are two hypothetical reasons. The first reason is because it did not respect the objective (P-4) “Maintain a
good relationship with the JBIC/Japan,” although the JBIC/Japanese government requested a peaceful solution
to the conflict problem. Instead of notifying the Japanese contingent of the demolition, the PPA acquired
approval from the Philippine government. This suggests that the PPA thought it was the Philippine
government’s responsibility to maintain a good relationship with the donor, the Japanese government, rather
than theirs. Although we could not obtain any direct documented evidence pertaining to the behavior of the
Philippine government, it might have contacted the JBIC and/or the Japanese government about the demolition.
It might also have been that the PPA dared not notify the Japanese government of the demolition, knowing that
the Japanese government would have no option but to reject the demolition plan, due to the nature of the conflict.
The PPA also felt that demolition was unavoidable, given that negotiations had reached an insurmountable
impasse.
Finally, did the PPA ask the JBIC to support the assistance package for affected people? There is no
evidence of this, and there are two possible reasons for this lack. One possible reason is that the PPA did not
request it; if this is the case, it is possible that the PPA was not willing to improve the assistance package. As
had been mentioned, the opposition group had escalated demands for assistance, including a proposal requesting
that the PPA pay an extraordinary amount of compensation. The PPA might have felt that the opposition groups
had proposed high levels of compensation, not with the intention of coming to a consensus with the PPA, but to
impede the project and/or receive a higher amount of compensation than had been previously offered. It is
entirely possible, then, that the PPA thought that additional support in the form of a larger assistance package
would not break the impasse. The other possible reason is that the PPA may have asked the JBIC, informally, to
6
Hironori Kato, Crispin Emmanuel D. Diaz, and Marie Onga
support the assistance package funding. If this were the case, the PPA likely did so because they needed
additional funding to keep maintain negotiations with the local residents. As mentioned previously, the JBIC
had requested that the PPA find a “a peaceful solution;” this might have been interpreted by the PPA as an offer
by the JBIC, however subtle, to shoulder part of the expenses related to achieving that “peaceful solution”—i.e.,
additional (possibly financial) support to the PPA. Why, then, would the PPA have requested it informally? It is
likely that the PPA was concerned that opposition groups would request even more compensation, if they knew
that the JBIC was bank-rolling a portion of it.
The JBIC/Japanese Government’s Strategy
The JBIC knew that the PPA had encountered difficulties in consensus-building with local residents.
Nonetheless, the JBIC expected the PPA to find a peaceful solution. During negotiations between the PPA and
local residents, what options did the JBIC/Japanese government have, hypothetically? The hypothetical options
are as follows:
z (J-i) Keep requesting the PPA find a peaceful solution and ignore the results, even if the PPA conducts the
demolition’
z (J-ii) Propose a supporting scheme for the local residents, without suspending the loan; and
z (J-iii) Suspend the loan to the project and propose a supporting scheme after the demolition.
z
z
The hypothetical objectives of the JBIC/Japanese government are summarized as follows:
(J-1) Contribute to Japan’s benefits, which may include its good reputation among other countries; and
(J-2) Support the development of the Philippines while not harming the local people.
To which objective does the JBIC/Japanese government give the most importance? In general, the
JBIC/Japanese government appeared to give the most weight to objective (J-1), “contribute to Japan’s benefits”;
this is because (J-2), “support the development of the Philippines while not harming local people” is considered
a necessary condition in satisfying objective (J-1). This means that the successful support of the Philippines can
contribute to a more positive reputation for the Japanese government. In some cases, an option may satisfy
objective (J-1) while not satisfying objective (J-2); in such cases, the JBIC/Japanese government may accord
greater respect to objective (J-2) than to objective (J-1). This is because (J-2) is considered a minimum condition
for international cooperation.
Why, then, did the JBIC/Japanese government choose the specific option that they did? First, it was
difficult for the JBIC to choose option (J-i), given objectives (J-1) and (J-2). On one hand, the demolition forced
the local people to move, which meant harming local people in some way; this violates objective (J-2). On the
other hand, the demolition may have marred the reputation of the JBIC/Japanese government among other
countries, including developed and developing countries; this would violate objective (J-1).
The JBIC/Japanese government was likely faced with a choice of pursuing either option (J-ii) or (J-iii).
The JBIC/Japanese government requested that the PPA find a “peaceful solution”; to attain this, it is certain that
the PPA would need a larger budget, to compensate the local residents and/or provide other, additional support.
The following two cases are proposed:
1. Had the JBIC/Japanese government chosen option (J-ii), they would have needed to be involved in the
negotiation process with the local residents. This is because a peaceful solution would not have been
achieved, with the local residents agreeing to the proposal offered by the JBIC/Japanese government.
However, if the local residents would not agree even to the JBIC/Japanese government’s proposal, there be
no one left to mediate the conflict between the PPA and the local residents. This would be a “worst-case
scenario” for the JBIC/Japanese government.
2. Had the JBIC/Japanese government chosen option (J-iii), the JBIC/Japanese government may have
experienced a variety of problems. First, the JBIC/Japanese government would not have been able to
complete the project within the proposed schedule, and the Japanese taxpayers would likely have accused
the JBIC/Japanese government of poor schedule management. Second, the international relationship
between Japan and the Philippines would have worsened. The local people and businesses who expected
an early start to Batangas Port service may have blamed the Japanese government for delaying the
schedule. Third, the JBIC/Japanese government may have lost its international reputation with respect to
project management. Fourth, the JBIC/Japanese government may have lost the power or leverage to
control or influence the PPA. On the other hand, the JBIC/Japanese government would derive benefits as a
result of choosing option (J-iii). First, they could show strong displeasure with the demolition, and the fact
that the Japanese government could suspend loans whenever the borrowers did not follow the requests of
the JBIC/Japanese government may send a strong message to others, thus making the JBIC/Japanese
government’s threat-as-option effective in the future. Second, they could show a consistent attitude toward
the stakeholders during the project; this could increase the trust in the JBIC/Japanese government in the
7
Hironori Kato, Crispin Emmanuel D. Diaz, and Marie Onga
future. Third, a temporary halting of the loan could shock domestic stakeholders in Japan; although the
JBIC/Japanese government wanted to give additional support to the PPA, they probably assessed
difficulties in building consensus among domestic stakeholders in Japan. The act of suspending the loan
would help domestic stakeholders understand BPDP’s gridlock situation.
INSTITUTIONAL SPILLOVER IN THE DEMOLITION PROCESS
This section discusses the institutional influences observed in a process where a conflict occurred between the
opposing local residents and the PPA, and how the demolition affected stakeholders. We focus on the
interactions between the PPA and the JBIC/Japanese government. Within this context, we will discuss two types
of games. The first is the game between the PPA and the JBIC/Japanese government, with respect to giving
support or compensation to the opposing residents; this is called the “support game.” The second is the game
between the PPA and the JBIC/Japanese government, with respect to the suspension or halting of loans; this is
called the “halt-loan game”.
Support Game between the PPA and the JBIC/Japanese Government
First, let us consider the support game. Suppose that the PPA has two options, (P-i) and (P-iii), as described
earlier. Remember that option (P-i) is “Keep negotiating with the local opposition group, mainly with regards to
compensation, under the condition that the PPA fixes the relocation sites” and option (P-iii) is “Request that the
JBIC support the assistance package for the affected residents, without conducting the demolition.” Next,
assume that the JBIC/Japanese government has the following two options: (J-i) and (J-ii). Remember that option
(J-i) is “Keep requesting the PPA find a peaceful solution and ignore the results, even if the PPA conducts the
demolition” and option (J-ii) is “Propose a supporting scheme for the local residents, without suspending the
loan.”
Let us consider combinations of these options between the two actors, as shown in the matrix in
TABLE 2. This can be considered a simple non-cooperative game between two players, and Table 2 shows the
hypothetical payoffs for each stakeholder, for each pair of options. The left values in the payoff box in the table
refer to the payoffs of the PPA, whereas the right values refer to the payoffs of the JBIC/Japanese government.
First, assume that the payoffs are both zero when both actors choose the “status quo” option. Second, the PPA
receives negative payoffs while the JBIC/Japanese government gets the same payoff as status quo, when the
PPA chooses option (P-iii) while the JBIC/Japanese government chooses option (J-i). This is because the PPA
incurs some costs when making a request of the JBIC/Japanese government. Third, the PPA has a positive
payoff and the JBIC/Japanese government has a negative payoff when the PPA chooses option (P-iii) and the
JBIC/Japanese government chooses option (J-ii); this is because the PPA can benefit from the support proposed
by the JBIC/Japanese government while the JBIC/Japanese government simply loses resources by providing
support. Finally, the PPA has a positive payoff while the JBIC/Japanese government has a positive/negative
payoff when the PPA chooses option (P-iii) and the JBIC/Japanese government chooses option (J-ii): The PPA
can derive the benefit of the support proposed by the JBIC/Japanese government, while the JBIC/Japanese
government may lose or earn benefits by providing that support. However, we can expect the JBIC/Japanese
government’s payoff in the (P-iii)-(J-ii) case to be higher than that in the (P-i)-(J-ii) case; this is because the
JBIC/Japanese government will be more satisfied with their support proposal when the PPA requests it. In other
words, if the JBIC/Japanese government first receives the PPA’s request and then makes a counterproposal, the
outcome will be more positive for the JBIC/Japanese government, especially with respect to their Japanese
stakeholders.
There are two possible equilibria in this game. The first equilibrium involves the pairing of (P-i) and
(J-i); we call this equilibrium the “status quo equilibrium,” and it is a stable equilibrium. The second equilibrium
depends on the relative values in the payoff matrix, particularly the values of a, e, and f. If e > a and if the
JBIC/Japanese government’s payoff in the (P-iii)-(J-ii) case is positive, the case with (P-iii)-(J-ii) can be the
TABLE 2 Support Game between the PPA and the JBIC/Japanese Government
JBIC/Japan Government
Option (P-i)
A Status quo
P
P Option (P-iii)
Request support
Option (J-i)
Status quo
[0, 0]
Option (J-ii)
Propose support
[+a, -b]
[-c, 0]
[+e, ±f]
8
Hironori Kato, Crispin Emmanuel D. Diaz, and Marie Onga
second equilibrium. However, in reality, only the “status quo equilibrium” was observed. This means the
conditions of “e > a” and/or “the JBIC/Japanese government’s payoff in the (P-iii)-(J-ii) case is positive” did not
hold true. The authors suggest that the JBIC/Japanese government’s payoff in the (P-iii)-(J-ii) case was negative.
As discussed earlier, this is probably because the JBIC/Japanese government would need to be involved in the
negotiation process with the local opposition groups, if they were to propose a support scheme. If the local
opposition groups did not agree to the JBIC/Japanese government’s proposal, there would be no one left to
mediate the conflict between the PPA and the local residents. Thus, the JBIC/Japanese government was likely
careful not to fall into this “worst-case scenario” and acted to avoid it.
Halt-Loan Game between the PPA and JBIC/Japanese Government
Now let us consider the halt-loan game. Suppose that the PPA has two options, (P-i) and (P-v), while the
JBIC/Japanese government has two options, (J-i) and (J-iii). Remember that option (P-i) is “Keep negotiating
with the local opposition group, mainly with regards to compensation, under the condition that the PPA fixes the
relocation sites,” while option (P-v) is “Conduct demolition without approval from the JBIC.” Also, option (J-i)
is “Keep requesting the PPA find a peaceful solution and ignore the results, even if the PPA conducts the
demolition,” while option (J-iii) is “Suspend the loan to the project and propose a supporting scheme after the
demolition.”
It is then assumed that we have a two-step dynamic game. The first step is that the PPA makes a choice
as a leading player, and the second step is that the JBIC/Japanese government makes a choice as a following
player. The game tree is depicted in Figure 2. The left side of the payoff vector represents the PPA’s payoff,
while the right side is the JBIC/Japanese government’s payoff. It is assumed that the payoffs are both zero when
they choose options (P-i) and (J-i). On the other hand, both players have negative payoffs when the PPA
chooses option (P-i) while the JBIC/Japanese government chooses (J-iii). Also, the PPA has a positive payoff
whereas the JBIC/Japanese government has a negative payoff, when the PPA chooses option (P-v) and the
JBIC/Japanese government chooses (J-i). This is because the PPA can force the opposing residents to move by
conducting the demolition, while the JBIC/Japanese government probably loses the trust of stakeholders and the
power to persuade the PPA. Finally, the PPA has either a positive or negative payoff, whereas the
JBIC/Japanese government has a negative payoff, when the PPA chooses option (P-v) and the JBIC/Japanese
government chooses (J-iii). We can expect that the JBIC/Japanese government’s payoff in the (P-v)-(J-iii) case
to be greater than that in the (P-v)-(J-i) case; this is because the JBIC/Japanese government can derive benefits
in addition to the negative impact by halting the loans, as discussed previously.
By applying the backward induction method to this dynamic game, we can obtain a sub-game perfect
equilibrium. The solution depends on the state of the PPA’s payoff in the (P-v)-(J-iii) case. If the PPA’s payoff
in the (P-v)-(J-iii) case is positive, “+p” is derived; then, the game produces (P-v)-(J-iii) as the solution. If the
PPA’s payoff in the (P-v)-(J-iii) case is negative, however, “–p” is derived; then, the game outputs (P-i)-(J-i) as
the solution. Reality shows that the PPA’s payoff in the (P-v)-(J-iii) case was positive; this means that the PPA
had a positive payoff by conducting the demolition, even if the JBIC/Japanese government were to halt the loans.
In other words, the PPA thought that conducting the demolition was better than the status quo, even if there was
the possibility of the JBIC/Japanese government halting the loans.
ROLE OF THE INTER-AGENCY COMMITTEE AND ITS LIMITATIONS
In this section, we discuss the Inter-agency Committee established by the PPA as an example of an “influence of
Start
PPA
JBIC/
Japan Government
Status-quo (P-i)
Status-quo
(J-i)
[0, 0]
Demolition (P-v)
Halt the loans Status-quo
(J-iii)
(J-i)
[-t, -u]
[+r, -s]
Halt the loans
(J-iii)
[±p, -q]
Figure 2 Halt-Loan Game between the PPA and the JBIC/Japanese Government
9
Hironori Kato, Crispin Emmanuel D. Diaz, and Marie Onga
donor” policy and practice on institutional impacts. The JBIC strongly and repeatedly requested that the PPA
find a peaceful solution to consensus-building with respect to the relocation of local residents. JBIC’s explicit
expression of policy impacted the PPA’s strategy of negotiation with the local residents.
First, the PPA established the Inter-agency Committee. It aimed to discuss the various issues relating to
the BPDP and attempted to explain to the local residents the necessity of developing the port. The Inter-agency
Committee members consisted of agencies and stakeholders related to the BPDP, including representatives of
the Department of National Defense (DND), the Department of Transportation and Communications (DOTC),
the PPA, the NHA, the PCUP, the Presidential Advisory Committee, the Philippine National Police (PNP), the
Batangas City, the Batangas Province, and the DSWD.
One of the most important effects of establishing the Inter-agency Committee was that it enabled the
PPA to declare publicly that the decision made in this committee was an “official agreement” among all those
stakeholders, and it was difficult for affected residents to oppose the decisions made by such a committee. The
PPA likely enjoyed the greatest benefit by establishing the Inter-agency Committee; this is because the PPA was
the only agency that, in reality, could manage the budget and had the power to make final decisions. The
interview with the PPA shows that the Inter-agency Committee took an important role in allowing the project to
progress. Additionally, the Inter-Agency Committee helped established smooth communications among the
stakeholders, even after this project, creating an atmosphere of close coordination among the agencies involved.
A similar committee was created for Phase 2 of the BPDP. The officers interviewed told us that the
establishment of the Inter-agency Committee was an important lesson learned during Phase 1, in that it enabled
the agencies to cooperate and to coordinate their actions in smoothly completing the project.
On the other hand, establishing the Inter-agency Committee also had a negative effect. The
committee’s decision-making process was not completely transparent and open to the public. As the committee
included governmental department officers who held administrative power, the decisions made by the
committee had a critical influence on the project and gave the impressions to local residents that decisions were
being made behind closed doors and that local residents were excluded from the committee. This might be one
of the reasons why the opposition groups protested even more loudly. From this viewpoint, it could be said that
the Inter-agency Committee was not well managed. In general, the selection of members is one of the most
important processes in setting up a committee. The members should be carefully selected by taking into account
the balance of stakeholders. In the case of the Inter-agency Committee of the BPDP, it would have been ideal to
include a representative of the opposing local residents; after all, the captain of the Barangay, who attended the
meeting of the Inter-Agency Committee, was not really an affected resident. This complicated the negotiation
process between the PPA and the opposing local residents.
CONCLUSIONS
This paper examined the institutional spillover effect observed in the BPDP in the Philippines, which had been
funded by foreign aid. First, the project purposes, processes, and results were examined by reviewing literature
and interviewing local actors. Next, a key single event, the demolition, was focused on, to identify the
institutional impact arising in relation to it. The local executing agency experienced difficulty in finding
relocation sites acceptable to the affected residents. With support from some NGOs, the local residents started to
oppose the project, making it more difficult for consensus to be reached. The donor requested that the executing
agency find a peaceful solution in negotiating with opposition groups; although the executing agency exerted a
great amount of effort to build consensus with the local opposing residents, including the introduction of an
Inter-agency Committee, the demolition was finally conducted without notifying the donor. We examined the
detailed behavior of the donor and recipient, to understand the reasons why the demolition occurred as it did.
Two simple games, the support game and the halt-loan game, were introduced within this study, as they were
useful in examining the interaction between the PPA and the JBIC/Japanese government. Finally, we examined
the Inter-agency Committee, which was an important bridge between stakeholders; nonetheless, its main
limitation was that representation therein of the residents may have been lacking.
There are several possible topics for future research. First, although institutional impact was examined
during the project, further impacts may occur even after the project. It is necessary to keep observing
institutional changes that fall out from a project, to understand both mid- and long-term effects. Next, the game
analysis could be performed in a more sophisticated manner, to analyze the behaviors of stakeholders in greater
detail. Particularly, an iterative game may be introduced, to analyze mid- and long-term institutional changes.
Finally, a comparative analysis of projects funded by foreign aid and projects not funded by foreign aid would
be useful, in properly understanding the impact of foreign aid on developing countries.
10
Hironori Kato, Crispin Emmanuel D. Diaz, and Marie Onga
ACKNOWLEDGMENTS
This study was originally undertaken as part of the “Aid Effectiveness to Infrastructure: A Comparative Study
of East Asia and Sub-Saharan Africa” project, initiated by the Institute of Japan Bank of International
Cooperation (JBICI). We greatly appreciate the many interviewees for their kind support of our study.
REFERENCES
1.
Salehi, E. H., and M. T. Ramirez. Institutions, Infrastructure and Economic Growth. Journal of
Development Economics, Vol. 70, 2003, pp. 443–477.
2. Cesar, C., and L. Serven. The Effects of Infrastructure Development on Growth and Income Distribution.
World Bank Policy Research Working Paper, No. 3400, 2004, Washington D.C.
3. Datt, G., and M. Ravaillion. (1998) Why Have Some Indian States Done Better than Others at Reducing
Poverty? Economica, Vol. 65, No. 257, 1998, pp. 17–38.
4. Jerve, A. M., and M. Nissanke. Aid Effectiveness to Infrastructure: A Comparative Study of East Asia and
Sub-Saharan Africa: Framework Paper. JBICI Research Paper, No. 36-1, 2008 pp. 1–68,
http://www.jbic.go.jp/en/research/report/research-paper/pdf/rp36_e03.pdf (last accessed July 16, 2009).
5. Bourguignon, F., and M. Sundberg. Aid Effectiveness – Opening the Black Box, World Bank, 2006.
6. Porio, M., C. S. Crisol, N. F. Magno, D. M. Cid, and R. M. Indon. Demolition and Resettlement of Sta.
Clara Residents: Policy, Politics, and Personalities in the Batangas Port Development Project, A Paper
Prepared for the Japan Bank for International Cooperation, 2000.
7. Japan Bank for International Cooperation. Batangas Port Development Project Phase 1 Completion Report,
1999.
8. Japan Bank for International Cooperation. Batangas Port Development Project: Project Evaluation Report,
March 2000. (in Japanese)
9. Philippine Port Authority. Implementation Program for the Expansion of Container Berth under the
Batangas Port Development Project, Phase II, May 2004.
10. Kato, H., C. E. D. Diaz, and M. Onga. Aid Effectiveness to Infrastructure: A Comparative Study of East
Asia and Sub-Saharan Africa: Philippines Case Study. JBICI Research Paper, No. 36-2, 2008, pp. 1–60,
http://www.jbic.go.jp/en/research/report/research-paper/pdf/rp36_e03.pdf (last accessed July 16, 2009).
11