Austrian Development Co-operation
Evaluation of
Small Hydro Projects in Namche Bazaar (Nepal) and
Rangjung (Bhutan)
EZA Projekt: 1389
Prepared by:
ENTEC AG
Consulting & Engineering
St. Gallen, Switzerland
Contract No.:
1389-03/2000
Date:
March 2001
Final Version
Electronic files:
Ev NE-BHU Schlussbericht 1.PDF….. pages 1 to 71
Ev NE-BHU Schlussbericht 2.PDF……pages 72 – 147
EV NE-BHU Annex 1-7.PDF……..
Annexes 1 to 7
D:\ENTEC\2133 BHU-NE\reports\Eval Bericht Nepal ver20.doc
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
1. EXECUTIVE SUMMARY
1.1 Background
Small Hydro development has been recognized at an early stage to be of considerable
importance to the Himalayan kingdoms of Nepal and Bhutan, since no other natural
resource is known in these countries of comparable abundance. Electricity from natural
resources such as hydro constitutes an environmentally acceptable and a reliable resource. Its utilization is generally considered economic in the long rather than the short
term.
Austria has been a key player in the early stages of rural electrification in both, Nepal
and Bhutan. After more than 20 years of involvement in the sector, it desired to evaluate its own work. The assignment to carry out such evaluation was awarded to an outside consultant in a competitive process, and the present report is the result of the
work done under this assignment.
1.2 The Namche Bazaar Small Hydro and Rural Electrification
Project
1.2.1
Introductory remark
The Namche Bazaar project, as defined by the Austrian input, is much more than a
small hydro plant. It includes high tension transmission, the entire distribution network
and house installations, as well as training of personnel and institution building. Also, a
reforestation component and drinking water supply system have been added. Thus, it
constitutes an autonomous rural electrification project in which Austria has been involved almost 25 years, and has taken almost complete responsibility during a time
period of more than 15 years.
1.2.2
History
The beginnings of the project reach back to 1976. The first power scheme was initiated
by the Austrian export industry, with the objective to establish a scheme for reference
purposes. It was initially agreed that Austria would provide the electro-mechanical
equipment, whereas from the Nepalese side, costs for all construction was to be taken
over. However, the Nepalese government found itself unable to meet total construction
costs. Detailed planning was concluded in 1979, and construction started after the
signing of an agreement between Austria and His Majesty’s Government (HMG) in
1983. However, in August 1985, the construction site at the Bhote Kosi was completely
destroyed by a Glacial Lake Outburst Flood (GLOF) that originated from the Langmoche glacier. A feasibility study was later commissioned on the basis of a new site, and
the new power scheme was implemented between 1988-1994.
An agreement was formulated in 1994 between the Austrian government and HMG
with the objectives to establish a share holding company for the operation of the
scheme. Training of personnel had started much earlier. 12 young men were trained,
who today constitute the work force of KBC. In the institution-building task, the NGO
Eco-Himal, on behalf of the Austrian government, was involved for a period of more
than 6 years, up to the end of 2000. During the same period, design flaws of the
scheme were rectified as far as possible, to improve operational reliability.
Page 2
ÖEZA, Projekt 1389
1.2.3
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
SHP Namche Bazaar Project Status by the end of 2000
Today, the electricity company KBC operates the scheme all by itself. The company
has now five years of experience in power generation, transmission and distribution,
with related tasks such as maintenance and associated administration. The area within
the reach of the project is fully electrified. A population equivalent to about 3’000 permanent inhabitants is served.
Consumers benefit from very reliable electricity at low cost, and technical installations
are of a high standard of safety. The acceptance rate of electricity has been 100%; all
households within reach, except for three, are connected.
The level of wood substitution achieved is about 30%.
Economic activity is tourism oriented to a large extent. Businesses are almost always
family-based, with supplementary labour hired if necessary. The most prevalent commercial activity is the small shop or lodge. Some new ventures are totally electricity dependent, and have arisen as a direct impact of the project.
1.2.4
Evaluation Results
• To plan and implement the Namche SHP was a very ambitious undertaking,
given the extreme remoteness and climate of the project site, and practically from
the beginning a difficult and strained relationship with partner institutions. In this
situation, the achievement is considerable. The Austrian agency for Development
Co-operation has shown persistence in bringing the project to a successful end.
• Despite the fact that the beginning of the project dates back to times when Austrian Development Co-operation principles and objectives were not yet firmly established, the approach over time reflects serious adaptation to today's objectives.
• Interventions from the Austrian side always had effectiveness as an objective.
For the most part, effectiveness was achieved, but in some cases, contractors
that were engaged failed to provide top-quality service, especially in the area of
design, equipment supply and installation.
• The efficiency of utilisation of funds is difficult to assess: Taking the extreme remoteness and the altitude of the Namche SHP site into account, its cost are favourable when compared with another project example. In absolute terms, costs
1
were exorbitant, at a level of more than 8’300 US$/kW of installed capacity, including transmission and distribution networks. Total spending, including the
institution building task, training and coaching, amounted to ATS 83.2 Million.
• In implementation, Austria has practically gone all the way alone, after attempts
in the area of partnership and local participation had failed. There is not much
evidence that considerable donor coordination, local participation and effective
partnership with national government or non-government institutions took place.
A certain degree of isolation was evident during the early construction phase, not
in the least due to the extreme remoteness of the project site.
• While both sexes unequivocally enjoy having and using electricity, it has probably
contributed most to improvements in the quality of women’s lives.
1
An exchange rate of 13 ATS for 1 $ was used.
Page 3
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
• As regards the environmental impacts, the outcome of the Thame hydro project
has been successful. There is no “dry river bed situation” during any period of the
year, as a direct impact of the scheme, and scars from construction have disappeared due to a major reforestation effort.
• A positive environmental impact has been achieved, as planned, by the partial
substitution of firewood by electricity for heating and cooking.
• The Namche SHP functions well under the management of KBC, despite a number of remaining flaws in the design and quality of civil structures and installations. KBC is technically capable and motivated to maintain and operate the
scheme.
• Sustainability may be judged by the success of KBC. In financial terms, the operation is still critical. It has not been possible to develop the load factor to its
maximum, and income from electricity sales is still insufficient. Depreciation, the
main financial instrument to build up reserves and thereby attain financial sustainability, has not been possible at all so far.
• On the basis of audited accounts up to 1999, the cash flow that KBC generated
was largely insufficient. However, in the most recent financial year ending in midJuly 2000, net surplus has increased by more than 300%. This is thanks to tariff
restructuring that became effective on 17 July 1999. KBC must increase its net
earnings still by a factor of 3 to 4 to achieve full financial independence and sustainability. A further step in this process has been taken by restructuring tariffs
and user levels again, effective from 16 December 2000.
• Sustainability may also be judged by the stability and quality of KBC as an institution. KBC appears to be well established and well run on the operative level. On
the level of strategy and long term business development, it lacks active leadership.
1.2.5
Lessons Learned for Sector Policy Development
Impact level
Electricity supply to rural areas can assist development activities and can substantially
improve living conditions. In Namche Bazaar, numerous economic development opportunities have opened up on the basis of electricity and the growing tourism industry.
Small hydropower is the most effective means of electricity supply in remote rural
The example set by Austria with the Namche SHP was adopted at the national level.
The Ninth Development Plan largely mentions the principles of the Namche institutional set up as the formula for future remote rural electrification.
Negative environmental impacts were kept in check, mostly by the reforestation activity
which became a part of the project.
There is a positive environmental impact of the project in terms of fuel wood substitution at the household level and in the tourism industry. A still greater impact is possible
by measures on the consumer side, such as energy saving and energy efficiency efforts.
Page 4
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
Policy level
New interventions bear a lot of risk in terms of commitment required
The interventions for the implementation of the Namche SHP have been new in terms
of current activities of the BMfaA at that time. The original intention for the project (to
build a small hydro scheme) was very different from what the BMfaA ended up with after almost 25 years of interventions. The lesson learnt is that projects of such complexity as remote rural electrification require persistence and the means to see the
intervention through.
A comprehensive and multi-level approach is advisable
A considerable number of other small hydro schemes in Nepal (and elsewhere) are
today on an institutional basis that is by far not as solid and sustainable as the Namche
Bazaar scheme today proves to be. To achieve this better result, Austria had to make
inroads into areas such as local ownership and institution building. The lesson learned
is: Interventions that have a significant impact need to be comprehensive. Interventions
cannot be limited to the level of the project but have to be extended to the policy level.
The time required to achieve success is often underestimated
The time requirement for interventions in the areas of infrastructure and institution
building cannot be stressed enough: The intervention in Nepal carried on for almost 25
years. Other examples show that significant results require 10+ years.
Considerable human and material resources are required
The previous lessons make it clear also that considerable human and material resources are required.
Setting priorities
Looking beyond the Namche Bazaar project, at the entire sector, it is relatively easy to
conclude broadly that the Namche SHP, perhaps on a par with the Swiss Salleri SHP
are among the “best” in the country. Both interventions were of a long term and comprehensive nature. Other donors have tried superficial interventions. Since resources
are likely to be scarce, and on the basis of the negative experience of others, interventions of a long term and comprehensive nature should take precedence over short-term
and superficial interventions,
Project Steering level
Context appropriate decisions and flexibility
Flexibility and openness to new issues coming up has been a constant feature of the
interventions, and this was necessary to achieve project success. The lesson: Flexibility will be required to be able to act appropriately in the specific context.
Effectivity: Streamlined procedures and short reaction time
Most of the time-delay factors are outside the sphere of influence of the donor. The
only area where the BMfaA can possibly make a difference is by streamlining its
administrative procedures as far as possible, and by making sure that personnel on the
various levels have the capacity to attend to matters on short notice.
Page 5
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
Efficiency versus control
In small projects such as the Namche SHP, for reasons of cost, different tasks need to
be executed by one single entity. This was done for efficiency reasons. It also resulted
in the lack of independent control.
The lesson learned: Improved implementation efficiency bears the risk of less control.
It requires competent and trustworthy partners.
Relationship with Austrian suppliers, consultants and others
The award of a supply contract is the basis for the relationship with any supplier. Quality and completeness of specifications determine the scope of supply. The difficulties
encountered had largely to do with stipulations that were inaccurate and too general,
which could not have been in the interest of the BmfaA.The lesson: It must be assured
that contracts are very specific and that tasks are assigned in detail. Independent
checking of supply and performance is important.
1.3 The Rangjung Small Hydro Project
1.3.1
Introductory remark
The Rangjung project, as defined by the Austrian input, differs from the Namche SHP
in its scope and co-operation pattern. The project is limited to the generation facility.
Transmission and distribution lines were not under the responsibility of the AustrianBhutanese co-operation. The Austrian supported Rangjung SHP was complemented
by a national rural electrification project under DOP, the Bhutanese national utility,
which established transmission and distribution lines with ADB and SNV (Dutch cooperation) financing and support. The Rangjung project is thus a fine example of donor
co-ordination and integration of multiple inputs under the overall co-ordination of the
partner government.
1.3.2
History
The Rangjung SHP project dates back to 1986 when the Austrian Development Cooperation responded positively to a request by the RGOB for assistance in the electrification of Eastern Bhutan. The Rangjung SHP plant with an initial capacity of 1.1MW
was planned by DOP to complement the existing Indian-funded mini hydro plants
which energised an existing grid of limited extension in Trashigang District. Following
feasibility studies and detailed design, actual plant construction was started in 1993
with the Austrian Design Engineer providing site supervision and construction management.
Construction was already well under way when in March 1994 an increase of plant capacity of the Rangjung SHP in view of new frame conditions was deemed necessary. It
was decided in August 1994 to double the capacity of the project in view of the low
output of the two existing mini hydro plants supplying the isolated Eastern grid and to
improve the economics of the Rangjung project. Due to the redesign, the plant was
commissioned in January 1996 after almost ten years of joint project planning and implementation.
In 1996, DOP staff had observed considerable abrasion damage on the turbine runners
at the Rangjung SHP. The problem was related to an insufficient capacity of the desanding facility whose size was not increased when it was decided to double plant capacity. For resolving the problem in the long run an additional desanding facility on the
Page 6
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
headrace and the procurement of two new spare runners was planned. This work,
partly funded by BMfaA, is currently on-going. Completion is planned for early 2001.
1.3.3
SHP Rangjung Status by the End of 2000
The Rangjung SHP has been operational for 5 years and load has risen sharply so that
during the winter evening peak hours, load shedding had to be introduced in the isolated mini grid of currently 450km length and close to 4000 consumers, mostly rural
households. Consumers complain about frequent blackouts and the inconvenience of
load shedding. DOP is trying to rectify the situation by installing back-up diesel generators and by accelerating the interconnection with the 60MW Kuri Chhu hydropower
plant which should be operational by the end of 2001.
1.3.4
Evaluation Results
• Objectives of the project have largely been achieved thanks to an effective cooperation effort between Austria and Bhutan and an above-average performance
of Austrian engineers and suppliers, and the Bhutanese project partner DOP.
• Up to commissioning of the project in 1996, project costs remained within budget
which is an outstanding achievement. Rehabilitation and repair work as a result
of slope instability and excessive turbine wear increased total project costs by
21% to ATS 86.8 Mio (US$ 7.5 Million.). But even with the unfortunate rehabilitation work, specific investment costs of around US$ 3400 / kW still make the
Rangjung SHP one of the most cost-efficient small hydro projects of the developing world built under a co-operation effort.
• The Rangjung project was conceived basically as an engineering undertaking
without directly addressing today’s chief objectives of Austrian development cooperation such as poverty alleviation, environmental conservation and genderbalanced development. Electricity supply was assumed to automatically have
positive impacts on development.
• The Rangjung SHP supported rural electrification which is a development activity
of high importance to RGOB. The project responded to the real needs of the targeted beneficiaries as is evident from the high connection ratios in the electrified
villages: on average 40% of households in Trashigang district are connected;
connection ratios reach 100% in the vicinity of the transmission lines.
• The technical sustainability of the Rangjung SHP is constantly threatened by
floods and landslides, a fact which no design or protection measure will ever be
able to fully remove.
• The economic viability of the plant will only be ensured when the Rangjung SHP
is connected to the transmission line from Kuri Chhu HEP and an economic use
of Rangjung excess power during off-peak periods is possible. Until such time,
the Rangjung operation must be subsidised.
• The economics of the project remain modest and the EIRR is only 0.5%. The
Rangjung project has thus not achieved the projected EIRR of 5.2% as per project approval documents of 1994. The reason for this lies in over-optimistic energy sales projections for the early years of plant operation and the extensive rehabilitation work.
Page 7
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
• But rural electrification in Bhutan is not measured along these economic lines.
Not only is electricity considered to be a basic need that has the potential to contribute to improving both the gross national product as well as the “gross national
happiness”, it is also considered a means to reduce the pressure exerted on the
environment from excessive fire wood use.
• The Rangjung SHP project has brought about a significant shift in energy consumption patterns away from the traditional firewood and kerosene fuels to electricity. An electrified household uses about 25% less firewood than a nonelectrified thanks to partial fuel wood substitution in cooking and water boiling.
• Consumers are using electricity mostly for domestic purposes, and little productive use has emerged. However, the population in the project area is much more
enthusiastic and grateful about the project and its impacts than the economic and
social indicators would suggest.
1.3.5
Lessons Learned for Sector Policy Development
Impact level
• If given sufficient time to get fully operational, electrification projects do have a
positive impact on social development since electricity is linked to modern life
and it has thus the potential to change the attitudes of the rural population.
• Quite to the contrary of expert opinion, a positive environmental impact of rural
electrification in terms of fuel wood substitution at household levels can take
place. In Rangjung this is due to the DOP strategy of providing high-powered
connections at tariffs below generation costs.
• Economic development takes off on a slow pace following electrification of the
project area as there is – in the case of Rangjung - only a limited number of economic niches available that can thrive through the use of electricity.
Policy level
• Human resources development (HRD) has been the most effective intervention
that generated effects beyond the Rangjung project proper. But the training
measures implemented are not comprehensive enough to substantially reduce
the Bhutanese dependence on foreign expertise in small hydro development.
• The Rangjung project has successfully brought about a shift in Bhutanese project
implementation concepts. Initially conceived as a turn-key project, the Rangjung
SHP project was gradually converted into a partnership approach. The lesson
learned is that development co-operation must interfere in partner concepts and
believes in order to contribute to development and change.
• Sensitive, process-oriented issues and policy development can only become
components of co-operation when credibility has been achieved through
successful (hardware and input-oriented) projects such as the Rangjung SHP.
Project steering level
• BMfaA’s in-house project steering and management - though time-consuming proved to have the right pace for a development co-operation project. It allowed
Page 8
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
the BMfaA to thoroughly consider development co-operation principles and objectives in all its decisions.
• When introducing a technology (small high-head hydro) into a new environment
(the Himalayas), the quality of the design work can only be assured through regular independent reviews by other experts. Such “second- opinion” consultation
should be an integral part of the project set-up right from the start and not only
when failures have occurred.
1.4 Overall Comparison of Both Projects
1.4.1
Project Features
Project feature
Rangjung
Namche Bazaar
Intended power supply
To mini grid
Stand alone
Plant capacity
2.2 MW
0.63 MW
Plant type
High head, runof-river
High head, runof-river
Power transmission & distribution
line length
450 km
13 km
People served (capita)
23’000
3’000
Installed capacity per capita
served
0.1 kW
0.21 kW
Transmission distance
per capita served
19.6 m
4.3 m
Total cost to Austria (ATS)
86.9 Mio
83.2 Mio
ATS per kW installed (power
plant)
39’500
54’600
ATS per kW installed, incl.
Transmission + Distribution
n.a.
132’000
ATS per capita
3’780
27’730
Figure 1:
Technical and cost data for Rangjung and Namche Bazaar SHP
Technically speaking the two schemes are of the same type and both belong to the
small hydro size range. Capacity-wise, Rangjung is about 3.5 times larger than Namche.
1.4.2
Achievement of Austrian Development Assistance Objectives
The question is which one of the projects have better served Austrian development cooperation objectives? The answer is that considerable achievement has been possible
in both projects, but in different ways and on different levels.
While Rangjung significantly contributed to reaching Bhutanese rural electrification targets (physical infrastructure development), the Namche project stands out in terms of
institutional model development in rural electrification but does little to physically improve rural electrification ratios in Nepal. This difference in achievement is a result of
the different paths that the projects have taken through their long histories. Both pro-
Page 9
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
jects assumed a pioneering role in establishing the Austrian development co-operation
in the partner countries. Despite the different routes, both approaches proved to be
relatively successful in terms of achieving development co-operation objectives:
• Project ownership has been achieved in both projects but at different levels;
• Sustainability is assured in both projects if certain conditions are fulfilled in the future
Intended beneficiaries as well as the environment have benefited in both projects
but at different scales and depths.
1.5 Conclusions
From an engineering point of view, both projects have been implemented successfully,
despite remaining design and implementation flaws. In the case of the Namche Bazaar
SHP costs have been exorbitant. Overall, the efficiency of spending money appears to
be better in the Rangjung project.
In Namche SHP, sustainability is directly in the hands of the beneficiaries. In financial
terms, KBC has not achieved sustainability so far, but it is on a good course. The
Rangjung SHP is under national ownership. Its sustainability does not depend on local
initiatives but is determined by the strategy of the national government. The
sustainability of the Rangjung SHP is threatened as soon as it no longer fulfils a vital
role in electrifying Eastern Bhutan.
Both projects assumed a pioneering role in establishing the Austrian development cooperation in the partner countries. Despite the different routes, both approaches proved
to be successful in terms of achieving development co-operation objectives. Environmental concerns are successfully addressed by both projects, mainly due to successful
(but only partial) fire wood substitution. Social issues of gender equality and poverty
reduction were not explicitly addressed in the implementation of the projects. However,
it has become apparent that women, who are generally in the role of housekeeper,
benefit more from electricity than men while economic opportunities are slightly more
favourable for men.
The Namche SHP is one of the first examples in Nepal of private sector and community ownership in rural electrification. It is a successful pioneering project in this respect. The model developed in Namche Bazaar has implicitly been adopted for remote
rural electrification in the 9th Development Plan of HMG. The Rangjung SHP was used
by the Bhutanese partners to reduce the massive Indian dependence in the power sector.
In Namche, on a local level, the acceptance rate of electricity has been 100%. The
same rate has been achieved in Bhutan in all areas within reach of the grid powered by
Rangjung SHP. Human resources development (HRD) and concept development have
been the most effective interventions that generated effects beyond the projects. Training measures implemented under the Rangjung and Namche SHP were mostly on the
level of operational staff.
Development co-operation must be willing to interfere in partner concepts and believes,
in order to contribute to development and change to the general benefit of the population and the environment. Sensitive, process-oriented issues and policy development
can only become components of co-operation when credibility has been achieved
through successful (hardware and input-oriented) projects.
Page 10
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
1.6 Recommendations
1.6.1
ÖEZA Sector Policy
Small hydropower development should remain the general theme of Austrian assistance to the energy sector not only because of Austria’s comparative advantage and
the experience in the BMfaA with this technology, but more so because of the inherent
potential of small-scale hydro electric development to induce change at the target
population and its many inter-linkages with the environment, the economy and the service sectors as well as its positive impact on gender balanced development.
In concrete terms, the Austrian energy sector policy for Nepal, could manifest itself in
the following:
• Co-ordination with HMG and other donors in the energy sector on balanced subsidy policies;
• Capacity building at meso and macro levels to further develop and disseminate
the concept of community-owned hydropower and democratic rural electrification
development;
• Development of technical concepts that enable a gradual adaptation of power
supply to the growing power demand of communities and avoid establishing large
capacity reserves during the early project stages;
• Capacity building in the field of project finance in collaboration with administrators
of power development funds (to be provided by the World Bank and KfW, Germany), private investors and banks as well as GEF funding where applicable.
In Bhutan, the Austrian sector policy could be substantiated through the following:
• Development of decentralised organisational and management concepts for
small-scale hydropower and rural electrification schemes in remote areas of Bhutan, suitable to reduce costs for DOP. Make maximum use of the Namche experience;
• Assistance to the development of the legal and administrative framework for the
above decentralisation concept at national level;
• Capacity building for rural electrification and rural energy development planning
at national level;
• Skills development at local private consultants in the field of plant design and
construction;
• Capacity building in the field of project finance including the bundling of projects
and funding agencies to increase financial volume and to reduce transaction
costs respectively.
In both countries, co-operation on conceptual issues and capacity building will only be
accepted by partners if funding support for physical infrastructure deployment is provided through Austrian facilitation. This need not and should not be pure grant financing for demonstration projects but should include loan funding, GEF contributions and
private investment with guarantees by the donor. It is further recommended that the
following aspects be observed when implementing the above policies:
Page 11
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
• Comprehensive interventions will require a commitment for a long-term engagement where results cannot be expected within a two to three-year period but
rather after five to ten years of co-operation.
• Administrative procedures of the Austrian development co-operation should be
streamlined and given sufficient specialist resources such as for example through
regular independent reviews of project designs and interventions.
• Regular collaboration and networking between Austrian partners in the two countries as well as with national and regional institutions and associations working in
the same fields is imperative. Appropriate forums must be supported to this effect.
1.6.2
Regarding the Namche Bazaar SHP
A number of recommendations have been formulated in section 6.1.3 to provide an
input, based on the evaluation results, to make still further improvements in:
• Organisational structure
• Operation and maintenance of the scheme
• Revenue development
• Accounting practises
• Strategic thinking about future developments
1.6.3
Regarding the Rangjung SHP
• Provide engineering support in rectifying the poor reliability and safety of supply
from the Rangjung SHP and associated transmission and distribution grid;
• Maintain a residual flow in the by-passed section of the Karthiri River in order to
reduce the negative impacts on the aquatic life, especially when continuously
supplying maximum capacity to the Indian market;
• Make sure that a well-elaborated and easy-to-use maintenance plan (e.g., computer-based) is adhered to by Rangjung powerhouse staff and that a spare-part
inventory is established.
• Improve recording and accounting of electricity generation and sales so that system losses can be evaluated and ultimately be reduced.
Page 12
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
TABLE OF CONTENTS
1.
Executive Summary
2
1.1
1.2
Background
The Namche Bazaar Small Hydro and Rural Electrification Project
2
2
1.2.1
1.2.2
1.2.3
1.2.4
1.2.5
2
2
3
3
4
1.3
1.4
1.5
1.6
Introductory remark
History
SHP Namche Bazaar Project Status by the end of 2000
Evaluation Results
Lessons Learned for Sector Policy Development
The Rangjung Small Hydro Project
6
1.3.1
1.3.2
1.3.3
1.3.4
1.3.5
6
6
7
7
8
Introductory remark
History
SHP Rangjung Status by the End of 2000
Evaluation Results
Lessons Learned for Sector Policy Development
Overall Comparison of Both Projects
9
1.4.1 Project Features
1.4.2 Achievement of Austrian Development Assistance Objectives
9
9
Conclusions
Recommendations
10
11
1.6.1 ÖEZA Sector Policy
1.6.2 Regarding the Namche Bazaar SHP
1.6.3 Regarding the Rangjung SHP
11
12
12
Table of Contents
13
Table of Figures
16
List of Abbreviations and Acronyms
19
2.
Introduction
20
2.1
2.2
2.3
2.4
2.5
Background
Objectives and Scope of the Evaluation
Methodology
Project terminology used
Structure of the report
20
20
21
22
22
3.
Small Hydro Project Namche Bazaar, Nepal
23
3.1
Project History
23
3.1.1
3.1.2
3.1.3
3.1.4
3.1.5
23
25
27
27
29
3.2
3.3
Project Identification and Appraisal
Project Implementation
The establishment of KBC
Initial Operation, Rehabilitation and Repairs
Follow up
Project Approach and Performance
30
3.2.1 Objectives, Results and Activities of the Austrian Intervention
3.2.2 Project Planning and Implementation Set-up (institutional map)
30
31
The Present Status
34
3.3.1 Technical Features
34
Page 13
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
3.3.2 Institutional set-up
3.3.3 Development of sales and income
37
38
Specific Questions and Main Findings of the Evaluation
43
3.4.1 Programming
3.4.2 Need-Driven Intervention
3.4.3 Participation and Donor Co-ordination
3.4.4 Techno-economic Evaluation of Namche SHP
3.4.5 Project Effectiveness and Efficiency
3.4.6 Impacts on population and resource base
3.4.7 Gender aspects
3.4.8 Environmental impacts
3.4.9 Sustainability of project institutional structures
3.4.10Project Steering
3.4.11Lessons Learned for Sector Policy Development
43
43
45
46
49
50
61
63
65
67
68
4.
Small Hydro Project Rangjung, Bhutan
72
4.1
Project History
73
4.1.1
4.1.2
4.1.3
4.1.4
4.1.5
73
73
73
74
74
3.4
4.2
4.3
4.4
Project Identification and Appraisal
Project Implementation
Re-optimisation and Re-design
Rehabilitation I
Rehabilitation II
Project Approach and Performance
75
4.2.1 Objectives, Results and Activities of the Austrian Intervention (Logical Framework)
4.2.2 Project planning and implementation set up (institutional map)
75
76
The Present Status
78
4.3.1 Waiting for Kuri Chhu
4.3.2 Rapid line extensions into the rural areas
4.3.3 Ongoing Plant Modification and Rehabilitation
78
79
81
Specific Questions and Main Findings
82
4.4.1 Programming
4.4.2 Need-Driven Intervention
4.4.3 Participation and Donor Co-ordination
4.4.4 Techno-economic Evaluation of Rangjung SHP
4.4.5 Project Effectiveness and Efficiency
4.4.6 Impacts on population and resource base
4.4.7 Gender aspects
4.4.8 Environmental impacts
4.4.9 Sustainability of Project Institutional Structures
4.4.10Project Steering
4.4.11Lessons Learned for Sector Policy Development
82
84
88
92
103
106
115
116
117
119
120
5.
Overall Comparison of Both Projects
123
5.1
Project Cost, Technical and Institutional features
123
5.1.1
5.1.2
5.1.3
5.1.4
123
124
125
125
5.2
6.
Project Features
Comparison of Impact Potential and Visible Impact
Institutional Set Up and Ownership
Achievement of Austrian Development Assistance Objectives
Socio Economic Analysis and Comparison
127
5.2.1 Consumer Profiles
5.2.2 Other Electricity Use
127
133
Conclusions and Recommendations
138
Page 14
ÖEZA, Projekt 1389
6.1
6.2
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
Conclusions
138
6.1.1
6.1.2
6.1.3
6.1.4
6.1.5
138
138
138
139
140
Success of Implementation
Project Sustainability
Project Approach and Steering Mechanisms
Achievement of ÖEZA objectives
Impact
Recommendations
140
6.2.1
6.2.2
6.2.3
6.2.4
140
141
144
145
Background
Policy recommendations (BMfaA)
Recommendations for KBC regarding the Namche Bazaar SHP
Recommendations to DOP regarding Rangjung SHP
Annex
147
1.
Terms of Reference for the Evaluation, derived criteria and indicators
2.
Effective time schedule for the evaluation
3.
List of persons met, institutions visited
4.
Economic Analysis of the Rangjung SHP
5.
Questionnaires used for household surveys
6.
Survey Data Namche Bazaar, Nepal
7.
Survey Data Rangjung, Bhutan
Page 15
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
TABLE OF FIGURES
Figure 1:
Technical and cost data for Rangjung and Namche Bazaar SHP 9
Figure 2: Location of ÖEZA Projects evaluated, on the Indian sub-continent 20
Figure 3: Relief Map showing the Namche Bazaar SHP project area in the Sagarmatha
National Park in Solu Khumbu District in Eastern Nepal.
23
Figure 4: Log Frame Matrix of the Namche Bazaar Small Hydro Project
30
Figure 5: Institutional Map of the Namche Bazaar Small Hydro Project
32
Figure 6: The area and villages covered today by the Namche SHP; the red line represents the
transmission line
34
Figure 7: The intake area of the Namche SHP at Thame; in the foreground the desander35
Figure 8: The two sets of double-jet Pelton turbines with synchronous generators, in the
background the control and switch gear panels36
Figure 9: Along the transversal course of the penstock, considerable slope stabilisation had to
be implemented with high retention walls and shrub planting.
36
Figure 10: Organisation chart of KBC 37
Figure 11: Trend of load development in the Namche SHP
38
Figure 12: Recent development of sales income from electricity 39
Figure 13: Namche SHP: A typical daily load curve in the peak (tourist) season
40
Figure 14: Namche SHP: Development of KBC electricity connections by load level category
40
Figure 15: Namche SHP, KBC tariffs in effect since 16 July 1999
41
Figure 16: Namche SHP, KBC tariffs in effect since 16 December 2000
Figure 17: Table showing costs of different SHP’s in Nepal
41
50
Figure 18: Mostly tourists are customers of an e-mail business at Namche Bazaar 51
Figure 19: Household fuels used in the Namche Bazaar area
54
Figure 20: Locally available hot plate or electric coil in a local home
56
Figure 21: Ownership of electric appliances 57
Figure 22: The Head Master of Khunde High School with an array of Media Equipment
Figure 23: Women of the Thame Women’s Association being interviewed
Figure 24: Ranking of Development Priorities
59
62
62
Figure 25: Relief map of Bhutan showing the Rangjung project area in the remote Eastern
districts of Trashigang and Trashiyangtse.
72
Figure 26: Log Frame Matrix of the Rangjung SHP 76
Figure 27: Institutional Map of the Rangjung Small hydro Project
77
Figure 28: Load development of the Rangjung Small hydro Plant since commissioning in Jan.
1996. Note the seasonal peak load variations with rapidly increasing peak loads
during the winter seasons and the somewhat reduced peak loads in summer (July,
August, September). 78
Figure 29: Supply area of the Rangjung MHP. Only the major transmission lines are shown,
distribution and short spur lines are not shown. The mini grid to Pemagatsel is
Page 16
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
currently not interconnected with Rangjung (at Khaling). The line from Kuri Chu
(Mongar District) is under construction (dashed line). 79
Figure 30: Growth of number of consumers since commissioning of the Rangjung SHP
80
Figure 31: Growth of electricity consumption since commissioning of Rangjung SHP
80
Figure 32: The double-basin sand trap under construction in December 2000 81
Figure 33: The transportation path along the penstock alignment has been widened by the local
population to become their main access track 83
Figure 34: Electrification ratios (% electrified households to total number of households per
Gewog) in the Trashigang and Trashiyangtse districts
84
Figure 35: Ranking of development priorities from household interviews (sample of 329
households in Trashigang and Trashiyangtse Districts)
85
Figure 36: Sector-wise allocation of development spending in the Bhutanese Eighth Five-Year
Plan (1997 – 2002) 86
Figure 37: Budget allocations to the power sectors of various Asian countries86
Figure 38: Rural Electrification Spending / Targets according to the Bhutanese Five-Year Plans
87
Figure 39: Co-ordination and communication pattern during Rangjung SHP implementation
89
Figure 40: Energy consumption pattern of non-electrified households in the project area from
three different surveys
92
Figure 41: Energy consumption pattern of electrified households in the project area 93
Figure 42: Sources of household energy in the project area (excluding transportation and
agricultural activities)
93
Figure 43: Generation and sales figures for Rangjung and Khaling power stations
95
Figure 44: O&M costs as an indicator for the cost-effectiveness of the Rangjung SHP and its
associated transmission and distribution grid 97
Figure 45: Staff performance of Rangjung SHP supplied area in comparison with other supply
areas and utilities. 98
Figure 46: Pipe bridge crossing the potentially unstable slope on the Rangjung headrace 99
Figure 47: Current tariffs paid in the Rangjung SHP supply area (exchange rate: 46 Nu/US$)
100
Figure 48: Electrical spare-part store at the Rangjung powerhouse
Figure 49: Cash flow Analysis Rangjung SHP
101
103
Figure 50: Final project costs after modification and repair work 105
Figure 51: Back strap weavers at the Weaving Centre in Khaling
Figure 52: Household fuels used in the Rangjung area
108
Figure 53: Ownership of electric appliances in the Rangjung area
Figure 54: Cooking at Sherubtse College, Kanglung
107
109
112
Figure 55: Computer room at Sherubtse College, Kanglung, in the dark as another black-out
occurred at the time of visiting the establishment.
113
Figure 56: Typical Bhutanese farm house with electricity supply and satellite dish
114
Figure 57: Technical and cost data for Rangjung and Namche Bazaar SHP 123
Figure 58: Main impact figures for Rangjung and Namche Bazaar SHP
124
Page 17
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Figure 59: Institutional and Co-operation issues
125
Figure 60: Achievement of ÖEZA Objectives and related Concerns
Figure 61: Population data of the project areas
Figure 62: Size of surveyed households
Final Report
127
128
130
Figure 63: Namche Bazaar, Solu Khumbu’s most important trading and tourist town130
Figure 64: Typical hamlets of relatively disbursed households in the Rangjung SHP supply area,
Eastern Bhutan.
131
Figure 65: Occupational data of project areas
132
Figure 66: Occupations in electrified and non-electrified households
132
Figure 67: Electric Bakery in Namche Bazaar; a profitable commercial use of electricity
Figure 68: Cyber Café in Namche Bazaar; the highest in the World?
133
134
Figure 69: Doctor’s practise at the Khunde Hospital in the Namche SHP area
135
Figure 70: A porter on the steep approach to Namche carrying empty water bottles for the local
factory. 136
Figure 71: Spheres of intervention in hydropower development 142
Page 18
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
LIST OF ABBREVIATIONS AND ACRONYMS
ADB
Asian Development Bank
AFC
Austrian Federal Chancellery
ATS
Austrian Shilling (currency)
BMfaA
Austrian Federal Ministry for Foreign Affairs (succeeded AFC in
handling Austrian development co-operation in January 1995)
DOP
Department of Power, Ministry of Trade & Industry, Bhutan
Dzongkhag
District in the Bhutanese administrative system
EIRR
Economic Internal Rate of Return
ESSU
Electricity Supply sub-unit
ESU
Electricity Supply Unit (sub-entity of DOP Bhutan)
GEF
Global Environment Facility
Gewog or Geog
Block in the Bhutanese administrative system
GLOF
Glacial Lake Outburst Flow
GWh
Energy Unit 1’000 MWh = 1’000’000 kWh
HRD
Human Resources Development
HMG
His Majesty’s Government (of Nepal)
IPP
Independent Power Producer (private sector generation)
KBC
Khumbu Bijuli Company Pvt. Ltd.
kW
Kilowatt = 1000 Watts, Power Unit
kWh
Kilowatthour, Energy Unit
MW
Mega Watt, Power Unit = 1000 kW
MWh
Mega Watt Hours, Energy Unit = 1000 kWh
NEA
Nepal Electricity Authority
Nu
Bhutanese Currency (at par with Indian Rupee)
NGO
Non-Government Organisation
NRs
Nepalese Rupee
RGOB
Royal Government of Bhutan
SHP
Small Hydropower Project
SHPD
Small Hydropower Directorate of NEA
SNP
Sagarmatha National Park (in the Everest/Namche area)
VDC
Village Development Committee (Nepal)
Page 19
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
2. INTRODUCTION
2.1 Background
Hydropower is one of the most important resources for the ecologically sensitive Himalayan region both from the point of view of environmentally compatible energy supply
as well as for the export market and the improvement of trade balances of Himalayan
countries. The development of hydropower as a renewable energy source has been
the cornerstone of Austrian Development Co-operation in Nepal and Bhutan. The Austrian aid budgets to the sector have been considerable over the last 15 years.
Projects of ÖEZA
Figure 2: Location of ÖEZA Projects evaluated, on the Indian sub-continent
The Austrian engagement in the hydropower sector is embedded in today’s main focal
points of development co-operation such as poverty alleviation and resource protection. However, the Austrian projects are also characterised by the transfer of specific
Austrian (hydropower) know-how and by Austrian economic interests.
2.2 Objectives and Scope of the Evaluation
Despite the extended support to the Nepalese and Bhutanese energy sectors by the
Austrian Government, the usefulness and the impact of the 15-year long Austrian engagement has never been evaluated. A verification of the project achievements and
the main project impacts was therefore overdue and a contract for an evaluation was
awarded to ENTEC AG, Consulting & Engineering, Switzerland in September 2000.
The main purpose of the evaluation is to quantify the relevance, the impact and the
sustainability of the Austrian contribution and assistance to the sector. It is expected
that the evaluation derives a number of policy guidelines for future interventions of the
Austrian Development Co-operation in the energy sector.
The evaluation comprises three distinct areas of study:
Page 20
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
A qualitative and quantitative evaluation of the planned interventions, the
achievements during project implementation and its impact
The degree of sustainability of the mini hydro projects as achieved by the Austrian interventions and their complementary measures
The suitability and acceptability of the policies, procedures and structures devised and implemented in the course of project implementation
The scope of the evaluation includes document study, key-informant interviews and
field surveys of short duration for data collection and verification. A scientific assessment and evaluation of the main socio-economic and ecological impacts has not been
undertaken due to budgetary and time constraints. Field surveys were conducted in
October 2000 (by local experts using questionnaires) and in November / December
2000 (by international experts).
2.3 Methodology
Based on the specific questions of the terms of reference compiled by the BMfaA, a set
of evaluation criteria and associated indicators have been defined (see Annex 1). The
qualitative information and quantitative data required by the indicators have been gathered through document study, key informant interviews and field surveys at the power
plants, the surrounding environment and at the districts connected to the power plants
(see Annexes 5 for the questionnaires used and 6 + 7 for raw survey results of Namche and Rangjung respectively).
The results of the surveys and investigations were then compared with the stated targets in the planning documents and/or with the results and achievements of other programmes in the energy sector which are considered as the benchmarks and the best
practice of the “industry”. The analysis of the results, why the targets have been
reached or not, why the Austrian projects did better or worse than the programs considered as “best-practice” was the main subject of the work. A number of instruments
and methods have been used for the analysis:
Project phasing: The projects were structured for the analysis work according
to the various phases of the Austrian interventions which had led to particular
decisions and processes (project identification and appraisal, project implementation, etc.). Key informants from Austria as well as from Nepal and Bhutan have been selected based on these different phases and milestones of
achievements and decisions taken.
Logical framework matrix: stated objectives, activities and expected output of
the projects have been brought into a causal relationship. The matrix provided
a way of checking whether the projects had been well designed and thought
out and whether the expected outputs and impacts have been achieved.
Institutional map: The relationship between the various organisations and institutions involved in the project are shown graphically. Such presentations provided a means to quickly gain an overview on who played what role and
whether the Austrian intervention was targeted at the right levels and
organisations to achieve the objectives.
The evaluation was carried out by a team of three international consultants with engineering, economic and socio-cultural backgrounds. This team was assisted on the one
hand by local small hydro and social survey specialists in Nepal and Bhutan and on the
other hand by a pool of experts at the home office of ENTEC, who were consulted for
Page 21
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
specific know-how and “best practice” information in the fields of rural electrification,
environmental impact assessment, institutional analysis and policy issues.
2.4 Project terminology used
Hydropower development is often referred to as Pico Hydro, Micro Hydro, Small Hydro,
Mini Hydro, Medium Hydro and Large Hydro by the international development community, depending on the size in terms of installed output capacity, beginning from extremely small (around 1 kW for Pico) through Micro (commonly less than 100 kW), to
Mini (less than 1 MW), or Small, (less than 10 MW), extending to Medium (up to 30
MW), and Large (above 50 MW). No consistent standard exists when it comes to the
definition of the limits of each term. Moreover, other terms, such as Hydel (for Hydro
electricity development), and “RE development using Hydro” (RE = Rural Electrification, but also Renewable Energy), are used for the same topic.
To add to the confusion, abbreviations used are commonly PHP, MHP, SHP, etc. MHP
may refer to Micro Hydro Power, but also to Mini, and Medium sized hydro power.
In international usage, projects are most often identified by assigning the name of the
river being developed to them. If not the name of the river, the name of the village
closest to the power scheme site, is used. All this notwithstanding, for the two projects
evaluated, the following consistent terms are used:
In Nepal: Namche Bazaar Small Hydro Project, or Namche SHP, because: a) it has
most often been named like this throughout project history, and b) it reflects the scope
of the project better by naming it after the main distribution area, rather than after the
relatively small place of Thame, where the intake is situated. Also, Small is the correct
translation of the term “Klein”(wasserkraft) used in the German language.
In Bhutan: Rangjung Small Hydro Project, or Rangjung SHP, because: a) it has
most often been named like this throughout project history, and b) it reflects the more
limited scope of the project, by naming the project after the site of the generating facility rather than the distribution area.
Other terms used: Scheme is a synonym to project, whereas Hydro Plant refers more
specifically to the generating facility alone.
2.5 Structure of the report
Chapters 1 and 2 are summarising the results of the evaluation and give general information about the methodology used and the structure followed.
The analytical part is contained in chapters 3 and 4 for Nepal and Bhutan respectively.
The chapters begin with the descriptive part, giving facts and figures as have emerged
from the data collection and study. The order is chronological, from planning and implementation to the present day status. This is followed by analysis: Answers are given
in response to the specific questions of the terms of reference, and in the sequence as
given in the terms of reference.
Finally, since the evaluation of both projects has been regarded as a single coherent
effort, facts and figures as well as evaluation results are compared in chapter 5. The
attempt at applying the same yardstick to both projects has not been entirely successful, because the different nature of the two projects required different emphasis in
evaluation. In the view of the authors this could not possibly have been avoided.
Conclusions and recommendations complete the report in chapter 6.
Page 22
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
3. SMALL HYDRO PROJECT NAMCHE BAZAAR, NEPAL
3.1 Project History
Figure 3: Relief Map showing the Namche Bazaar SHP project area in the Sagarmatha National Park in Solu Khumbu District in Eastern Nepal.
The project area roughly covers the VDC areas of Namche Bazaar and Khumjung.
3.1.1
Project Identification and Appraisal
Early History2
The beginnings of the project reach back to 1976. The first power scheme was initiated
by the Austrian export industry and it was based on a Norwegian study which had investigated several sites on the level of pre-feasibility. The objective of this initiative was
2
From „Projektgeschichte des Kraftwerks Namche Bazaar; DI Hans-Georg Danninger, BMfaA, September 1995
Page 23
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
to establish a scheme for reference purposes. From among the sites proposed in the
pre-feasibility study, a site on the Bhote Kosi in the vicinity of the village Thamo was
chosen. The company Verbundplan of Austria was commissioned with the detailed
study for a 650 kW run-of-river scheme.
Negotiations were taken up simultaneously with the Finance Ministry of HMG, his Majesty’s Government (of Nepal). It was initially agreed that Austria would provide six turbines with the associated electro-mechanical equipment, whereas from the Nepalese
side, costs for all construction was to be taken over. In the course of negotiations, the
Nepalese government found itself unable to meet total construction costs. The Austrian
contribution was therefore limited to four units of the electro-mechanical equipment, but
also expanded to include a financial contribution of ATS 3 Million towards construction
cost. An agreement to this effect was signed between the Austrian Federal Chancellery
and the Finance Ministry of HMG. At this stage, the Nepalese project partner NEA
(Nepal Electricity Authority), had already initiated preparations for construction. Detailed planning was concluded in 1979, and construction started with the signing of the
agreement 1980. the company Verbundplan undertook to provide some degree of construction supervision. The final design was submitted by Verbundplan in March 1982,
and local construction started at the beginning of 1983. The consultants Posch + Partners were entrusted by the Austrian government to complete all remaining design
works and to handle all necessary construction supervision in May 1985. It was estimated at that time, that the project could be completed by the end of 1987.
A natural calamity and a new project site
On 4 August 1985, the construction site at the Bhote Kosi was completely destroyed by
a Glacial Lake Outburst Flood (GLOF) that originated from the Langmoche glacier and
the Dig Cho lake at its foot, discharging flood water into the Langmoche Khola, a small
tributary to the Bhote Kosi further upstream from the project site. The magnitude of the
flood was unheard of at that time. Estimates put the flow volume at 2’000 m3/s, while
3
the scheme was designed to withstand a flood of 100 m3/s. It is apparent that any attempt in design and construction would have been futile to cope with such an enormous flood and as a consequence to the damage that had occurred, the site was
abandoned. The financial loss to Austria was put at approximately ATS 2 Million. Fortunately, supply contracts for the equipment had not been awarded yet at the time of
the incident.
In the course of the investigation of the damaged construction site, a new site was
identified. This site appeared more favourable: it was removed from the unpredictable
Bhote Kosi, situated on the Thame Khola. Also, in contrast to the previous site, the new
site had the potential to be developed as a high head scheme. This appeared to be an
advantage, because with a higher head less volume flow is required for the same output, thus also reducing the sediment removal problem.
The Austrian government, not having fulfilled its contractual obligations towards HMG
at the time of the natural calamity, felt compelled to further assist NEA. A feasibility
study was therefore commissioned on the basis of the new site. This established the
techno-economic feasibility and was the basis for an amendment to the agreement with
the Finance Ministry of HMG.
3
Namche Bazaar Hydro Power Development: Outlining proposals for organisation, management and tariff structure,
Posch+Partners, Innsbruck, Rev.1, February 1989
Page 24
ÖEZA, Projekt 1389
3.1.2
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
Project Implementation
Sharing of tasks between HMG and BMfaA
In the amended agreement of 1986, all tasks were assigned, not only for the construction of the Small Hydro scheme, but also for the transmission lines and the distribution
network. NEA was to be responsible for overall project execution, and an Austrian consultant was charged with a supervision function in an advisory capacity to NEA.
Slow progress of construction
4
Construction began in 1988. Due to cumbersome and ineffective procedures of
awarding contracts, numerous delays occurred. Some of the contractors, lacking work
experience under extremely remote high-altitude conditions, could not execute their
tasks and contracts had to be re-negotiated. Also, difficulties in budget allocation from
the Finance Ministry to NEA made it necessary to direct some of the work, especially
transportation, through the consultant. The latter, in turn, caused further delays due to
unavailability of his advice at the site, as and when necessary. In the view of the electrical contractor and the consulting engineer, the required administrative process with
Austrian authorities also contributed to slow progress.
By July 1989 current planning foresaw construction of the powerhouse in the spring
construction season of 1990, and considerable progress in the construction of transmission and distribution was to be made. At-site welding of the penstock pipes supplied
from Kathmandu, was also to be done in spring 1990.
Tendering for the supply of the electro-mechanical equipment, on the other hand, was
already done during 1986. The supply contract was awarded to the consortium Geppert/Fiegl+Spielberger for the hydraulic-mechanical equipment and electrical equipment respectively in December 1987. Acceptance inspection of the delivery was done
at the works of the supplier in Austria in March 1988.
Costly transportation
More than one year later, the equipment, consisting of 5 containers of 20’, and 122 cable drums, arrived in Kathmandu, via Calcutta, on 21 July 1989.
By this time, transportation of local materials, such as penstock sections and cement,
was under way. However, the trade-treaty crisis with India and general inflation resulted in much higher cost of transportation than anticipated. A budget worked out in
late 1989, and taking account of expected price increases, shows a total of 116.7 tons
of cargo for STOL aircraft (Twin Otter) transportation and 90.8 tons of helicopter cargo,
as well as 25.9 tons for porter carriage from Lukla to Thame, at a total estimated cost
of ATS 5’500’000.--. This represents more than 10% of construction and equipment
cost for local transportation alone!
Collaboration with SHPD
Due to the various difficulties encountered, and due to budgetary constraints, the collaboration with SHPD was under a strain at the best of times. With democratisation developing in the country in 1991 and the associated decentralisation and privatisation
trends, SHPD ceased to play an executing role in the project, after it had formally done
4
HMG regulations prescribe among other requirements, that at least three offers must be evaluated, and that the offer
giving the lowest cost needs to be considered. Quality of work and reliability of the contractor are almost non-existing
criteria in this procedure.
Page 25
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
technical acceptance tests. However, this happened at a time, when transmission and
distribution were incomplete. This forced the Austrian side to bring the project to an
end by itself. Also, it opened up the opportunity for the discussion of local ownership
models for the project with HMG.
Training of local personnel
Training of personnel had started 1992. 12 young men were trained for one year in a
technical training institution in Kathmandu (BTTC), and selected members of the team
were also trained in Austria, at a local electricity utility. After the basic training, on the
job training took place at the site under the charge of the Austrian contractor responsible for transmission and distribution installation work. Also, a team of 5 were sent to
Austria for a welding course, and the assigned manager of the utility received very brief
management training in Austria.
KBC staff were also trained at BTTC in Kathmandu in the installation of drinking water
and waste water schemes during 1998. In addition, the technical manager of KBC was
trained for a short period in Austria.
Studies of possible institutional set-up for power scheme ownership and operation
5
The contract of Posch + Partners was extended as early as 1987 to include a study on
a possible institutional set-up for the operation of the Small Hydro scheme. The various
tasks for the study included the following:
• the analysis of the institutional development of the organisation proposed to own,
operate and manage the Namche Bazaar electricity system, including an outline
of its legal basis
• the financial, social and economic analysis of demand and load management
• special measures required to substitute fire wood by electricity
A number of alternatives were evaluated against a set of criteria, and it was concluded
that a joint ownership share company would be the most suitable. User associations,
NEA and the National Park (SNP) were anticipated to become shareholders. The proposal broadly constituted the institutional model adopted by the Salleri-Chialsa Small
Hydro scheme further to the South in Solu Khumbu. The study also included an analysis of the financial viability at different cost recovery levels. In order to increase the income from electricity sales at an early stage, a “positive” electricity connection model
was proposed, i.e. it was suggested to connect relatively large commercial consumers
with preference to generate income from sales of electricity.
6
Another, subsequent study also favoured a role by SNP. It also was very critical of a
role by NEA, citing a poor image on the local level and a disinclination in other cases
towards the management of small, remote units. The study remained vague in its conclusions on the preferable legal form of the institution-to-be. However, the study was
very clear on its advise against a Kathmandu based centralistic approach. At the same
time, the view was expressed that for the years to come the government of Austria
should play a major role in aspects of “social engineering”. Another notable view was
expressed: The existing Namche Micro Hydro Scheme of 27 kW was proposed to be
5
Namche Bazaar Hydro Power Development: Outlining proposals for organisation, management and tariff structure,
Posch+Partners, Innsbruck, Rev.1, February 1989
6
Khumbu Utility Management Study, Interdisciplinary Analysts, Kathmandu, June 1992
Page 26
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
maintained in functioning order to protect the investment that had been done with
UNESCO funding in 1983.
3.1.3
The establishment of KBC
However, progress at the institutional level was achieved only at a much later stage:
Dr. Uitz, an Austrian expert, was entrusted to negotiate with HMG, in particular with the
Ministry of Water Resources, the National Planning Commission and NEA, about the
setting up of a “utility company” to take over the operation of the Namche SHP. An
agreement was formulated in 1994 between the Austrian government and HMG with
the objectives to:
• transform the project into a self-sustainable local institution with the capacity to
manage all aspects of the rural electricity supply system in the project area
• optimise the overall socio-economic development of the project area through responsive interaction with an economically viable electricity supply system.
It was agreed that a share holding company was to be established, and that Eco Himal
on behalf of the Austrian government and NEA on behalf of HMG were to be entrusted
with all related activities. The share holding of NEA was established at 15%, the rest
going to local users groups, cooperatives or/and non-government organizations. The
amount of share capital on the other hand, was not mentioned.
It was further proposed in the draft agreement, that Eco Himal would initially hold the
shares of the local user groups, to be transferred to the respective groups after their
establishment. This clause was later disputed by HMG, and this resulted in further delays in implementation.
3.1.4
Initial Operation, Rehabilitation and Repairs
Testing and trial operation was initially planned to take place in 1993. However, the delays mentioned made this impossible. Also, the intake area and the storage basin required repairs. Joints in the concrete had suffered damage from frost and had to be
renewed. Full load testing was not possible because consumers could not be connected due to the incomplete transmission and distribution network.
Regular operation from February 1995
Testing with connection to the grid could take place only in November 1994. Villages
st
were connected step by step, and on 1 February 1995 regular operation and electricity
sales started. The official inauguration took place on 9 October 1995 in the presence of
the Nepalese Minister for Water Resources and the Austrian General Secretary of the
BMfaA.
Various faults occurred in the power house during the early months of operation: The
main circuit breakers of both machines could not take more than 200 kW load and
needed to be exchanged. Also, the PLC control of one of the machines ceased to function already in May 1995 and needed to be sent to Austria. Other minor faults could be
repaired within short periods, but the Austrian Engineer responsible had to cope with
incomplete documentation.
Page 27
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
The extreme climate takes its toll
In the period 1994-95, the penstock pipe was damaged twice. Welding seams developed leaks that were discovered by maintenance personnel of KBC. This was apparently caused by settling of foundations. Repairs could be done by a welder from Kathmandu. A part of the penstock foundations were in danger of sliding due to monsoon
rains and measures to stabilise the steep slope were established by an Austrian geologist in November 1995.
In the first monsoon of operation it came to light that the desander could not cope with
the sediment load. Several times heavy sediment deposit occurred in the desander and
in the storage basin. In September, the storage basin was completely filled with sand.
The flushing arrangement proved completely inadequate and the basin had to be emptied by hand. It took 120 men 5 days to do this!
Very bad weather in November 95 caused heavy damage on the transmission line.
Heavy icing on the high tension cables caused two masts to tilt heavily. Mast foundations and stay cable anchorage proved to be inadequate. The tilting of the masts
brought the high tension cable in contact with the ground and an earth circuit occurred.
These damages could be repaired by the KBC team.
Earlier, an earth circuit occurred in the underground cable between Zarok and Syangpoche. A joint was faulty. Its location was difficult due to incomplete documentation.
A number of short circuit faults also occurred in the low tension distribution network,
mostly due to poor workmanship during installation.
Regarding the condition of construction works and equipment, a detailed study was
7
done in spring 1996 . The report critically assessed all components, summarised as
follows:
• Unsuitable intake site with insufficient inclination of intake screen (Tyrolean weir)
• Desanding chamber of poor design, resulting in only partial settling of sediment
• Poor concept of storage basin bypass pipe, penstock aeration and shut-off valves
• A lack of well dimensioned flushing facility for the storage basin, resulting in a labour-intensive cleaning process.
• Turbine design faults: outlet apron too short (zu kurze Schachtpanzerung) resulting in a leaking of water between turbine housing and foundation; possible blow
holes in turbine runner and advanced abrasion; indent in turbine spear valve, reducing efficiency; leaking penstock valve and nozzle of turbine.
• Sub-standard electrical installations and lacking safety protection of high tension
installations and transformers
• Incomplete documentation.
KBC have done repair work as far as possible but it must be pointed out that the major
shortcomings in the hydraulic design of structures remained unchanged.
Regarding the issue of incomplete documentation, the question is relevant, whether full
documentation existed at one time. As a regular procedure, checking of documentation
7
Bericht über den Besuch des Wasserkraftwerkes Thame Hydro Power Plant, Dr. DI W. König, 24.6.96
Page 28
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
for completeness is done during commissioning. It was SHPD that had the task of accepting the scheme in the handing over process. If any document exists which would
contain such details, it would apparently have to be with SHPD, or at the next higher
level, with NEA, if it cannot be located at KBC.
The supplier of the electro-mechanical equipment, Geppert of Austria, was given a
contract to do repair work on the turbines and the PLC controller earlier found defective, was replaced. Since the equipment had been supplied a number of years earlier,
the supplier took the position that warranty had lapsed. Negotiations resulted in a price
concession on the new contract, as stated by the supplier.
The runners of both turbines were replaced in 1999. The contract was awarded to EFG
of Austria, from among five suppliers who were invited to provide their offers. In the
view of the original supplier the supply contract went to EFG because of a lower price,
but the fact that EFG had offered runners with buckets from forged steel may have
played a role also.
3.1.5
Follow up
An agreement was formulated in 1994 between the Austrian government and HMG
with the objectives to establish a share holding company for the operation of the
scheme, and that Eco Himal on behalf of the Austrian government and NEA on behalf
of HMG were to be entrusted with all related activities.
On this basis, Eco Himal was responsible for a period of almost 8 years to:
• Carry out and oversee completion of all remaining construction and installation
work.
• Initiate, plan and carry out necessary repair and installation work to improve the
reliability of the scheme.
• Negotiate with HMG and establish KBC with the objective of maximum local
ownership, independence of NEA and full autonomy.
• Operate KBC with full responsibility and train staff on the job
• Build up the institution, administer and organise all areas of activity
• Hand over to local staff and provide services in an advisory capacity for a limited
period of time.
The task of Eco Himal has ultimately been completed by the end of the year 2000. Eco
Himal has shown considerable initiative in all phases of the project, and it has been
able to mobilise resources, mostly in terms of expertise, to tackle a wide variety of
problems and development issues. The BMfaA had to provide additional funding for
the project at different stages. By the end of 2000 total spending has amounted to ATS
83.2 Million, including ATS 1.2 Million for the Namche Water Supply scheme, which is,
strictly speaking not subject to the present evaluation, but which also constituted a part
of Eco Himal’s input.
It is noteworthy that Eco Himal also provided on the basis of its own initiative, electricity
meters supplied by the Water Works and City Utility of Salzburg, and a remote control
load switching system from BEWAG.
Page 29
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
3.2 Project Approach and Performance
In the following chapter the programming approach for the intervention project is analysed, as well as the mode of cooperation and collaboration with local, government and
non-government institutions. This is supposed to help systematically in answering the
question how useful procedures and steering measures have been.
3.2.1
Objectives, Results and Activities of the Austrian Intervention
A logical framework as such was never prepared to describe the project in all its details. However, a logical framework matrix can be established on the basis of the tasks
assigned to the consultants, suppliers and manufacturers. The logical framework matrix of the Austrian intervention and its initial intention is briefly as follows:
Overall Goal
Reliable electricity supply to foster the economic and social development in the project
area, with special emphasis on environmental protection and wood conservation
Output 1
The civil works of a small
hydropower plant in
Thame, Solukhumbu
District of Nepal are
implemented
Output 2
Electro-mechanical
equipment for the small
hydropower plant is tendered and supplied
Output 3
Equipment for transmission and distribution is
supplied to the project.
Austria also takes on the
responsibility to install
this equipment.
Output 4
Setting up of KBC to
operate and maintain the
scheme professionally
Activity 1.1
Provide the financial
means for local civil
works contracts awarded
by SHPD
Activity 2.1
Award e/m equipment
supply contracts to Austrian companies.
Activity 3.1
Establish detail design
and detailed planning
documents
Activity 4.1
Train 12 local personnel
at Kathmandu BTTC and
on the job, and some in
Austria.
Activity 1.2
Provide an Austrian
consultant for overall
supervision
Activity 2.2
Organize and finance all
transportation of equipment and construction
materials
Activity 3.2
Define co-ordination and
communication set-up
Activity 4.2
Provide studies on possible institutional set-up
and negotiate for a solution with HMG
Activity 1.3
Establish scientific exchange and cooperation
between Nepal and Austria on environmental
issues?
No evidence on the implementation level!
Activity 2/3.3
Provide an Austrian electrical contractor
for installation works
Activity 2/3.4
Execute operational tests and commission the scheme
Activity 2/3.5
Execute repairs and various improvements to provide better reliability
Activity 4.3
Provide project management services and
expertise for:
- on the job training of
staff
- the establishment
and initial operation
of KBC
- re-forestation activities
- Implementation of
drinking water supply
Figure 4: Log Frame Matrix of the Namche Bazaar Small Hydro Project
Page 30
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
The Namche SHP was planned with a classical engineering approach whereby the
main responsibilities for plant design, project management and site supervision and
administration rested with the Austrian consulting engineer. Initially, SHPD the responsible branch of NEA, was to be overall in charge and responsible for all construction
works. However, for various reasons and towards the end of the project, SHPD found
itself unable to comply. This, and severe transportation problems, as well as a lack of
sufficient on-site presence of the consulting engineer, led to delays in implementation.
In order to conclude the project successfully, Austria took on additional financial obligations.
Thus, from a limited engineering approach, the intervention of Austria developed into a
comprehensive approach of overall institutional and even regional development. This is
substantiated by the fact that today, the Namche SHP has been succeeded by the
Thame Valley Development Project, which is a new intervention of Austria, with overall
development at its core.
3.2.2
Project Planning and Implementation Set-up (institutional map)
For the implementation of the Namche Bazaar Small Hydro Project, bilateral agreements were signed between the Austrian government (at that time AFC) and the Finance Ministry of Nepal. Execution of the interventions was delegated to executing
agencies on both sides: in Nepal the SHPD (Small Hydel Power Directorate) under
NEA, the Nepal Electricity Administration, and on the Austrian side to a Consulting Engineering firm Posch+Partners, Innsbruck, and at a later stage to the NGO Eco Himal,
Salzburg. Various contractors on both sides were also engaged, to carry out specific
components of the project and other tasks.
At the early phase of the project, during most of the construction, local participation
was limited to tasks of transportation. The setting up of the Khumbu Bijuli Company,
KBC, introduced a degree of local participation and of local ownership that was at that
time unheard of in Nepal, perhaps with the exception of the Salleri-Chialsa Small Hydro
scheme, where the Swiss Development Cooperation had pursued a similar model.
The institutional map, attempting to show the relationship of the various actors and
stakeholders follows on the following page.
Page 31
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
HMG Nepal
Ministry of Finance
Final Report
Bilateral Agreements
FCA-BMfaA
DONOR
NEA, Nepal
Electricity Authority
CLIENT
Executing Agencies, Contractors and Suppliers
Consulting Engineer
Posch + Partners
LEGEND
Line of command
SHPD, Small Hydel
Power Directorate
Electrical Contractor
Fiegl + Spielberger
Various Construction
and transportation
Contractors
Equipment Supplier
Geppert & Co.
Penstock Supplier
BYS, Kathmandu
NGO, Institutional
Contractor EcoHimal
A lternate
C o n tractors
Line of Support
and cooperation
Ownership
Consultants
and
Sub-contractors
Planning
Installation
Commissioning
A lte r n a t e
C o n tra c tors
Construction
Institutional
set up
Operation
Ownership
Village Communities
User Group
Namche Bazaar
Training
User Group
Thame
KBC, Khumbu
Bijuli Company
Electricity supply
and services
Consumers
User Group
Khunde and
Khumjung
Figure 5: Institutional Map of the Namche Bazaar Small Hydro Project
The complexity of the institutional map results from the fact that over the duration of
the project, various changes in the approach took place, such as:
Page 32
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
• SHPD as the local and national project executing agency, phased out from active
involvement before all works, particularly transmission and distribution, were finished. This forced the Austrian side to find other solutions. The consulting engineer and the electrical contractor began to subcontract remaining work directly
with alternate contractors for transportation and erection works.
• The concept of local ownerships and the establishment of KBC as the operator
and owner did not initially exist, but came up only after the main construction
works were completed.
• The task of the consulting engineer Posch + Partners was taken over by the
NGO Eco Himal because it was felt that the latter would be better suited for the
institution building task.
Initially, the set up followed a classical engineering approach by which the client and
national executing agency SHPD was supported and supervised by an Austrian Engineering Consultant, who also provided design inputs. Also, an Austrian Electrical Contractor did supply materials and was in charge of supervising the local erection contractors, who had been engaged by SHPD.
Both, the consulting engineer and the electrical contractor, had to take on additional
tasks, such as subcontracting of work for transportation and erection directly, and staff
training, as well as supply of additional materials. This meant a departure from the
division of work between consultant (supervision) and contractors (execution). Also,
when Eco Himal came into the picture, the lack of a clear division of tasks and
responsibilities continued and new activities were directly acquired and executed by
Eco Himal. This means that the BmfaA thereby transferred the control function of
individual tasks to its main contractor, but retained the overall steering function.
Page 33
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
3.3 The Present Status
3.3.1
Technical Features
The Namche SHP is a run-of-river high head project with a rated generating capacity of
630 kW. It consists of an intake with Tyrolean weir, desander, head race conduit in
stone masonry carrying the water to a storage pond. The latter can be used for about 3
hours of full capacity generation during peak times. A bypass pipe with sluice gate
connects the headrace canal directly with the penstock, just below the gate valve. The
purpose of this is to feed water directly into the penstock while cleaning of the storage
pond is going on, so that no interruption of power generation takes place. The drawback is that water directly from the headrace canal is not free from sediment.
Figure 6: The area and villages covered today by the Namche SHP; the red line represents the
transmission line
Page 34
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
At the lower end of the storage pond, there is an intake grill to the penstock with a penstock valve chamber. The penstock valve is manually operated. The penstock is of
welded steel, 450 mm diameter, 6 meter sections welded in situ, with a total length of
945 m. It is buried to protect it from frost. The penstock connects to a bifurcation at the
power house which in turn connects to two Pelton turbines.
Figure 7: The intake area of the Namche SHP at Thame; in the foreground the desander
The turbines are double-jet, equipped with spear valves and jet deflectors. Each turbine is designed for a discharge of 180 l/s which results in a power output (electrical) of
315 kW (rated) at the design net head of 205 m. This implies an overall efficiency of
87%. At the time of visit, actual net head was 201 m, pointing to the fact that penstock
pressure losses are higher than expected. This is due to calcination, i.e. building up of
a layer of calcium inside the penstock.
Electricity is generated by two synchronous generators directly connected to the respective turbine shaft, operating at 1500 RPM/50 Hz and a voltage of 400 Volts. A
power factor of about 0.95 is maintained.
A transformer brings voltage up to 11 kV and transmission is via a 13 km long transmission line, which consists of an overhead line with metal poles and underground cable in the vicinity of settlements. Transmission line poles were supplied locally, while
overhead and und underground cables were part of the contract of Fiegl + Spielberger.
Electricity is distributed at present through 4 step-down transformers at the level of
400/230 Volts, entirely by underground cables. In November 2000 the number of connections was 672. This was reduced to 632 with effect from 16 December 2000, due to
a new connection and tariff policy. Within easy reach of the transmission line and the
existing distribution network, only three houses are not connected. Outside the area
covered by the distribution system, about 20 households were provided with solar PV
panels, subsidised by Eco Himal. Despite the subsidy, lighting provided by PV sets is
Page 35
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
extremely expensive for the households.8
Figure 8: The two sets of double-jet Pelton turbines with synchronous generators, in the background the control and switch gear panels
Figure 9: Along the transversal course of the penstock, considerable slope stabilisation had to
be implemented with high retention walls and shrub planting.
The Namche scheme is equipped with a remote control load switching system. 22 different switching programmes are possible, and KBC has started to introduce load
8
Owners of PV systems pay a service fee of NRs. 260 per month for a 32 Watt panel. Average power provided by
such a panel is about 3.5 kWh per month, resulting in a cost of NRs 74 per kWh, a factor of 10 higher than the commercial tariff of KBC!
Page 36
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
switching with a twofold objective, a) to reduce peak-load problems, and b) to improve
the overall load factor, by offering low tariff energy for specific purposes during off-peak
hours.
3.3.2
Institutional set-up
KBC, the Khumbu Bijuli Company, owns and operates the generating facility, transmission and distribution system. Also included in the operation is a tree nursery and KBC
has been entrusted with the installation and operation of the Namche Drinking Water
Supply project. The operational set up is as per the following organisation chart.
BOARD DIRECTOR
KHUMJ.-KUNDE
USER GROUP
LHAKPA THUNDU
SHERPA
BOARD DIRECTOR
NAMCHE BAZAAR
USER GROUP
SONAM GELZEN
SHERPA
BOARD DIRECTOR
THAME
USER GROUP
PASANG RITA
SHERPA
BOARD DIRECTOR
NEA
SHREE PRAKASH
JUNG RANA
EXECUTIVE
DIRECTOR
SONAM GELZEN
FINANCE & ADMINISTRATION
MANAGER
VACANT
TECHNICAL MANAGER
VACANT
ASST. FIN. & ADMIN. MANAGER
ANG DANU SHERPA
ASST. TECHNICAL MANAGER
ANG CHHIRING SHERPA
ACCOUNTANT
NAWANG THARWA SHERPA
SUPERVISOR
DANURU SHERPA
PEMBA GELGE SHERPA
CHIMEY KALDEN SHERPA
OFFICE ASSISTANT & STORE KEEPER
VACANT
TYPIST + METER READER
VACANT
HELPER
JIT BAHADUR RAI
PEON, GARDENER, GUARD
KATAK KUMAR RAI
ANG DOMA SHERPA
NIMA LHAKI SHERPA
Figure 10: Organisation chart of KBC
TECHNICIAN FIRST
ANG TSHERING SHERPA
MINGMA RITA SHERPA
KARSHSNG SHERPA
NIMA WANGCHU SHERPA
NAWANG TSHERING SHERPA
TECHNICIAN SECOND
VACANT
HELPER
VACANT
WORKER
VACANT
It is to be noted that the actual management staff are not (yet) on the level matching
their function. This is probably due to a pending board decision.
The assignment of the executive director is apparently a “political” assignment. The
individual concerned is not actually performing the assigned function.
Page 37
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
KBC has been established as a private limited company under Nepalese law. It is
owned by four institutional share holders - 3 local user groups holding 28.3% of the
shares - and NEA, holding the remaining 15% of shares. The company has an authorized share capital of NRs. 150’000’000, of which NRs. 137’660’010 is paid up and issued in lieu of the assets brought into the company by Austria (85%) and Nepal (15%).
The 85% of Austria were given as a grant to the three local user groups.
3.3.3
Development of sales and income
In its first year of operation starting in February 1995, total generation was somewhat
less than 1240 MWh. This represents an average load factor of less than 24%. In other
words, more than 75% of the resource available could not be used profitably. Four
years later (Feb. 98 – Feb. 99), total generation reached 1970 MWh, at an average
load factor of near 40%. This represents an improvement of more than 15% annually,
on the average. Figure 9 shows that minimum demand grows very slowly, while
maximum demand grows faster. This means that the overall load factor is increasing
only slowly, while a potential peak load problem develops. This is a very typical
situation in isolated small electrification schemes. Fortunately, KBC is better equipped
to cope with this situation than most other isolated schemes, because it owns a remote
control switching system.
Load Development Namche SHP
kW
600
max.
minimum demand
P l (
)
550
500
450
400
350
300
250
July 98: one machine
out of service
200
150
100
50
0
Feb 95
individual data points are selected from February, July and
November in each year
Nov 2000
Figure 11: Trend of load development in the Namche SHP
In the two most recent years, KBC generated a gross income of NRs. 3’049’000 in
1998 and NRs. 3’734’000 in 1999, an increase of 22%. It had made modest profits,
which were accumulated, and stood at NRs. 4’549’000 as of 16 July 1999. In the same
period, operating cost including all salaries, increased from NRs 2’015’000 in 1998 to
NRs. 2’349’000 in 1999. An increase of 16%, indicating improved productivity. In the
most recent financial year, from July 99 to July 2000, gross income was NRs.
Page 38
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
5’649’000, with expenditures of NRs 2’600’000, resulting in a gross profit of NRs.
3’485’000.
Year
2055
Sales of
electricity (NRs)
3’049’400
2056
3’734’200
2057
5’640’000
Data quality
Audited accounts
Audited accounts
9
Tentative
Increase over
previous year
22.5%
51 %
P.S.: The financial year 2057 runs from 17 July 99 to 16 July 2000, etc.
Figure 12: Recent development of sales income from electricity
In the electricity market of the Namche Bazaar area, there is considerable development
potential. The use of this potential has already been very successful, as can be seen
from the load development diagram (Figure 9), and the table on sales development
(Figure 10).
Because of tourism constituting the single most important demand factor in the electricity market, there is considerable seasonal variation in demand. Despite an appreciable
growth of overall demand, it has not been possible to reduce the level of seasonal
variation. The difference between the month of lowest demand and the month of highest demand shows this fact clearly: In July 1996 maximum demand was 320 kW, while
in November it was 380 kW. This is a difference of around 19%. In July 2000, which
again was the month with the lowest peak demand figure of the year, 396 kW were recorded as the peak demand. In November 2000, the highest ever demand figure was
recorded at 540 kW. This constitutes a difference of 36%. This reflects the growing dependence on tourism for the demand on electricity. This is a severe problem that needs
to be solved to make use of the full income potential of the Namche SHP.
Also revealing is the typical daily load curve of the scheme. As is common in small isolated systems, much of the peak load is for lighting. This results in high loads during
times when lights are needed, typically the early evening and morning hours.
The diagram (Figure 11) shows peaks between 7 and 8 in the morning and between 6
and 7 in the evening. KBC has been able to improve the load considerably during daytime hours between 9 in the morning and 4 in the afternoon. At night, between 22 and
5 hrs., the load is limited to purely lighting loads. With the remote load switching system recently installed, KBC is equipped technically to develop night time power use. It
has already begun to experiment with electric storage heaters and large volume water
heaters, for which it would offer a special rate, and would supply electricity only during
slack night-time hours.
9
Data supplied by KBC in March 2001
Page 39
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
Load in kW
Daily Average Load Curves November
440
420
400
380
360
340
320
300
280
260
240
220
200
180
160
140
120
100
1997
1999
17 18 19 20 21 22 23 24
1
2
2000
3
4
5
6
7
8
9
10 11 12 13 14 15 16
Time of day
Figure 13:
Namche SHP: A typical daily load curve in the peak (tourist) season
No. of connections
The number of electricity connections had reached 462 already in June 1995. It increased steadily to 672 in June 2000. Within the reach of the existing transmission system, this accounts for full electrification of the area. KBC is maintaining a tariff system
in which there are nine different categories, depending on the power level of the connection. Three categories are for unmetered consumption. This means that consumers
can use as much electricity as the respective connection permits against payment of a
monthly flat rate.
650
30 kW
600
12 kW
550
8 kW
500
5 kW
450
3 kW
400
Connections by Category
350
2 kW
300
1.26 kW
250
600 W
200
100 W
150
100
1995
1996
1997
1998
1999
2000
Year
Figure 14: Namche SHP: Development of KBC electricity connections by load level category
Level 1 customers, for instance, pay a monthly flat rate of NRs. 60 for a connection of
100 Watt capacity. With this, a few light bulbs can be connected, and electricity, calculated on the basis of maximum possible consumption, is cheap at less than NRs.
Page 40
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
0.90/kWh10. 200 customers are at present subscribed to this category. The most popular category is level 3. Connections are for 1.2 kW (which permits cooking) against a
flat rate of NRs. 600.- per month. 420 customers subscribe to this level. Their electricity
cost is even lower, if full use is made of the connection: a unit rate of less than NRs.
0.70/kWh11. Level 4 – 9 are commercial consumers with metered electricity, at a cost
of NRs. 7.50/kWh at present, plus a marginal flat rate. Thus, more than 90% of consumers benefit from un-metered electricity connections.
Level
1
2
3
4
5
6
7
8
9
Power
Flat rate Unit rate
Watts
Rs
Rs
100
60
600
300
1'240
600
2'000
200
7.5
3'000
300
7.5
5'000
500
7.5
8'000
800
7.5
12'000
1'200
7.5
30'000
7'000
7.5
Energy
meter
No
No
No
Yes
Yes
Yes
Yes
Yes
Yes
% of all
connections
29.8%
1.5%
62.5%
1.3%
1.2%
1.2%
1.6%
0.3%
0.6%
Figure 15: Namche SHP, KBC tariffs in effect since 16 July 1999
The effective tariffs, shown above, became obsolete as of 16 December 2000, actually
after the field evaluation took place, but before completion of the final report. It is therefore useful to include the new tariff structure.
Level
Consumer
category
Power
subscription
in kW
Flat rate
Rs/month
1
2
3
4
5
0.10
1.26
4.00
12.00
30.00
60
600
300
800
3000
total
1114.44
Unit rate
Rs/kWh
Energy
meter
No. Of
subscribers
% of all
connections
7.5
7.5
7.5
No
No
Yes
Yes
Yes
193
339
80
14
6
30.5%
53.6%
12.7%
2.2%
0.9%
632
100.0%
Figure 16: Namche SHP, KBC tariffs in effect since 16 December 2000
The previously existing 9 connection levels were reduced to 5, and KBC is making
sure, that small scale commercial consumers, typically lodges or house owners renting
out rooms, subscribe to a metered connection.
Restructuring of the connection policy and the tariff have resulted in a slightly lower
number of connections, without affecting the total number of consumers. Despite a re10
equivalent to 0.19 ATS/kWh, (exchange rate of 1 NRs = 0.2 ATS at the time of evaluation)
11
equivalent to 0.14 ATS/kWh, (exchange rate of 1 NRs = 0.2 ATS at the time of evaluation)
Page 41
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
duction in the total number of connections, the proportion of metered connections has
gone up from around 6 % to 16%. In the view of KBC, the new regulations do neither
increase nor decrease revenues. In the author’s opinion this is an unnecessarily pessimistic approach. Based on experience elsewhere, the change from non-metered
consumption to metered consumption will result in a temporary reduction of consumption, because consumers experience a “shock” when suddenly the electricity bill relates
to actual consumption. However, they get used to it, and consumption goes back to the
previous pattern, but is now to be paid for. In the mid-term, the prediction is therefore,
that revenue will go up. Also, ultimately, this is the chief objective of the restructuring
exercise.
Page 42
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
3.4 Specific Questions and Main Findings of the Evaluation
This section of the report addresses specific questions of the terms of reference for the
evaluation directly. Findings are substantiated with the relevant evidence, where available. Otherwise, argumentative comment is made.
3.4.1
Programming
Agreement with the Austrian Development Cooperation Philosophy
Question Q1: How far do conception, implementation and results reflect the chief objectives of Austrian
development co-operation, in regard to poverty alleviation, democratisation/ ownership development, ecological concerns and gender equality?
The first initiative that ultimately led to the Namche SHP of today, was motivated by the
Austrian export industry. It was the intention to set up a reference project. However,
how such a project reference was actually going to be instrumentalised is not documented.
Soon after planning activities had begun, a more partner-oriented chief objective was
identified and adopted: “Ecological protection and wood conservation by the provision
of reliable electricity to the villages in the area.” No explicit reference could be located
to the other relevant objectives, but what was actually done reflects implicitly that social
objectives were of importance.
By setting up KBC under local ownership, the intervention was clearly following the objective of democratisation and ownership development. The model developed was new
for Nepal and it took considerable persistence in negotiations on the central government level to implement it. On the local level, the intended model was not at first very
well understood either. Periodical reporting by Eco Himal shows that this was felt to be
a problem, and various measures were taken to improve understanding. Public information campaigns were launched to explain the structure of KBC and the nature of its
task. The representatives of the share-holding user groups were also invited to a number of seminars with the objective of imparting specific know-how regarding the functions of the board of directors of the company. Positive results of these most recent
measures are not yet fully discernible, but it is evident that interventions were aimed at
strengthening sustainable democratic structures.
Despite the fact that the beginning of the project dates back to times when Austrian
Development Cooperation principles and objectives were not yet firmly established, the
approach over time reflects serious adaptation to today’s objectives. Especially in the
environmental field, the project has gone a long way in achieving targets. This is reflected by the re-forestation carried out and by the continuing activity of the treenursery also under the management of KBC.
3.4.2
Need-Driven Intervention
Question Q2: How far were the interventions based on actual needs of the rural population and on priorities and development plans of the partner countries: What impact did measures have on
sector policy development of the partner governments?
To plan and implement the Namche SHP was a very ambitious undertaking, given the
extreme remoteness and climate of the project site, and practically from the beginning
a difficult and strained relationship with partner institutions. Bearing these conditions in
mind, the achievement is considerable.
Page 43
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
The reason for choosing such a difficult remote area was that with foresight, the increasing tourist influx was recognised to constitute a fast growing environmental hazard. It was also envisioned at an early stage, that a growing tourism-oriented service
industry would be in need of electricity, and that, if electricity was available, positive
occupational effects would result. In this sense, a latent, but nonetheless considerable
local need was identified and fulfilled. Results today show that a considerable economic potential has been created with cheap and reliable electricity.
That a real existing need was meet is also supported by the fact that the acceptance
rate of electricity connections has been 100%.
National priorities were implicitly followed with the Namche SHP. It was a declared national objective at that time to electrify all district head quarters and other important
centres in remote areas. Namche Bazaar falls in the latter category.
The effect that the example of the Austrian intervention could have had, should show in
th
one form or other in official documents. In Nepal, the relevant document is the “9
Plan, 1997-2002”, prepared by the National Planning Commission of HMG. This document contains several relevant passages:
• The ongoing activities and completed projects in the sector of rural small hydro
development comprised a total capacity of 2’600 kW in 5 projects. Austria is not
mentioned explicitly, but has contributed with 23% to this achievement under extraordinarily difficult conditions.
• On rural electrification, the following statement can be found: “For enhancing the
effectiveness of the rural electrification, user’s groups will be involved in project
formulation, implementation and operation. In the case of remote mountain districts, emphasis will be laid on micro and small hydel projects. Such projects will
also be implemented mobilising local participation and through the involvement of
NGO’s” (end of quotation). Two things in this statement are notable:
-
That a need was felt on the level of the planning commission to “enhance
the effectiveness” of rural electrification, and
-
That the way to do this, was plainly speaking by copying the Austrian approach.
It is evident from this, that the example of Austria has influenced this passage,
even though it may not have been acknowledged officially.
• In the ninth Plan, another 7 rural small hydro projects are planned, totalling 3775
kW. Compared to this, the Namche SHP, implemented during the 8th Plan,
amounts to a portion 16%. This goes to show that targets in the 9th Plan have increased as compared to the 8th Plan.
In addition, the legislative process in Nepal has produced the Electricity Act (1992), the
Water Resources Act (1992) and Electricity Regulations (1993). These acts contain
clauses that favour small hydro development fiscally and otherwise. The Namche SHP
may well have had a positive influence on the new legislation, although there is no hard
proof.
Page 44
ÖEZA, Projekt 1389
3.4.3
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
Participation and Donor Co-ordination
Decision making and coordination mechanism
Question Q3a: What decision making processes and co-ordination mechanisms were developed with the
partner government and other donors?
Question Q3b: What was the degree of local participation and of other stakeholders? What role did
NGO’s
and the private sector play?
The bilateral agreement between Austria and Nepal of 1989 outlined a sharing of responsibilities as follows:
Nepalese side:
• Land acquisition
• Site installations with camp facilities
• Administration and permanent site management
• Execution of all civil works, with Austrian financial assistance
• Transportation within Nepal for the civil works materials
• Installation of the transmission and distribution systems
Austrian side:
• All design works
• Construction supervision and construction management as far as necessary
• Supply, transportation and installation of penstock and hydro steel structures
• Supply, transportation and installation of all required electro-mechanical equipment
• Supply, and transportation of all required materials for the transmission and distribution systems
• Training of personnel
Austria did not at any time have direct permanent representation in Nepal, neither on
the ambassadorial level, nor by its Development Cooperation department. The typical
ACB (Austrian Coordination Bureau) as is to be found in Bhutan for instance, is missing. Headquarters therefore had to rely on full delegation of authority to its contractors:
Posch+Partners in the early stages of the project, and Eco Himal from 1993 to 2000.
As a consequence, coordination with government and others was largely left in the
charge of the contractors appointed. Only infrequent visits by head office staff took
place.
The Austrian Agency for Development Cooperation’s role was reactive rather than proactive. Despite this, it has shown considerable persistence in bringing the project to a
successful end. All possible difficulties have been met in a constructive and decisive
manner. Officials directly involved have shown considerable identification with the project and have provided firm and result-oriented leadership.
Page 45
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
Failure of the local partner (SHPD) to perform its assigned role was for financial
difficulties of HMG and not for the lack of Austria’s performance or a lack of
coordination. On the other hand, the Nepalese project management that existed during
early phases of the project also blamed the Austrian consulting engineer for nonperformance at various points in time. The lack of continuing involvement of SHPD
must also be seen in the light of the political situation prevailing. A democratic
revolution was ongoing at that time, and numerous government agencies were in effect
put on hold. Inactivity at the project level is therefore comprehensible. It was the safest
method to avoid exposure to a revolution-minded public. After the political situation had
calmed down, it was too late for SHPD to resume a strong role. Legislation had been
established in the mean time that made local ownership possible. This was the
necessary legal basis for the Austrian initiative on the institutional level.
After most of the construction was completed, but before commissioning, a new
agreement was formulated in 1994 between the Austrian government and HMG with
the objectives to:
• Transform the project into a self-sustainable local institution with the capacity to
manage all aspects of the rural electricity supply system in the project area
• Optimise the overall socio-economic development of the project area through responsive interaction with an economically viable electricity supply system.
Despite the agreements entered into, in implementation, Austria has practically gone
all the way alone, after attempts in the area of partnership and local participation had
failed. An exchange of information took place without doubt with a number of institutions, such as the National Park authorities, local government offices and central government institutions in Kathmandu, as well as with the ongoing SHP project Salleri
Chialsa sponsored by Switzerland. Also, close cooperation in implementation was established with the leading mechanical workshop Balaju Yantra Shala (BYS), in Kathmandu. This reflects a policy of getting done locally what was possible. This is a merit
of the project.
Otherwise, there is little evidence that considerable donor coordination, local participation and effective partnership with national government or non-government institutions
took place. A certain degree of isolation was evident during the early construction
phase. No permanent local presence (i.e. a Kathmandu office), and the extreme remoteness of the project site have very likely contributed significantly to this situation.
3.4.4
Techno-economic Evaluation of Namche SHP
Question Q4a: Are processes, structures, plants and equipment technologically adapted to the frame
conditions (technically, economically and ecologically) and designed in a sustainable way?
What economic impact did re-designs and rehabilitation measures have?
Several criteria and indicators have been used to evaluate these issues:
Technical adequacy and status of installations
As outlined in chapter 3.3.1 the installations and their status is adequate, although with
some flaws in design and execution which cannot be rectified. This is borne out by the
fact that the frequency and severity of breakdowns has decreased over time. The plant
has never before run as well as over the past few months.
Page 46
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
Relevance of electricity supply for the energy situation in the project area
From the household survey, and information gathered during the project visit, it becomes apparent that the electricity supply from the Namche SHP has made major inroads into the traditional household energy pattern not only in the field of indoor and
outdoor lighting. The heat requirements are still dominated by firewood. A growing
substitution of firewood is taking place not only through electricity but also through LPG
and Kerosene, particularly in tourism use.
The electricity from the Namche SHP serves a resident population of about 2’600. In
addition, there are more than 25’000 tourists visiting the area every year, with an average stay in the area of say, 5 days. This would add about 347 to the resident population, so that we need to consider a capita figure of about 3’000 that is served by the
Namche SHP.
Today, total production and use of electricity has reached 2000 MWh/year. This
amounts to 666 kWh per year and capita, which is equivalent to 2400 MJ/capita/year,
or 200 MJ/capita/month, double the value that has been calculated for the Rangjung
area in Bhutan. In terms of other energy resources, such as fire wood, 200 MJ
amounts to 27 kg per month, if it is assumed that wood burning is commonly done at
about half the efficiency that applies to electricity use. The average requirement of en12
ergy for cooking in Nepal is said to be 8’200 MJ/capita/year . Compared to this, electricity supplies almost 30% of the cooking need. This is a rough estimate of the situation, giving a realistic order of magnitude. It goes to show that the electricity supply
provided is indeed very relevant, and most pronounced in the requirements of tourism.
Efficiency of Power Supply
Not at the moment, but soon, when the peak power demand reaches plant capacity,
the efficiency of generation and distribution become important. With each percentage
point of plant efficiency improvement or loss reduction, KBC income is increased by up
to NRs. 1’000 per day, which is a direct increase in profit. It is a sensible management
measure therefore, to keep an eye on overall losses.
Generation efficiency as initially measured during commissioning was according to the
values predicted by the supplier. However, due to the heavy wear on the turbine (sediment abrasion damage), the efficiency has been decreasing gradually. This was rectified by the installation of new runners in 1999.
The head loss in the penstock pipe had been increasing over the years to a level that
significant loss of power resulted. Instead of the rated output of 600 kW, only 580 kW
could be generated. This phenomenon has resulted in an investigation of the cause of
increased head losses. It was found that progressive incrustation of the inside walls of
the penstock was taking place. The measure taken was cleaning of the penstock with a
special process called pigging. A reduction of the head loss was achieved successfully.
Both measures combined, new turbine runners and cleaning of the penstock, have resulted in improved efficiency of power generation.
Transmission and distribution losses can not reasonably be established in the supply
area, because 96% of all connections before December 2000 and 84% from this date
onwards, are not metered. This makes it impossible also to monitor the efficiency of
power transmission over time. Perhaps one reason why a strategy of 100% metered
consumption should be adopted in the future.
12
Source: Rural energy Study Nepal 1999, Heijndermans, ASTAE, World Bank
Page 47
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
Adequacy of electricity supply
KBC provides a generally generous supply level of electricity. The most popular (420
consumers, or 62%, new 53.6%) single-phase connection of a household is for a
maximum capacity of 1.26 kW. This policy of relatively ample supply capacity connections is favourable for encouraging the use of firewood substituting appliances such as
rice cookers, hot plates, kettles and space heaters. Consumers that require more than
1.2 kW capacity can choose various higher levels, up to 30 kW. These connections are
metered. The supply of electricity is adequate and unrestricted so far. However, as the
first signs of reaching maximum generating capacity with demand appear, KBC will
have to control the switching of various load categories. Fortunately, it has the technical means to do so with the remote control switching system installed in the scheme.
Safety of the plant and associated mini grid
There have been no accidents reported from the power house. The safety precautions
and the protection schemes employed are in accordance with European systems. For
the distribution systems and especially the house wiring, the same applies. Not one
single accident was reported during more than five years of operation. This is mostly
thanks to the consistent use of earth leak fault relays in all consumer installations, but
also thanks to training and information campaigns.
Economic impact of repairs and rehabilitation of the Namche SHP
In terms of repairs and rehabilitation with an economic impact on the operation of the
scheme, a number of measures could be identified that do indeed have a positive impact. Some other repair measures appear to be beneficial for the scheme and such
measures were absolutely necessary, but these will also be of a recurring nature.
• Foundations of several high tension poles and stay cables were improved after
the initial design and execution had proven inadequate. This has resulted in no
further interruption in power supply, the avoided outages representing an economic improvement.
• Concrete joint sealing in the headrace and storage basin area has been improved with specially cold-resistant material and this has resulted in no further
frost damage on a yearly basis, reducing maintenance cost.
• Slope stabilisation along the transversal path of the penstock has resulted in no
further damage to the penstock. Continuity and reliability of power generation
were improved. This also represents a better economic situation for KBC.
• Elaborate repair and rehabilitation works in the intake area were necessary due
to severe damage after the monsoon. Under the prevailing conditions, this is a
recurring activity that has become a regular part of yearly maintenance cost.
• The problem of using water from the Thame Khola with a heavy sediment load
during the rainy season could be solved: A separate spring catchment was built,
and water is diverted into the headrace canal of the scheme. Fortunately, this water is practically free from sediment also during rains and flow is sufficient for the
full requirement in the rainy season. Water from the original intake thus is not
used at all for as long as possible during the rainy season. This measure is promising to be very effective in avoiding further turbine runner abrasion.
Page 48
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
• The replacement of the turbine runners has been necessary for quality reasons.
It is economically effective, specially in combination with the use of water with
less sediment load because it extends the life time of the runners considerably.
• The recent cleaning of the penstock pipe has improved plant output by at least 20
kW. This represents an additional re-established earning potential. However, the
exercise is likely to be necessary again in a few years time. Since armatures in
the penstock and associated cleaning equipment are in place, KBC should be
able to do this work, as and when necessary, on its own.
• Not a repair activity, but an addition, is the installation of the remote control load
switching system. This will be extraordinarily useful in the future to increase the
earning capacity of the scheme, while managing peak loads without load shedding which would mean a loss of earnings.
On the one hand, in technical terms, a large potential exists to build up the power
factor, broadening the income base. A combination of technical measures (remote control load switching) and administrative measures (tariff differentiation,
connection policy) will enable KBC to effectively pursue load development. On
the other hand, the discontinuity of the tourism trade over the year will also set
limits to full use of the generating potential.
3.4.5
Project Effectiveness and Efficiency
Question Q5: What is the result of the analysis as far as effectiveness of interventions and efficiency of
allocated funds are concerned?
Effectiveness
Interventions from the Austrian side apparently always had effectiveness as an objective. For the most part, effectivity was achieved, but it must be assumed at high cost
due to expatriate (Austrian) expertise required. In some cases, contractors that were
engaged failed to provide top-quality service, specially in the area of design and supervision, equipment supply and installation.
A remarkable and positive case of fully achieved effectiveness is the institution-building
task that was assigned to Eco Himal. The period of engagement of almost 8 years
seems very long, and associated costs were high. However, what was attempted in
terms of institution building was new for Nepal and in terms of technology for the local
people. Also, another project example with a very similar comprehensive approach, the
Salleri-Chialsa small hydro scheme, shows that time spent and cost involved were on
the same order.
Efficiency of fund allocation
The efficiency of utilisation of funds is difficult to assess. In its implementation, the project has been plagued by natural calamities and economic crises in the region, as well
as by high levels of inflation. Delays were numerous, and every delay has added to the
cost of the project. The scope of Austria’s input into the project was extraordinary and
beyond the usual. It is possible to state relative rather than absolute efficiency by comparing with other projects in Nepal. When doing this, care was taken to make fair comparisons, i.e. project cost of compared projects were to have a comparable scope, and
specific features of the projects needed to be known.
Page 49
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Cost of
construction
Project
installed
capacity
Namche SHP
Tatopani SHP
Salleri-Chialsa SHP
600 kW 65.1 Mio ATS
1000 kW
400 kW
Final Report
Cost
US$/kW
8'346
4'970
9'375
1 $ calculated at ATS 13.0
Figure 17: Table showing costs of different SHP’s in Nepal
The cost of construction of the Namche SHP was compared with two other projects in
Nepal that were implemented roughly in the same time period. The cost of Namche are
between those of Tatopani and Salleri-Chialsa. Was money relatively efficiently spent?
Tatopani benefits from road access and to some degree from better economies of
scale. Also, no distribution network is included in the cost. It is therefore plausible that
its cost is only 63% of those of Namche.
Salleri-Chialsa is about 18% more costly than Namche, despite the fact that it is less
remote than Namche. On the other hand it is low head, implying higher unit cost, and it
was built in two stages, which tends to increase cost.
Taking the extreme remoteness and the altitude of the Namche SHP into account, its
cost are favourable when compared with the Salleri-Chialsa scheme. In absolute
terms, as repeatedly mentioned, costs were high. However, many small schemes were
implemented world-wide at this cost level.
Namche had local transportation costs of about US$ 700/kW, certainly a multiple of the
cost in the other projects. The efficiency of money spent on transportation cannot be
assessed because there is no firm basis for comparison.
3.4.6
Impacts on population and resource base
Question Q6: What are the economic, social and cultural impacts for the population of the project area?
Which direct effects have occurred in terms of economic and industrial development; in particular what are the income and employment effects?
What impacts on the resources (water, land, pasture and forest) have resulted from the
interventions e.g., on their exploitation and access and on the housing situation, health
conditions and the social structure of the population? What impacts have resulted on welfare and education, mobility and migration, lifestyle and cultural activities. What is the current status of corresponding indicators and processes of the impact monitoring?
Residents in Namche Bazaar remember the period prior to the commissioning of the
installation at Thame when only a small amount of electricity was supplied from a micro-hydro, and many residents had none at all. They articulate very clearly the changes
that have occurred since the plant at Thame came on line. The survey followed a fourday shut-down of the plant for penstock maintenance. This further reinforced recollection of life without electricity.
Economic Impacts
The economic impacts of abundant cheap electricity have been quite marked. New
economic activities that are completely dependent upon power have developed in the
past five years.
Page 50
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
Figure 18: Mostly tourists are customers of an e-mail business at Namche Bazaar
Two email shops have now operated for a year, one of which has an internet connection. At first it was used only by trekkers, but now local people also avail themselves of
the service. One operator reported that his three computer configurations cost him a
total of NRs 300,000 installed. He charges NRs 60 per KB to transmit, and NRs 20 to
receive messages for clients. His daily income in the season is NRs 14,000 per day;
around NRs 1,680,000 per annum. His running costs for the telephone line are NRs
1,300 per day. Originally his business was selling second hand books and some stationery items. Business was very slow, and now the email service is the main source of
income. Now clients browse and buy the books while they are waiting to use the computers, so even the book business has benefited. The four day power outage was “a
disaster” in terms of lost business.
Very successful, too, are the two laundry services that have opened. One operates out
of a general store. Originally the entrepreneur bought the machines hoping they would
prove a draw-card for his shop. The family’s normal business has not increased, but
the laundry service now makes more money than the core business.
It is a level 6 consumer13, paying NRs 4,500 per month on average for power. Most of
the laundry customers are trekkers, but more and more local shopkeepers, who have
no time to wash, use the service. During the four day outage (due to penstock clean13
All references to the connection level in the survey results apply for the “old” system prior to 16 December 2000, because during the time of the surveys it was still in force.
Page 51
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
ing) the proprietor stated that the business incurred significant losses, and “public life
came to a standstill! Why was it done at the peak of the season?”
The two bakeries that serve both the trekker and the local market are large electricity
consumers. Power costs are high, so outages are particularly damaging; one has a gas
oven, and during outages uses LPG at 10 to 15 times the energy cost because he says
the damage to consumer confidence is too great to be worth the risk of failure to supply.
The new local cinema also has stand-by generation. The family operating the facility
returned from working in Japan and set up the operation. They paid NRs 500,000 for
two sets of projection equipment, and for repairs since it was purchased. If more than
10 customers come, they screen a film, usually three times daily in season. Each show
nets on average NRs1,500 , giving an annual income of around NRs 540,000. Market
days are particularly lucrative; they screen only Nepali films, aimed at the population of
Namche Bazaar and its surrounding market catchment area.
Other new energy dependent businesses are a sauna, a hot shower facility, a water
bottling plant, and a pizza restaurant. All of these are tourist-oriented.
The shower service is interesting in that it is considerably more expensive than showers in the average lodge, but its owner defends her pricing with the observation that
she offers “real showers with real hot water”, electrically heated, and unlimited, as opposed to the lukewarm wood heated bucket shower commonly on offer in lodges.
All these businesses are family based, though they employ extra casual labour as bakers, cleaners or shop assistants. Typically, the new enterprises have paid off the capital
cost of the equipment they purchased (computers, washing machine and dryer, projection equipment) within one year. The exception is the sauna, which covers its costs, but
does not make much money, as it has very high power demand. All owners stated that
electricity is no longer a luxury, but a necessity of daily life. All stated that electricity is
extremely good value for money.
Other entrepreneurs are using electricity to add value to conventional goods and services. Significant among these are the luxury lodges. One of these is not new, and was
operating with its own generators prior to electrification. Its running costs are significantly reduced by using a local renewable energy source. This lodge, Japanese coowned and targeted at the luxury Japanese market, is by far the largest power consumer. It is a level 9 consumer with a 30 kW connection.
Another luxury lodge opened for the autumn 2000 season in Namche Bazaar. Lighting
is all electric. The lodge cooks with gas, kerosene and electricity. In the kitchen is a
fairly typical array of appliances; mixer, blender, toaster, geyser, refrigerator and oven.
There is also a vacuum cleaner.
All the guest rooms are warmed with oil-filled electric space heaters. There is abundant
hot water in the attached bathrooms, benefiting from a low tariff provided through the
remote control system recently introduced. A hairdryer is available for guest use. Laundry is done at the local laundry service. Wood is only used for space heating in the
lounge area, more for atmosphere than for warmth; there is also an oil-filled electric
heater for effective heating. They do not pay for wood, but an employee fetches it from
out of the conservation area. There is a TV in the lounge, used for videos as a television signal is not yet available.
Formerly the proprietor and his family operated another smaller luxury lodge. The differences in the old and new lodges are in the ease of operation, lightness and cleanliness of the new lodge. The proprietor and his wife manage the lodge, but have five
Page 52
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
male employees. One is Sherpa; the others are migrant seasonal workers from the
Terai, who stay for nine months of the year.
Income and Employment Impacts
Namche Bazaar now has a more diverse employment profile than the rest of Solu
Khumbu District, and is much less dependent upon subsistence agriculture and herding, though herds are still maintained as pack animals as well as for yarn, hides and
meat.
Average monthly cash income per household in a sample of 33 was NRs 15,725. Lowest, mean and highest figures are NRs 600, 9,000 and 60,000. On a per capita basis
the range is from NRs 300 to 15,000. Differences in economic status may not be so
marked as this disparity may suggest, since the subsistence economy and barter systems still operate. The average personal monthly income equates to around US$ 555
per annum (at 1 US$ = NRs. 70), where estimated national per capita GNP in 1996
was US$ 210. No comparative baseline data are available but it is fair to surmise on
qualitative evidence that the project has assisted growth in incomes.
The impacts of electricity on employment are marked, but the increase in job numbers
is not as dramatic as the new economic activities might suggest. This is because the
businesses that have arisen from the opportunities electricity makes available are still
largely family-run. Certainly some new positions have been created, but they tend to be
filled part-time by family members who are also undertaking other activities; for example, one laundry owner also earns money as a guide to trekkers during the season,
while his wife runs the shop and his daughters help with the laundry after they have
gone out in the early morning to gather dung to cook at home. They employ no external
labour.
In the Namche Bazaar project area, the number of jobs per household surveyed averages 3.7 in a household averaging 5.5 persons, while in the Rangjung project area
survey, there are on average 1.4 jobs in households averaging 6.7 members.
In all, the new businesses mentioned above have created 24 new non-family positions,
17 occupied by males and 7 by females. These positions are seasonal, and occupy the
persons concerned from four to nine months of the year.
This shows that in the more mature market and the more reliable electricity supply
situation of Namche Bazaar, there has been a comparatively favourable impact on the
number and variety of employment opportunity, some directly linked to electrification.
However, lack of desirable employment opportunity continues to be a source of social
concern, and still results in clusters of mainly male youths loitering in the bazaar with
time on their hands. Asked to rank priorities for development and investment, both men
and women in Namche Bazaar cited employment as either first or second priority of
nine items, (water, food, housing, employment, health, education, electricity, transport,
recreation and entertainment). In subsistence-based Trashigang, economic activity is
th
not a choice, but a strategy for survival; both sexes ranked employment 8 , indicating
instead priority concerns about water, food, health and education, much closer to the
basics in the hierarchy of needs.
No-one instanced loss of employment through electrification. However, the fuel wood
porters, often Rai or Magar people from the neighbouring middle hills and Terai, who
carry fuel wood in from outside the National Park boundaries must be affected, given
the consensus that fuel wood use has declined by about one third since the commissioning of the Namche Bazaar installation.
Page 53
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
Impacts on the Household Economy
The advent of electricity has made quite profound changes to patterns of household
energy use and expenditure. Baseline data for energy use prior to commissioning of
the system is not available, but most people interviewed said they spent less on energy
overall now than before. Fuel use patterns reported in the household surveys are
shown in the table below. Blanks indicate that no user or main use emerged from the
survey results.
Number of Users and Percentage Main Use of Household Fuels
Lighting
Cooking
Boiling Water Space Heating
Candles
33
Gas
0
9
5
Kerosene
41
22
16
3
1
Main Use %
Fuel wood
25
59
43
55
Main Use %
8
49
56
78
Electricity
56
53
50
27
Main Use %
87
46
43
22
Other
6
Main Use %
5
6
Figure 19: Household fuels used in the Namche Bazaar area
Significant is the relegation of kerosene from its former position as principle lighting
fuel to that of an adjunct for cooking.
The decline in dependence on fuel wood is dramatic in the short space of five years.
Electricity has made an astonishingly rapid ascent as most used fuel for cooking and
boiling water in almost half the households surveyed. This is no mere conquest of cost;
46% of heads of households, and 53% of spouses named electricity as their preferred
cooking fuel, citing cleanliness and convenience. Ama Samuha (Women’s Group) representatives from Thamo and Thame complained that when the power supply was interrupted for maintenance, they had to adapt the family menu and their cooking patterns, and were quite aggrieved about this retrogressive requirement. “I lost my eyes”,
complained the President.
The Ama Samuha calculated that non-commercial households spend about 7% of their
cash income on average on electricity, and believe that 60% of their energy requirements are now met by this resource.
Fuel wood may not be taken from living trees in the Park, and costs around 10 NRs per
kilo to import from the now depleting buffer zones. Average wood-cooking household
use is around 10 kg per day, giving expenditure of up to NRs 3,000 per month if commercial fuel wood is used exclusively. Most families say they gather and do not buy
wood, but in fact, 63% hire labour to fetch the wood, which they then regard as free.
A wood porter typically costs NRs 150 per day. The wood, around 30 kg per day/load,
is included in this price. Monthly costs, assuming usage of 10 kg per day, are around
NRs 1,500. The wood porter is sometimes a family employee, undertaking other duties
Page 54
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
such as herding on non-wood portering days. Some families hire a porter to work solidly two to three months in the off-season to deliver the year’s wood supply.
By comparison, households reporting cooking mainly with electricity are for the most
part Level 3 consumers, spending only NRs 600 per month on electricity. This includes
lighting and other uses.
Also significant is the use of electricity by somewhat less than one quarter of the sample as their main source of space heating, notoriously the hardest use to displace fuel
wood, with its appeal of flickering flame, and its association with warmth, hospitality
and sociality.
The case history below illustrates one household’s experience of impacts of electricity
on the household economy.
Case History
A family of five in Khumjung are now Level 3 consumers, paying a fixed NRs 600 per
month for electricity. The house is lit with electricity, and they have an electric cooking
coil and a blender. They now use almost no fuel wood, since it is quick and convenient
to cook on the coil, and they have learned to plan the cooking so that one is enough.
Sometimes the children gather dung that they use in the old stove for extra warmth.
They do not miss the appearance of the fire; it was smoky and made everything dirty,
and besides, the house is now so bright.
Before they were connected, they used wood for some of their light requirements, and
for cooking and heating. It cost them NRs 100 per day for the labourer they employed
to fetch it. The house was lit elsewhere with kerosene wick lamps. Supply was sometimes short; they eked it out, using only about two litres a month, at a cost of NRs 50
per litre. Their total monthly energy cash cost was usually about NRs 3,100 per month.
Their costs are now 20% of that sum.
The impact on the budget is not the only change; they have good light, and the house
feels more spacious and pleasant. The children are learning better, and everyone feels
more energetic and inspired to work since they had electricity. Their health has not
really changed, but they feel better.
Social life has changed; before the youngsters used to gather in houses in the evening,
and sing and dance. This has diminished; they are doing more homework.
But cultural and religious life are easier. There is lighting for festivals, and the lama can
come at night now, and stay longer because there is good artificial light. The family remembers the old dark days, and wants to express thanks for the electricity that has
given them new eyes.
…End of story…
Page 55
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
Figure 20: Locally available hot plate or electric coil in a local home
Electricity is correctly perceived as offering very good value for money in the household
budget, and as being no longer a luxury, but a necessity of everyday life. In addition,
there have been changes in the time spent fuel wood gathering; 78% spend less time,
19% the same, and only one household reports spending more time. In some cases,
time has little opportunity value, but as seen from the number of sources of earnings
per household in this area, people put “spare” time to economically productive use.
Ownership of Electrical Appliances
Ownership of electrical appliances is a good indicator not only of electricity use, but
also a surrogate measure of affluence where it is difficult to obtain data about household income and expenditure. Householders recorded appliance ownership and use as
shown in the Table Figure 21.
The penetration of consumer durables shown in this table is the more remarkable for
the fact that there are no appliance service facilities in the project area. Appliances that
fail are frequently simply written off, and the owner purchases a new item. No instances were reported where a failed appliance was not replaced with something of a
similar function, suggesting that people value the qualities the appliance confers, and
are willing and able to spend considerable sums and take quite heavy risks to secure
those advantages. Namche Bazaar consumers did not indicate in the household survey that they find appliance expensive.
Page 56
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
Ownership of Appliances
Item
Number of owners
Percentage of sample
Light bulbs
Tube lights
30
100
30
100
Radio cassette deck
22
73
TV
11
37
Fan
4
13
Refrigerator
7
23
Space heater
13
43
Water heater
20
67
Hot plate, cooker
22
73
Iron
8
27
Mixer, grinder, blender
19
63
Power tools
1
3
Other
5
17
Data Source: Household Surveys, October-November 2000.
Sample size: 30
Figure 21: Ownership of electric appliances
Health Impacts
Impacts on health can be considered under two main headings, delivery of services,
and health outcomes. Both are reported to be positive.
The project area is served by a hospital funded by the Hilary Commission in Khunde,
Khumjung VDC. At the time of its foundation, Khunde was the largest village in the
area, but has now been somewhat overshadowed by the more strategically located
Namche Bazaar VDC and Khumjung village.
Though its location is not ideal for the main commercial hub, the hospital is very well
appointed. It has always had electricity from a stand-alone generator, but had insufficient capacity to run all services simultaneously. It also has solar panels to lighting and
water heating.
The hospital is equipped with and x-ray machine, 2 oxygen concentrators, and operating lamp, power microscope, ECG apparatus, ultrasound machine, incubator, opthalmascope and centrifuge. Connection to the Namche Bazaar system has enabled the
hospital to acquire and run recent electrical equipment arrivals: a new electrickerosene refrigerator for vaccines, a domestic refrigerator-freezer, a computer, microwave oven, oil filled heaters, an electric oven, water heaters, TV, video, a slide projector and a telephone.
There is a resident doctor and her family, and 3 local staff – a qualified nurse and two
medical assistants, who serve a population of about 10,000 in the hospital catchment
area.
Since the arrival of the minigrid, the hospital uses electricity for cooking, heating water
and space heating, displacing the old coal/wood range that used to perform this func-
Page 57
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
tion. Laundry is washed by hand using hot water, and dried in the sun to assist sterilisation. Rubbish, including surgical waste and sharps are disposed of on the “three B”
system; burn, bash and bury.
The arrival of a reliable electricity supply has enabled the hospital to speed up throughput of the 30-50 patients who are present each day, as they can now see more than
one patient at a time, and use more than one item of diagnostic or treatment equipment simultaneously.
The impacts of electrification on health outcomes are difficult to quantify as the hospital
has not yet computerised its records, but staff assert that there is a change in the
cases they see; they note that women under 30 do not squint like the women who grew
up and cooked in smoky kitchens, and though upper respiratory infection is still prevalent, it is predominantly males suffering the effects of tobacco smoking rather than females suffering the effects of wood fires in the home.
Since the hospital opened in 1966, the birth rate has dropped from around 8 children
per family to around 3, though this is not necessarily only an impact of electrification.
Home birth is still the norm; around 15 babies per year are delivered at the hospital,
and the presence of reliable electricity helps to make the service safe and readily
available at all hours. The average age of death is considerably higher than the 52 for
males and 54 for females averaged in the rest of the country; local people die on average in their mid to late sixties.
Education Impacts
With partial electrification of the school, dramatic changes have occurred to living,
teaching and study conditions for both staff and students. Educational outcomes are
also improved, with motivated students achieving better results, and students tending
to remain longer at school as it attractions increase and the benefits of education are
better known.
Case history
“Revolutionary changes” have occurred in education since electrification, says the
Principal of the Khumjung High School, the only school in the two VDCs. The school
offers Grades 1-10 education to 330 students, of which about 40% are female. Some
20 students are resident in the hostel, living too far from home to travel daily. The students from Namche Bazaar walk an hour or more each way over a saddle 3900 metres
above sea level to attend school each day. Schooling is free, and the teachers distribute pens and books to the 20% or so needy children.
There are 11 classrooms, and 15 salaried teachers, most of whom are seasonal residents rather than locals. Prior to electrification it was hard to recruit and retain teachers, as the area is remote and offers few comforts. Teachers had to buy kerosene and
collect fuel wood. A welcome outcome has been that now that the school is electrified,
teachers have electric light and cooking facilities, better food, a radio cassette recorder,
television for videos. Recruitment has ceased to be a problem, and they can read, prepare and mark lessons at night.
Page 58
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
Figure 22: The Head Master of Khunde High School with an array of Media Equipment
Four of the eleven classrooms have electric light and power points, so the students can
use videos for language and other training. The science laboratory has no electricity;
one of the school’s development plans is to electrify and warm all classrooms. Electricity has also made possible listening to the radio. This has proved very beneficial to
learning; before, the children “did not know their own language and culture”.
The students do not work much at household tasks at home, and most do their homework. Motivated students are performing better with the enhanced opportunities to
study afforded by electric light; some are not interested and show no particular improvement.
The school leaving age seems to be higher, as parents and students are more aware
of the needs for education. Most now leave at age 16 or 17, though girls tend to leave
on average two years earlier than boys. The ratio of males to females becomes progressively higher in the last three or four years of schooling.
When electricity first came to the area, there was no particular teaching module to assist consumers to know about safe use, though the physics course contains some information. KBC distributed posters and gave some consumer education. Fortunately
each home has an ELCB, which prevents accidents, and now people understand better
about electricity, and learn at home.
A welcome development with electrification was the possibility of offering non-formal
education in the evenings; many residents over the age of 40 had no educational facility available, before the School opened, and are now attending basic literacy and numeracy courses.
Environmental awareness is part of the school curriculum, and has increased since
electrification. With it has come the ability to respond to environmental concerns. Even
the simplest households are now using electricity not only for lighting, but also for cooking. Electricity has transformed education not only in the school, but education in the
wider school of life.
…End of story…
Page 59
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
Cultural Impacts
There can be no doubt that cultural, social and spiritual life have been affected not only
by electrification, but also by the onslaught of outside influences that were in part responsible for the urgency for electrification.
Local people are resolutely positive about the nature and impact of these changes, and
speak in terms of the new windows opening on to the world as reinforcing their confidence in their culture and customs, and of electricity specifically assisting them in the
expression and preservation of their way of life. Only one person expressed offence
about what is heard on radio or seen on TV.
The Chairman of the Monastery Society commented favourably on impacts on the religious life. Conditions are much easier, now, in the Gompa, especially in the kitchen,
and in the availability of good light and pumped water. Before, during the major festival
week, the monastery employed 10-15 people who worked all day every day carrying
water 20-30 litres at a time from Namche Bazaar up to the Monastery, a vertical climb
of about 400 metres. Water can now be pumped from the public supply, and this enables the monastery to focus on the religious aspects of the celebration, and frees
them from logistical concerns of caring for the health safety and sanitation of the hundreds of guests and pilgrims who attend the festival.
The Gompa has electric light, a blender, and occasionally uses a rice cooker, though
most cooking is still done with fuel wood donated by the village faithful. Before, they
used pressure lamps run on kerosene donated by the villagers. At festival time, they
required three or four pressure lamps for five to six hours daily, using about 1.5 litres
each per day. When the lama was by himself he used a simple wick lamp, and used
only 3-4 litres of kerosene per month. The Gompa is a level 3 electricity consumer, and
the monthly charge of NRs 600 is met out of its own budget.
The impacts of electrification are as good as they are bad. There is a tendency for
youth to be less interested in religious observance, but they come back to it as they
mature.
Changes in social life see young people in the last two year in pool bars, which aggravate the tendency to gamble and get in to financial difficulties. There is also some
noise disturbance down in the bazaar, especially associated with alcohol consumption.,
but this is nationwide phenomenon, and is only incidentally associated with electrification in his view.
The lama agrees that there has been change to cultural life, but sees this as part of the
wider phenomenon of globalisation that requires management in terms of preservation
of cultural identity.
Sociality has also generally increased since electrification; people visit each other in
the evenings, because the light in homes is brighter, they can share entertainment, and
street lighting helps them to see the way safely.
The police say that their job is facilitated by street lighting. The communities are on the
whole law abiding, and the worst problem they face is usually local youthful drunkenness and disorder. Trekkers do not generally cause any offence or disturbance.
The President of the Sagarmatha Club, a youth group with mainly young male membership, states that the cultural impacts of electrification have been wholly beneficial
from their standpoint. The Club practices song and dance, and puts on small shows in
the Monastery, or larger programmes in a tent on the school grounds. During Visit Nepal ’98 year, they staged a concert for which an admission charge of NRs 100-150 was
made, and they raised NRs 15,000 for activities. These include assisting students with
Page 60
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
education expenses, running an AIDS awareness campaign, and participating in environmental clean-ups. They need electricity for sound and light to stage such cultural
events. The group has made a CD of Sherpa song, which would never have been possible without electricity.
Maintaining the membership of the group is a problem, as many members leave the
area to study. They believe that the presence of electricity and the cultural stimulus this
facilitates is a factor in getting local people to return and participate in their own culture
and society.
Both young and old, lay and religious in general reject the idea that their identity and
culture is under electrical siege, and express a determination to harness electricity to
their own cultural ends.
3.4.7
Gender aspects
Question Q7: How do the impacts compare in terms of gender balance? How has the work load of women
and children changed? In what way have gender aspects been considered in design and
implementation of the projects? What gender specific support mechanisms have been developed?
While gender considerations were not part of the implementation design brief, women
do not feel that they were excluded from decisions in which they should have participated, and on the whole consider themselves to have been winners from the process
of electrification.
Questions in the household survey about development objectives of the head of
household and spouse of the head of household reveal harmony in setting priorities
between head of household and spouse. In general Sherpa women identify strongly
with their roles and exercise a greater degree of independence and self-determination
than women of most groups in Nepal. The table below sets out relative ranking of development priorities. In most cases the head of the household is male.
In no case are the rankings more than one position apart. Electricity supply takes its
place in the middle of the field, reflecting perhaps that people feel that basic livelihood
and infrastructure are secure, and are looking to development of quality of life improvement.
Women did not express frustration over any aspect of electricity supply through the
household surveys, though as businesswomen managing shops or lodges, and
through the Ama Samuha they protested about the losses and inconvenience caused
by seasonal maintenance outages as vociferously as their male counterparts.
Page 61
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
Figure 23: Women of the Thame Women’s Association being interviewed
Women participate fully as family members in the income generating opportunities that
electricity has brought. Some enterprises are run by women; a bakery, a pizza hut,
laundry service, shower and sauna service are all run by women who either live locally
or have local matrilineal connections. Men, however, outnumber women four to one in
new jobs held by non-family members.
Ranking of Development Priorities
Item
Water supply
Food production & preparation (cooking)
Housing improvement
Employment opportunities
Health services
Education services
Electricity connection / supply
improvement
Transportation facilities
Entertainment and recreation
Head of Household
Spouse of
Head of
Household
4
7
4
8
6
3
1
2
4
5
2
1
2
5
7
9
7
9
Data source: Household surveys October-November 2000
Figure 24: Ranking of Development Priorities
Women work longer since electrification, but still say that they have enough time for
themselves. A third of household respondents say they do housework and handcrafts
in the evening, while three quarters say they talk, read, watch videos or listen to the
radio.
Page 62
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
The local women’s group has been running for three years, and participates in religious
festivals, runs a credit and savings programme for members, has kitchen garden and
livestock raising programmes, and cooking courses for lodges. Electricity has facilitated their festival participation, and has changed and eased their cooking patterns.
One of the more popular appliances is the kitchen blender, which is rapidly displacing
the traditional butter churn used to make butter for special Tibetan tea. The appliances
that feature in electrified household have a heavy bias towards women’s labour saving.
Both sexes state that electricity supply is of highest importance to them. Most of all,
(83%) they value the labour saving that has occurred, but also prize the health improvements through not having such smoky houses (37%), and the entertainment they
can now enjoy (27%)
While both sexes unequivocally enjoy having and using electricity, it has probably contributed most to improvements in the quality of women’s lives.
3.4.8
Environmental impacts
Question Q8: How were the sensitive ecological conditions and consequences taken into account and
what measures for resource protection have been taken? What are the direct and indirect
impacts of the energy supply through hydropower on the conservation of the natural resources (in the project area and downstream) and in the energy balance of the households,
esp. fuel wood harvesting?
Background
In the past, the Khumbu area including the present project area was under dense forest cover. The old name of “Nauche” implies a “dense forest” in Sherpa dialect. The
original area under forest in the Khumbu area is estimated at 5,500ha. Today, the relatively dense forest comprising natural stand, planted and regenerated ones is limited at
only a few localities such as “Pare ko jungle” across Thamo, Phortse , Syangboche
near “Everest View Hotel” , and Namche-Lukla corridor along the river banks of
Dudhkoshi and outside the national park area.
Fuel wood is today obtained from forests mostly lying outside of the national park and
some lying within the protected area permitted collectors. There are no private plantations. Generally fuel woods are collected during the spring and summer season. With
the advent of electricity supply, the traditional pattern of energy use characterized by
the heavy dependence on fuel woods has changed. In addition to the use of electricity
for cooking and heating, alternative fuels are used increasingly, such as kerosene and
bottled gas. The widespread use of thermos flasks, and the adoption of insulation in
newly constructed houses adds to the wood substitution effect.
Loss of land and land use changes
For the construction of the Thame small hydro-electric plant, the major structural works
of intake and powerhouse were constructed on barren and public grazing lands. There
has been no loss of productive farmlands and houses. Due to the “run-of-river”
scheme, no inundation has taken place, and burying of the penstock pipe and transmission lines along the open trail, and trimming instead of felling of tall trees along the
alignment of the transmission line, there has been a minimal negative impact.
Also, there is no land use change that could be attributed to the electrification of the
area.
Page 63
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
Environmental Survey
An environmental survey has been carried out by the evaluating team’s environmentalist. His main findings follow:
As there is regular supply of water from the spring catchment and from the Thame
khola, there exist no chances of the river section going dry. This was confirmed by
looking at the data of stream gauging by KBC.
Altogether 10 microinvertebrates river fauna species, 11 aquatic plant species have
been identified in different sample sites. There was no record of fish species and submerged, floating leaved aquatic species. The average population estimation of river
fauna indicated insignificant differences at sample sites above and below the power
scheme, and at alternate sites.
In relation to the composition and distribution pattern of aquatic flora, comprising periphytons, aquatic moss and filamentous algae; samples taken at different sites also
indicated insignificant environmental impact from the Thame hydropower plant on the
river ecology and biodiversity status of the project area.
Status of erosion problems
The number of landslides in terms of gulleys and signs of overgrazing was found
higher at the powerhouse site, the intake upstream, and at the downstream outlet, and
relatively less in the access road and transmission line. This can be attributed to the
impact of the GLOF in 1985 in Bhotekoshi river. The Thame stream is erosion prone
and consists of relatively loose, calcareous moraine deposit soils in river bank sides,
and it has sparse vegetation cover.
The fragility status of the access road site joining the intake and powerhouse site features relatively fewer gulleys/landslides and signs of overgrazing This implies relatively
sound soil and water conservation and grazing management.
The transmission line alignment features a marginal extent of habitat disturbance and
cases of overgrazing. This can be related with good forest management and adoption
of environment friendly approaches during the construction phase.
The hillside and steep slope between the power plant intake and the powerhouse have
been replanted almost completely. The entire area is fenced in to protect it from grazing cattle and mountain goats, and notice boards are in place to keep people out.
However at places just like near Phurtse along Namche-Thamo trail, in upper reach of
eco Himal constructed Thame trail, there has been extensive quarry work to the extent
that the local trail is damaged. This was done with permission of the Sagarmatha national park authority. Evidently, this indicates inadequate monitoring from concerned
park officials. As the project area features more problems of wind induced rather than
rainfall induced soil erosion, there is a need of adequate ground cover and shelterbelt
plantation of tall trees such as silver fir and blue pine which are fast growing.
Impact of electricity usage on fuel wood consumption
Traditionally the forest of Khumbu area has been serving as a source of fuel wood and
construction timber. The use of fuel wood is still persisting for cooking and room heating but in substantially reduced quantity among the electricity users. Protection of the
National Park is much easier to implement since the advent of electricity.
Page 64
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
Systematic reforestation
Started as a measure to correct scars from the construction period, reforestation has
become a regular activity of KBC itself. A tree nursery is maintained with three full-time
staff, and most construction damage is today overgrown with new trees. Reforestation
of other areas is going on in collaboration with the village communities and with the
Thame Valley Development Project.
3.4.9
Sustainability of project institutional structures
Question Q9: Which measures to achieve viability and sustainability of interventions have been taken?
How far have relevant institutions and capacities been developed?
The Namche SHP functions well under the management of KBC, despite a number of
remaining flaws in the design and quality of civil structures and installations. KBC is
technically capable and motivated to maintain and operate the scheme. This is substantiated by the fact that also difficult repair jobs were carried out without outside assistance in the past year.
The Namche SHP has not achieved sustainability in financial terms so far
Sustainability may be judged by the success of KBC. If it is surviving and doing well
financially, the project is sustainable. In financial terms, the operation of KBC is still
critical. In the five years of operation, it has not been possible to develop the load factor
to its maximum, and income from electricity sales is still relatively small. Depreciation,
the main financial instrument to build up reserves and thereby attain sustainability, has
not been possible at all so far. KBC sees itself in a very difficult situation in this area.
Raising tariffs is very unpopular with consumers and meets with opposition. Also, it
compromises levels of fuel wood substitution achieved.
Required earnings for financial sustainability
As mentioned above, KBC must be in a position to depreciate its assets in order to become sustainable. Depreciation will not guarantee sustainability, but in accounting
terms, it is a first necessary step. To make depreciation possible, earnings must be
much higher than at present.
An attempt is made here to show what the financial requirements are to establish a
long term sustainable operation.
The assets of KBC are in the books with an amount of roughly NRs. 140’000’000, including “under construction assets”. This is equivalent to approximately ATS 28 Mil14
lion . A first problem is here, that assets are much lower than the cost of the project
which stood at about ATS 50 Million for equipment, transmission and distribution. Another problem is that on the basis of Nepalese currency, replacement cost will ultimately be higher than original cost due to continuing inflation. Nevertheless, in terms of
accounting, depreciation must be done on the basis of the book value of the assets.
There are different methods of depreciating which is not important at this point. However, what is important is a realistic time frame for full depreciation. 25 years is a life
time often used for this purpose for small hydro schemes. With the straight-line depreciation method, this simply results in a depreciation rate of 4% per year. (100/25). The
amount of depreciation which results from this is NRs. 5,6 Million, which must be covered by earnings.
14
calculated with an exchange rate of 0.2 ATS for 1 NRs.
Page 65
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
In addition, to account for the difference between the book assets and the actual value,
KBC must generate profit/reserves of about an amount which is equivalent to depreciation. This adds up to a total cash-flow of about NRs. 10 Million. If it is possible to do
this, KBC would accumulate reserves on the order of 250 Million over a period of 25
years. This amount could then be used for replacement of the entire scheme after 25
years, or a part of it at an earlier date for partial replacements.
At present, on the basis of the first two financial years of independent operation, the
cash flow that KBC generated was roughly NRs. 1 Million on average. In the most recent financial year, ending in July 2000, cash flow generated amounted to around NRs.
3.5 Million, an increase by a factor of about 3. It is assumed that this is a result of the
massive tariff increase at the beginning of the financial year. In the years to come, it
must increase its net earnings again by a factor of about 3 to 4 to achieve full financial
independence and sustainability.
The implications of this are serious, because only two means are available with the
present plant to increase earnings: a) increasing the quantity of electricity sold by increasing the overall load factor, and b) increasing tariffs. A third means of increasing
income is new activities, such as the water supply scheme. In fact, this has already
contributed roughly half a Million Rupees to last years earnings for 9 months of opera15
tion. .
The load factor stands at present at about 41% overall. On the one hand, in technical
terms, a large potential exists to build up the load factor, broadening the income base.
A combination of technical measures (remote control load switching) and administrative measures (tariff differentiation) will enable KBC to effectively pursue load development. On the other hand, the discontinuity of the tourism trade over the year will also
set limits to full use of the generating potential. It is unlikely that the present load factor
can be more than doubled. This would nearly double the income to about NRs. 6 Million at today’s tariffs.
From this follows that tariff increases and other measures would have to result in earnings of about another 4 Million. In the light of this, it is fair to say that, from the point of
view of financial sustainability, the average price of electricity that is paid to KBC is
much too low. It would have to be almost doubled as soon as possible, and inflation
adjustments will have to be done periodically.
At a level of sales of roughly 2’000 MWh, KBC has realised gross earnings of NRs.
3.73 Million, according to the profit and loss account of the financial year that ended on
16
16 July 1999 . The resulting average price of electricity was therefore NRs. 1.86/kWh,
about equivalent to 2.5 US cents per kWh. This is less than almost anywhere else
worldwide! It explains, why income today is insufficient and why this is ultimately not
sustainable.
Solutions
Answers to the problem are difficult but not impossible to find. New activities that are
supposed to generate additional income like the drinking water supply scheme, have
already shown some potential, as per the most recent information received. Tariff increases to the tune required will be difficult politically. However, the commercial tariff
charged is still well below NEA rates, and a part of the answer is to work on the persistent transformation of non-metered consumers to metered consumption. To a degree,
15
Income and cost information for the last financial year (mid 99 to mid 2000) is from KBC, dated March 2001, as a
reaction to the draft report.
16
This was the most recent reliable data at the time of the evaluation
Page 66
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
higher tariffs will jeopardize wood substitution levels achieved. The process therefore
has to be a cautious one.
However difficult it might appear to achieve the stated earning objectives, there are
only two choices: a) achieve income levels shown as soon as possible, thereby becoming economically viable, or b) subsidise the operation of KBC in the long term. A realistic outcome is most likely somewhere between the two extremes. A considerable increase in income to a level that is still below the 100% target will permit partial depreciation and reserve accumulation and a subsidy of operations may not be necessary at
all. It is conceivable that wealth accumulation that takes place in the project area, not in
the least because of the opportunities that electricity opened up, can be invested in renewing and replacing the power plant in the long term future.
Institutional sustainability
Sustainability may also be judged by the stability and quality of KBC as an institution.
KBC appears to be well established and well run on the operative level. On the level of
strategy and long term business development, and in view of the gigantic task ahead
as outlined above, it lacks active leadership. The role of the board of directors remains
ambivalent. Given the existing set up, where consumers are represented in the board
of KBC, it is difficult to see how these representatives could possibly identify fully with
company interests rather than opposite consumer interest.
3.4.10 Project Steering
Question Q10: How effective have been the steering measures and the backstopping of the HQ and the
co-ordinating offices? Which conclusions can be drawn from this for the steering of similar
interventions in future?
Steering measures and backstopping have been adequate, otherwise it is unlikely that
the project could have been brought to a successful end. It has become evident from
the study of documents over the period of project implementation, that personal continuity from the side of HQ has been a big asset. Only with this was the required persistence possible. The task of BMfaA was made difficult by the lack of direct local and
permanent representation. This may have been cost effective, but not ideal in terms of
obtaining first hand critical information. It could only work on a basis of trust in the institutions to which all activities were delegated. It also implies that the steering role was
reactive rather than pro-active, because action could only be taken as and when critical
information was provided.
Lack of reporting cost information
Largely, HQ had to rely on periodical reporting. In this connection, no evidence could
be found during the study of documents, that budget and cost information was supplied
on a regular periodical basis. It is the evaluator’s opinion that such information would
have been an important component of reporting, and it would have made controlling
more effective. Besides, it is exactly this requirement that is prescribed in the terms of
contracts17 awarded by the BMfaA.
The conclusion is that reporting of the current budgetary and cost situation should be
integrated into regular reporting in projects of considerable complexity. Concurrence
with contract clauses should be checked, and in case of non-compliance, corrective
action should be taken.
17
document referred to: Förderungsvertrag EH-Projekt 908-01-93-03-660-240-Nepal, …., Absatz 4.3.2
Page 67
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
Contract documents are important
In a situation where all implementation activities are delegated through contracts, contract documents, from initial tender to supplier’s and consultants contract agreements,
become enormously important. In a legal sense, contractors need to fulfil what is stipulated in the contract; no more and no less. If the contract is superficial, incomplete or
faulty, it is difficult or impossible to obtain top quality supply of goods and services.
Also, legal recourse in case of suspected default is very troublesome and it may fail
altogether due to a lack of specific stipulations.
18
Suppliers and contractors agree that good contract documents are important but feel
that specifications were in order. Checking the fulfilment of specifications is a process
that starts with acceptance checks at the works of the supplier (Werksabnahme), and
ends with acceptance of the installed equipment during commissioning. It did not become clear during evaluation what exactly were the results of this process. Apparently
there was some gap in the procedure, either in actually carrying out the necessary
steps, or in its documentation, or possibly both.
3.4.11 Lessons Learned for Sector Policy Development
Question Q11: What role do such interventions play in the development of a sector policy (of the Austrian
development co-operation)? Which conclusions and recommendations can be drawn?
Lessons may be learned at various levels, but not all are naturally of the same relevance.
Impact of the intervention
Electricity supply to rural areas can assist development activities and can substantially
improve living conditions. In Namche Bazaar, numerous economic development opportunities have opened up on the basis of electricity and the growing tourism industry.
Small hydropower is the most effective means of electricity supply in Nepal. Cost-wise,
it appears that large hydro and micro hydro plants to have some advantage over small
hydro.
Interventions in the field of small hydro for rural electrification require a long-term engagement (>15 years), especially in a situation where the institution building task finds
itself in a pioneering role.
The example set by Austria with the Namche SHP was adopted at the national level.
The Ninth Development Plan largely mentions the principles of the Namche institutional set up as the formula for future remote rural electrification.
Negative environmental impacts were kept in check, mostly by the reforestation activity
which became a part of the project.
There is a positive environmental impact of the project in terms of fuel wood substitution at the household level and in the tourism industry. However, sustainable levels of
fuel wood use cannot be brought about through electrification alone. In addition, energy
saving measures in cooking and space heating are required. General economic development with an increase in purchasing power will help most. People will naturally
switch to modern fuels when their opportunity costs for the long hours of firewood
gathering exceed the costs of the modern, commercial fuels.
18
Statement based on interviews with Messrs. G. Geppert of Geppert & Co., and B. Jud, of Fiegl + Spielberger
Page 68
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
Policy Level
New interventions bear a lot of risk in terms of commitment required
The interventions for the implementation of the Namche SHP have been new in terms
of current activities of the BMfaA at that time. The original intention for the project (to
build a small hydro scheme) was very different from what the BMfaA ended up with after almost 25 years of interventions. The lesson learnt is that projects of such complexity as remote rural electrification require persistence and the means to see the
intervention through. The partner is often weaker in terms of available resources. This
implies that unexpected requirements will usually fall back on the donor.
A comprehensive and multi-level approach is advisable
A considerable number of other small hydro schemes in Nepal (and elsewhere) are
today on an institutional basis that is by far not as solid and sustainable as the Namche
Bazaar scheme today proves to be. To achieve this better result, Austria had to make
inroads into areas such as local ownership and institution building. “Difficult” objectives
such as democratisation for example, cannot be achieved in volatile political situations
as were met, with a superficial input. This is probably also true for all other objectives in
the human resource/social sphere. The lesson learned towards sector policy development derived from this is: Interventions that have a significant impact need to be comprehensive. Interventions cannot be limited to the level of the project but have to be
extended to the policy level.
The time required to achieve success is often underestimated
The time requirement for interventions in the areas of infrastructure and institution
building cannot be stressed enough: The intervention in Nepal carried on for almost 25
years. Other examples show that significant results require 10+ years. On the other
hand, the government budgeting process is typically on a yearly basis and this results
in an inadequate planning outlook. While the solution to this problem is beyond sector
policy, the lesson learned is that a very considerable time requirement must be made
clear and understood on all levels, and that the issue must be addressed on a higher
level.
Considerable human and material resources are required
The previous lessons make it clear also that considerable human and material resources are required. Also, professional and social skills required of personnel engaged are considerable.
Setting priorities
Looking beyond the Namche Bazaar project, at the entire sector, it is relatively easy to
conclude broadly that the Namche SHP, perhaps on a par with the Swiss Salleri SHP
are among the “best” in the country. Both interventions were of a long term and comprehensive nature. Other donors have tried superficial interventions, for example by
supplying various sets of electro-mechanical equipment, without any further intervention. These approaches have failed, not only in Nepal, but also elsewhere. Since resources are likely to be scarce, and on the basis of the negative experience of others,
interventions of a long term and comprehensive nature should take precedence over
short-term and superficial interventions,
Page 69
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
Project Steering Level
Context appropriate decisions and flexibility
Flexibility and openness to new issues coming up has been a constant feature of the
interventions, and this was necessary to achieve project success. More adherence to
pre-conceived principles would most likely have done more harm than good. The lesson: Flexibility will be required to be able to act appropriately in the specific context.
Effectivity: Streamlined procedures and short reaction time
There are many reasons why interventions of the nature discussed here take so much
time. Most of these factors, however, are outside the sphere of influence of the donor.
The only area where the BMfaA can possibly make a difference is by streamlining its
administrative procedures as far as possible, and by making sure that personnel on the
various levels have the capacity to attend to matters on short notice.
Efficiency versus control
The implementation of engineering projects classically involves supervision and execution tasks assigned to different professionals and institutions. In a large scale project,
this involves a number of different specialists, each with a specific task. In small projects such as the Namche SHP, for reasons of cost, different tasks need to be executed by one single entity. The issue is here whether it is permissible to assign different
roles to one entity, particularly the supervision and the execution role? Strictly speaking, the answer in no, because it implies that supervision of one’s own work cannot be
impartial. However, in the implementation of the project, this is what happened. The
consulting engineer (supervisor) had to begin organising and subcontracting transportation tasks, thereby moving into the role of the implementer. This was efficient, but
control was lacking.
When Eco Himal “took over” the project, it was assigned the role of implementer. It
executed all activities on behalf of the BMfaA, and sub-contracted various tasks directly. Again, this was efficient, but the independent supervisory function was lacking.
The lesson learned: Improved implementation efficiency bears the risk of less control.
It requires competent and trustworthy partners. Partner selection is therefore of paramount importance. This is in no way meant to indicate that this was not done in the
Namche SHP.
Relationship with Austrian suppliers, consultants and others
The award of a supply contract is the basis for the relationship with any supplier. The
process consists of the steps design – equipment specification – tendering – offer
evaluation – contract award – delivery check – operational testing and commissioning –
various checks within the guarantee period. Using the “chain analogy”: The relationship
breaks at the weakest link. Quality and completeness of specifications determine the
scope of supply. Offer evaluation and contract award reflect the decision of what was
found best, and various checks make sure that the equipment complies to specifications and delivery is complete. It is usually the consulting engineer’s task to assist the
client in carrying out the process. In the case of the Namche SHP there were some
gaps in the process, but it is not clear who’s responsibility it was. It is the supplier’s and
contractor’s opinion that specifications were in order. The difficulties encountered had
largely to do with stipulations that were inaccurate and too general, which could not
have been in the interest of the BmfaA.
Page 70
ÖEZA, Projekt 1389
SmallHydro Project Evaluation Nepal & Bhutan
Final Report
The lesson: It must be assured that contracts are very specific and that tasks are assigned in detail. The process described must be followed through from beginning to
end. The last step is specially important. Only within the warranty period will claims be
honoured by the supplier.
Page 71