International Journal of Engineering Research
Volume No.5, Issue Special 1 pp : 164-167
ISSN:2319-6890(online),2347-5013(print)
8 & 9 Jan 2016
A Review of EVM Analysis with Primavera
Kunal B. Badgujar, B.A.Konnur, Amarsinh B. Landage
Government College of Engineering, Karad 415124 India
Email:
[email protected],
[email protected],
[email protected]
Abstract - Earned Value Management is a project management
tool that uses information based on cost, schedule and work
performance to define the current status of the project. EVM
helps the manager to extrapolate current trends to predict their
likely final effect. This method is proved effective in cost
control. The Primavera is project management software which
enables users to track and analyze performance of project. The
Report wizard in primavera creates customized reports that
extract specific data from its database. The paper outlines the
basic principles of the EVM & how it can be used successfully
for particular project with help of primavera. Also some
benefits and complications of EVM with reference to Indian
construction sector.
Keywords – Earn Value Analysis Primavera
Introduction
Project management can be defined as a body of knowledge, a
set of principles, or techniques dealing with the planning and
control of projects. Project management in construction consists
of a set of objectives which may be achieved by implementing
a series of operations subject to resource constraints. There are
always potential conflicts between the stated objectives with
regard to scope, cost, time, quality, human, material and
financial resources. These conflicts should be resolved at the
earliest by making the necessary
tradeoffs (change)
or
creating new alternatives.
Traditionally the budgeted cost is evaluated by computing the
difference between planned cost and actual cost incurred in a
project. The focus was on planned expenditure and actual
costs. Earned Value reveals future opportunities and it also
examines actual accomplishment. With the help of Earned
Value Analysis(EVA), project managers get sufficient help to
keep deep intuitive understanding into potential risk areas.
With the help of clearer picture of the project cost
performances, managers can create risk mitigation plans based
on actual cost, schedule and technical progress of the work. It
is like an alarm for the managers to identify and control
problems by taking timely corrective actions before they
become
too great to overcome EVM provides better
understanding of the project in terms of time and cost schedule.
EVA System is a set of guidelines to provide satisfactory
completion of project. It has been seen that to cover cost
overrun, project team undergoes cost reduction either by reducing
the project scope and quality or by providing additional
resources. Similarly in case of time overrun, they plan crashing of
activities or fast tract programs. Therefore with the use of EVA
system, project goals are achieved in better way.
The Primavera enables users to track and analyze performance.
It is a multiuser, multi project system with scheduling and
resource control capabilities supporting multi-tiered project
NCICE@2016
hierarchies, resource scheduling with a focus on roles and
skills, recording of actual data, customizable views, and
user-definable data. It supports an enterprise project structure
(EPS) with an unlimited number of projects, activities, baselines,
resources, work breakdown structures (WBS), organizational
breakdown structures (OBS), user-defined codes, and criticalpath-method (CPM) scheduling and resource leveling.
Primavera also provides centralized resource management. This
includes resource timesheet approval and the ability to
communicate with project resources who use the Progress
Reporter.
In addition, Primavera provides integrated risk management,
issue tracking and management by threshold. The tracking
feature enables users to perform dynamic cross-project rollups
of cost, schedule, and earned value. Project work products and
documents can be assigned to activities and managed centrally.
The Report Wizard creates customized reports that extract
specific data from its database.
Relevance
The primary skills for project management are Scoping (i.e.,
describing and agreeing on project objectives and requirements),
Scheduling, and Estimating. Other skills are Managing resources,
Managing risk and uncertainty, Managing quality,
Communicating and sharing information with stakeholders. It is
still difficult to get the exact answer about the real progress of
many construction projects with manual handling & tracking i.e.
by traditional process. A construction project is perhaps one of
the most complex and dynamic processes if to consider business
and engineering activities. Engineers usually express the
progress of works referring to the time schedule or to the cost
plan. Since the changes or variation orders are normal practice in
real construction projects, more integrated method is needed to
describe the true status of a project.
In project management, the concept of earned value is used to
measure and predict the progress of the on-going project. It has
become very popular now days as a performance measuring
method. EVM keeps the management on their toes. As
EVA is done periodically, management tries to make sure
that all the project parameters are on track. It is probably the
only system used at present which tracks the project in terms
of work, time and money. Timely performance measurement
makes sure that steps can be taken to the bring project back on
track before it’s too late.
With EVM, one can create an effective project portfolio
management process that
Aligns the project portfolio with strategic business
objectives
Completes projects faster and more efficiently
through role-based alignment
doi : 10.17950/ijer/v5i1/038
Page 164
International Journal of Engineering Research
Volume No.5, Issue Special 1 pp : 164-167
ISSN:2319-6890(online),2347-5013(print)
8 & 9 Jan 2016
Accurately measures
both
cost
and schedule
performance
Analyzes and presents project performance data
Increases program visibility through effective and
streamlined communication with all stakeholders.
Project management system is directly responsible on efficient
planning, monitoring and controlling of construction project
with use of project management software Primavera.
Purpose of earned value
The Earned Value method has been developed as a tool
facilitating project progress control. It is used for determining
a project’s status (is it behind or ahead of schedule? is it over
or under budget?) and the scale of current variances from the
plan. Moreover, it allows a project manager to make inferences
on the final effect of the project in terms of cost and, to some
extent, in terms of duration, by extrapolating current trends.
The method is simple: it assumes a simplified model of a
project, and calculations require nothing more than four basic
arithmetic operations. However, the method has been
recognized as a useful tool by many practitioners and
government agencies and has become a standard in project
management. It proved to be versatile enough to be applied to
any type of a project, ranging from defense schemes worth
millions and extending on many years to minor IT projects. The
analysis can be conducted on any level of work breakdown
structure and used by both clients and contractors. The method,
if to be used efficiently, requires a disciplined approach to
collection of data on project cost and progress (on weekly basis)
and the findings are to be processed immediately. The purpose
is to detect any deviation as soon as possible, so that there is
enough time to asses if the deviation is dangerous for the
project and, if necessary, to take corrective actions.
Fig. 1. Earned Value curves; this project is currently (“today”)
over budget and behind schedule.
2.
Project status indicators
PC - Percentage Complete:
PC = BCWP / BAC
CV - Cost Variance - a measure of deviation between
planned and actual cost of works done until the date of
recording progress in money units. If negative, it indicates that
the project is over budget:
CV = ACWP - BCWP
To capture the scale of deviation, it is often expressed as
a fraction of the budgeted cost of works performed:
CV% = CV / BCWP * 100%
The idea of earned value analysis and interpretation of its results
1.
Input data
Figure 1 presents the idea of the Earned Value project
control. The analysis requires following inputs:
BCWS - Budgeted Cost of Works Scheduled - the baseline for
the analysis, cumulated planned costs related to time of their
incurrence;
SV - Schedule Variance - a measure of deviation between the
actual progress and the planned progress. Though it is
interpreted as time deviation, it is expressed in money units. In
other words, it is the difference between the planned cost of
works that have been done and planned cost of works that should
have been done by the reporting date. If negative, it indicates a
delay:
SV = BCWP - BCWS
BCWP - Budgeted Cost of Work Performed - a measure of
physical progress of works expressed by cumulated planned cost
of works actually done related to time, it is also called Earned
Value (like the method it is used by);
To address any distortion caused by the relative value of
activities, it is expressed as a fraction of BCWS:
ACWP – Actual Cost of Work Performed - cumulated amount
payable for works done related to time;
CPI - Cost Performance Index - compares the planned and
actual value of works done, if less than 1, it indicates that the
project has consumed more money than planned, if greater
than 1, there have been savings.
BAC - Budget at Completion - total planned cost of the
whole project, it equals BCWS at the planned finish;
SV% = SV / BCWS * 100%
CPI = BCWP / ACWP
T – Planned duration of Project
SPI - Schedule Performance Index - compares the planned cost
NCICE@2016
doi : 10.17950/ijer/v5i1/038
Page 165
International Journal of Engineering Research
Volume No.5, Issue Special 1 pp : 164-167
ISSN:2319-6890(online),2347-5013(print)
8 & 9 Jan 2016
of works done with planned cost of works planned; if less than
1, it indicates a delay:
(expressed in terms of budgeted costs) and the money left from
the budget:
SPI = BCWP / BCWS
TCPI = (BAC - BCWP) / (BAC - ACWP)
3. Earned Value “forecasting” parameters
EAC - Estimate at Completion - is calculated at the date of
reporting progress to serve as an estimate of the effect of
deviations cumulated from the project’s start on the total
project cost, so it informs how much the project is going to be in
the end, if the cost performance index CPI stays the same:
EAC = BAC / CPI
It is clear that EAC is a simple linear extrapolation of current
tendencies. It does not allow for any future risks or effects of
corrective measures, so it is not a proper forecast. Nevertheless,
EAC indicates the potential scale of cost problems. As the
Earned Value method requires frequent progress checks from
the very beginning of a project, an early EAC-based
constitution that current tendencies are likely to double the
cost are likely to provide a valuable warning signal and trigger
rectifying actions when it is still time.
EAC is not necessarily based on the assumption that future
costs are going to follow the today’s pattern. Other scenarios
can be considered but, as the method rests upon a simplified
model of a project, linear extrapolation is a rule and it proves to
be adequate. The general EAC formula allows for a number of
simple scenarios:
EAC = ACWP + {(BAC - BCWP) / PF}
i.e. EAC is a sum of costs already committed and the
reminder of the budget adjusted by a factor (PF) that
reflects the relationship between the project’s future and its past.
This can be project-specific. Scenarios considered most often are
as follows:
1. the cost of remaining task is going to be as planned, i.e.
future costs are not related to current costs, PF=1, so:
EAC = BAC + CV
2. the cost of remaining tasks is going to stay in proportion to
current CPI as in equation (8); it ignores the real-life timecost relationship (if a project is to be accelerated, it usually
requires more money);
3. the cost of remaining tasks will be related to current
tendencies of both schedule and cost performance, so the PF is a
Critical Ratio (CR), called also a Schedule Cost Ratio (SCR):
SCI = CPI × SPI
Another measure used for forecasting (or rather for simple
extrapolation) is TCPI (To Complete Performance Index) - a
value of cost performance index that is to be maintained from
now on if the project is to be completed to budget. In other
words, TCPI is a proportion between the remaining work
NCICE@2016
If it is much higher than 1 and the current CPI, it indicates the
scale of effort needed for searching for economies.
Advantages of EVM
EVM keeps the management on their toes. As EVM is done
periodically, management tries to make sure that all project
parameter on track. It measures & predict the progress in the
ongoing project in terms of work, time & money. It also
allows the manager to be on time & on budget. The Cost
Performance Index (CPI) and Schedule Performance Index
(SPI) provides an early warning signals. It is mostly suitable for
the huge construction project. EVM timely performance
measurement
make
sure
that
steps
can
be taken to the bring project back on track before it’s too late.
Application of EVM
EVM provides project managers and the organizations
with triggers or early warning signals that allow them to take
timely actions in response to indicators of poor performance
and enhance the opportunities for project success. Such
indicators have been found to be reliable as early as 15% into a
project. Better planning & resource allocation associated with
the early period of a project might be the cause of this reliability
EVM can be used for progress payments to contractors based
on the EV of contracted or outsourced work. Because such
contractual arrangements create legal & financial obligations it is
important to consider the method specified for evaluating
progress.
For long terms projects it may be appropriate to consider the
incorporating the time value of money & time discounted cash
flows into EVM. Inflation can be explicitly considered in EVM
and the inflation variance can be calculated. However these
considerations
add
complexity
to
the method and may be justifiable only for very long term
projects or in very high inflation periods or economics.
Limitations of EVM
While doing the earn value analysis, quality is not taken into
consideration. Cost of implementing Earned value management
causes managers not to use it extensively. Generally
software is required and coordination between different
departments
should
be
good
to
achieve
the goal. It is required to be carried out at different stages as the
uncertainty may occur any time throughout the project.
Primavera
The Primavera enables users to track and analyze performance.
It is a multiuser, multi-project system with scheduling and
resource control capabilities supporting multitier project
hierarchies, resource scheduling with a focus on roles and
skills, recording of actual data, customizable views, and
user-definable data. It supports an enterprise project structure
doi : 10.17950/ijer/v5i1/038
Page 166
International Journal of Engineering Research
Volume No.5, Issue Special 1 pp : 164-167
ISSN:2319-6890(online),2347-5013(print)
8 & 9 Jan 2016
Earned value performance reporting is intended to forewarn
management of potential cost and schedule problems so
that corrective action may be implemented before problems
become critical. A fast turn-around from project status review
to reporting the results will give management more time to
devise alternate plans. Utilization of the earned value technique
for project control will result in better assessment of activity
time and budget requirements. Management will be better
informed to distribute work load. Improved productivity can
result through constant feedback to management on cost and
schedule performance, thereby, providing the opportunity to
concentrate on problem areas. However, the earned value
technique by itself is not enough for good project control. It is a
systematic procedure for performance measurement which can
be effective only if it is supported by good cost and schedule
control systems.
(EPS) with an unlimited number of projects, activities, baselines,
resources, work breakdown structures (WBS), organizational
breakdown structures (OBS), user-defined codes, and criticalpath-method (CPM) scheduling and resource leveling.
Primavera also provides centralized resource management. This
includes resource timesheet approval and the ability to
communicate with project resources who use the Progress
Reporter. In addition, Primavera provides integrated risk
management, issue tracking and management by threshold. The
tracking feature enables users to perform dynamic cross project
rollups of cost, schedule, and earned value. Project work
products and documents can be assigned to activities and
managed centrally. The Report Wizard creates customized
reports that extract specific data from its database.
Methodology
The construction projects are so vast and complex in nature
therefore for simplification of work, use of software came
into existence Here primavera is used for example. The
WBS for the project is created several activities are
identified. The following recommended steps for the successful
implementation of earned value analysis 1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
Create Project
Define WBS
Create Calendars
Define Activities
Assign Durations to Activities
Assign Logic Links
Perform Scheduling
Assign Resources
Create Baseline
Update Schedule
Earn Value Analysis
Publishing Reports
References
i.
ii.
iii.
iv.
v.
vi.
vii.
viii.
ix.
x.
Agata Czarnigowska, “Earned value method as a tool for project control”,
Budownictwo i Architektura 3 (2008) 15-32.
Andrzej Czemplik, “Application of Earned Value Method to Progress
Control of Construction projects”, Procedia Engineering 91 (2014) 424 –
428.
Bryan Wilson, Thilini Ariyachandra, Mark Frolick, “Earned Value
Management Systems: Challenges and Future Direction”, Journal of
Integrated Enterprise Systems Vol.2 No.1, (2013) 9-17.
Clifford F. Gray, Erik W. Larson, Gautam V. Desai, “Project Management
The Managerial Process” Tata McGraw Hill Publications New Delhi
(2010).
Chitkara.K.K, “Construction Project Management: Planning, Scheduling
and Controlling”, Tata McGraw Hill Publications New Delhi (1998).
Frank T Anbari. “Earn Value Project Management method & Extensions”,
Project Management Journal (2003) Vol.34, No.4, 12-23.
Ivan Damnjanovic, James Rispoli, “Practice Periodical on Structural
Design and Construction”, Vol. 19, No. 1, (2014) 41–49.
Prasanna Chandra, “Projects – Planning, Analysis, Selection,
Implementation and Review”, Tata McGraw Hill Publications, New Delhi
(1998).
Ruskin A. M., Two issues concerning the use of Earned Value
Measurements, Engineering Management Journal, 2004: 16(3) s. 26-30.
Seetharaman.S. “Construction Engineering and management”, Umesh
Publications, New Delhi (2012).
Conclusion
NCICE@2016
doi : 10.17950/ijer/v5i1/038
Page 167