Proceedings of the 16th Int. AMME Conference, 27-29 May, 2014
Military Technical College
Kobry El-Kobbah,
Cairo, Egypt.
PT
26
16th International Conference
on Applied Mechanics and
Mechanical Engineering.
USING COMPUTER SIMULATION IN LEAN MANUFACTURING
IMPLEMENTATION
S. N. Seleem*, M. Helal** and A. M. Elassal ***
ABSTRACT
Lean manufacturing is a systematic approach to identify and eliminate wastes.
Adopting lean manufacturing concepts has become inevitable. It can lead to many
advantages including higher efficiency, better responsiveness and flexibility, shorter
lead times, and lower rework and defect rates. This ultimately reduces the
production costs, and is appropriate for current business environment where it is
required to produce a portfolio of products with suitable production capacity.
This paper describes the process of transforming an assembly line to work with lean
concepts. A methodology has been developed and used as a framework to utilize
various lean manufacturing tools in analyzing configuration and performance of the
assembly line and identifying the present forms of waste and their causes. Wastes
included high levels of work-in-process that led to high defect rates, frequent
inability to meet production targets within regular capacity, lack of flexibility and
expensive change over between models were identified. Simulation models of the
modified (lean) assembly lines were built and used as management decision
support tools to investigate further modifications to the lean system.
Converting the assembly line into a lean production system led to cutting off work-inprocess by about 82%, reducing cycle time by 30%, and decreasing model
changeover time from 127.5 min to 11.5 min, in addition, converting the lengthy
assembly line to two shorter and parallel assembly lines to produce two models
concurrently.
KEY WORDS
Lean Manufacturing, Value Stream Map, Assembly Line, TAKT time, Multi-Skilled
operator, Work in Process, Model changeover time, Simulation.
---------------------------------------------------------------------------------------------------------------*
**
***
Researcher for M sc. Degree, Department of Mechanical Engineering Technology, Benha
Faculty of Engineering, Benha University, Egypt. Email:
[email protected].
Associate Professor, Department of Mechanical Engineering Technology, Benha Faculty of
Engineering, Benha University, Egypt.
Professor, and Chairman of Mechanical Engineering Department, Benha Faculty of
Engineering, Benha University, Egypt.
Proceedings of the 16th Int. AMME Conference, 27-29 May, 2014
PT
27
INTRODUCTION
Lean is the way to specify value, line up value-creating actions in the best sequence,
conduct these activities without interruption, and perform them more and more
effectively, Womack and Jones [1]. Also In Bauch [2], Lean is lean since it provides a
way to do more and more with less and less, that is to say less human effort, less
equipment, less time and even less space while simultaneously producing products
that customer really wants. Ohlsson [3], Sahoo [4], Reza [5], and Stephen [6] were
utilized the previous lean manufacturing definition practically in different industrial
field with motivated results.
Principles for practical implementation of the lean manufacturing were described in
Womack and Jones [7] as outlined in the following sections:
• Specify Value
Value can only be defined by the ultimate customer and is only meaningful
when determined in terms of a specific product that meets the customer’s
needs at a specific price at a specific time. It is important for companies to
understand what customer particular needs are at a certain time and what
they are ready to pay for
• Identify the Value Stream
The next Lean principle is to identify the actual value stream, i.e. the whole
set of activities or services required to produce the specific product
• Flow
After specifying the value, mapping the value stream and eliminating no value
adding activities, the next principle in lean thinking consists of making the
value-creating activities flow. This is a very critical step as it requires a change
in thinking, away from the traditional batch production approach thinking in the
direction of the continuous flow thinking.
• Pull Approach
Lean thinking however is not only concerned with the question of how to
provide the exact goods and services the customer really wants, but also how
to provide it when the customer really wants it. The strategy behind that is the
pull principle, which means that you let the customer pull the product from
your company as needed instead of pushing products onto the customer and
so accumulating huge stocks of products that no one wants
• Striving for Perfection
The final principle is striving for perfection which is some kind of reminder that
there is no end in reducing effort, time, space, cost and mistakes while
simultaneously producing more and more products which the customer really
wants, Womack and Jones [1].
The elimination of waste is the goal of Lean philosophy. While the elimination of
waste may seem like a simple and clear subject it is noticeable that waste is often
very conservatively identified. According to Naval [8], Toyota defined three types of
waste:
• MURI (or overburden). It is focused on the preparation and planning of the
process, or what work can be avoided by design
• MURA (or unevenness).It focuses on implementation and the elimination of
fluctuations at the scheduling or operations level, such as quality and volume.
Proceedings of the 16th Int. AMME Conference, 27-29 May, 2014
•
PT
28
Mura is traditional general Japanese term for unevenness. Mura is avoided
through the Just-in-Time systems.
MUDA (or non-value-added work). It is discovered after the process is in
place and is dealt with reactively. The following Seven Wastes identify and
classify resources which are commonly wasted Hirano [9]:
1. Production ahead of demand (excess production)
2. Transportation: To move product that is not actually required to perform
the processing.
3. Waiting: Waiting for the next production step or for tools.
4. Inventory: All components, work-in-progress and finished product not
being processed.
5. Motion: People or equipment moving or walking more than is required to
perform the processing.
6. Over-Processing: Due to poor tool.
7. Defects: The effort involved in inspecting for and fixing defects.
Once the sources of the waste are identified it is easy to use the suitable lean tool to
reduce or eliminate them and make waste free systems. Lean tools, like Value
Stream Map, production smoothing, continuous improvement, 5S, single-minute die
exchange, total quality management, just-in-time, etc., have been conceived by
Toyota production system, Liker [10].
Implementing lean manufacturing principles will involve many changes to the current
manufacturing system to make the system lean. Because every company is different
and has different needs, the changes made to each company will be different to suit
their specific situation. Also creativity is a big part of implementing lean
manufacturing principles; people have to fine tune the ways lean principle are
implemented and this is done by trial and error most of the time, McClellan [11].Lean
principles can be implemented without simulation, but it will require a trial-and-error
period to make sure the changes were optimally implemented. The point of this
paper is not to use simulation to decide if lean principles should or should not be
implemented, but work to benefit from the capabilities of simulation to support lean
implementation. If simulation were used to help with lean implementation, the
optimum solutions to each lean principle could be implemented without it being
expensive, time consuming and disruptive. In today's competitive business
environment it is essential that everything is done as effective as possible and
simulation would help that happen.
CASE STUDY
A methodology has been designed to deal with the assembly line problems indicated
after waste assessment; the four legs of work methodology are:
Developing Value Stream Map (VSM) and assessing current assembly line status Preparing Multi-skilled operators – Using Industrial Engineering tools - Utilizing
Simulation.
Proceedings of the 16th Int. AMME Conference, 27-29 May, 2014
PT
29
Developing Value Stream Map, Assessing Current Assembly Line Status
A value stream map which visually presents all processes flow in the company as
shown in Figure 1 was constructed. Lean concepts can be implemented anywhere, it
depends on company needs or assessments which help in finding the gap between
lean and non-lean systems. The big problem at the current VSM is the delay of
achieving customers' demand. Usually customers need mix of models during
shipping process. Current line can't achieve this easily due to relatively long models
changeover time which equal 127.5 minutes, on average, because of that assembly
line produce only one model per day, so the researcher select assembly line number
one to increase its flexibility and reduce models changeover time, by applying Lean
manufacturing principles on it. YAMAZUMI chart as shown in Figure 2 illustrates
operations average cycle times and the TAKT time which equals 30 seconds, for the
selected product. Figure 2 shows that operations are not balanced with each other.
As a result of unbalanced operations cycle times, the assembly line is suffering from
two types of wastes:
• Waiting Time, equation (1) - Waldemar [12], was used to quantify the
unbalance between operations cycle time,
n
[(CT)longest - (CT) i ]
Unbalance Index =
i =1
(CT )longest.(n)
= 60%
(1)
Where:
•
•
•
(n) is the number of operations which equal 42,
(CT) longest, is operation number 5 which equal 40 seconds.
(CT)i is operation i cycle time, from i=1 to i=42
(See Figure 3, the 60% is indicated by the black column areas)
• Work in Process (WIP), which increases model change time, it was observed
that total WIP is equal 255 units per line, also model changeover is 127.5
minutes.
Preparing Multi-Skilled operators
It was observed that each operator can perform one operation only. Achieving
balance between operations cycle time requires rearranging those operations. And
this can't be achieved without improving each operator skills to be capable of
performing multi tasks. Training programs were designed and implemented by
manufacturing, quality, and human resource departments in four phases:
• Outside assembly line training, in a training room which is equipped with jigs,
fixtures, tools, and components used in real assembly line. Also charts and
printed work instructions that describe in details all operations within the
assembly line. Based on assessment done by manufacturing engineers after
this training phase, the researcher classifies operators into two groups, group
(A) and group (B). Group A - 24 operators, was selected to continue the
second training phase.
• Group (A) are splitted into two equally subgroups, subgroup (AI), and
subgroup (AII).Both subgroups operators are trained in training room again to
be multi-skilled. Manufacturing and engineering departments determined the
Proceedings of the 16th Int. AMME Conference, 27-29 May, 2014
PT
30
needed skills and set skills priority as shown in Table 1; a skill matrix was
constructed by the researcher based on assessment done by manufacturing
supervisors before starting training. Table 2 shows subgroup (AI) Skill Matrix
before implementing training program. An index was used to assess the total
skills of the subgroup. It is shown that subgroup (AI) total skills were 566;
also Table 3 shows subgroup (AII) total skills before implementing training
program.
• Off-Line Training, training done without running assembly line. Subgroup (AI)
and subgroup (AII) operators are positioned on real assembly line, line
conveyor was stopped. They perform assembly operations under supervisions
and coaching of manufacturing engineers and quality supervisors.
• On Job Training, training done while assembly line running with normal
speed. This, to finally evaluate operators of group (A) and make corrective
actions concurrently. The researcher construct after training skill matrix (Table
4 and 5), based on assessment done by manufacturing supervisors after
finalizing training program phases, total training duration is 85 days.
Skills and knowledge were improved by 114.5% for group (AI), and 97.2% for group
(AII) after applying the four phases of training program.
Using Industrial Engineering Tools
During the value stream four different types of activities were clearly appeared along
the value stream:
1. Value adding activities (VA): Assembling of a panel, assembling of printed
circuit boards (PCB), etc.
2. Necessary but not value adding activities (NNVA): Inspecting PCB to ensure
quality, cutting burrs, etc.
3. Unnecessary and not value adding activities (UNVA): Activities that can be
eliminated instantly.
4. Abnormal Activities: Activities which done due to bad understanding of real
customer needs or due to bad integration with suppliers.
The Activities in each operation were classified, and improvement plan was decided
as shown in Figure 4. YAMAZUMI chart after considering this classification was
constructed as shown in Figure 5. The following five steps were implemented to
achieve balancing between operations cycle time, and to reduce identified type of
wastes.
Eliminating abnormal and Unnecessary Value Added activities (UNVA)
Inspection Process which performed within operations 28, 30, and 31 were
considered as abnormal activities, because suppliers of liquid crystal panels perform
this test before panel shipping. That operation was eliminated directly after a
discussion with the engineering department manager. Also in operation number 42
there is an abnormal activity, which is fixing labels that add no value to customer.
This activity was eliminated. Table 6 shows the reduction in process cycle time due
to eliminating the abnormal activities. Actually 33 Seconds on average were
reduced from total cycle time by eliminating abnormal activities, which means
5%reduction in the total cycle time.
Proceedings of the 16th Int. AMME Conference, 27-29 May, 2014
PT
31
The Unnecessary non-value added activities, such as extra cleaning by operators
were observed as all operators clean the units and in particular the glossy front
cabinet. Of course all units should be clean, but why should all workers do cleaning!
It was suggested to use front cabinet with protection plastic film on its glossy
surface, and removes it just before packing the unit. Thus there becomes no need
for cleaning this glossy surface in all steps. This eliminated 109 seconds of the total
cycle time, which means 16.2% reduction in the total cycle time.
Reducing bottleneck NNVA activities
After eliminating both abnormal and unnecessary non value added activities,
operations 5 and 33 remained greater than the TAKT time (30 seconds). As shown
in Figure 6. Both operations 5 and 33 were considered as bottlenecks processes at
that time. Those activities cannot be eliminated directly. Efforts should be done to
reduce them, then identify their root causes and eliminate those root causes.
• In operation number 5, the operator has to cut burrs from front cabinet before
assembly. Those burrs come from bad injection mold surface that need to be
grinded in the die and mold repair workshop. Repairing the mold surface
eliminate burrs then no need to perform such activity.
• In operation number 33, remote control inspection cycle time was reduced by
using special fixture, which reduces excessive operator motion. Figure 7
shows the YAMAZUMI chart after reducing necessary non value added
activities in operations number 5 and 33.
Grouping processes, reducing Work-In-Process (WIP) inventory
After preparing multi-skilled operators, operations were combined together as shown
in Figure 8. Instead of 42 operators only 9 multi-skilled operators are required to
perform the same tasks. For example, operations from one to five are grouped and
performed by only one operator, (Figure 9), 12 activities which performed by 5
operators in 62.5 seconds now performed by one multi-skilled operator in the same
time, also operations from six to 11 are grouped and performed by one operator.
Operators now are capable to perform multiple operations. Figure 10 shows the new
operations cycle time after utilizing nine multi-skilled operators. As a result WIP
between operators was reduced, because there is no significant difference between
cycle times, so no relatively high WIP was piled up.
Increasing assembly line flexibility
The assembly line targeted cycle time after utilizing the nine multi-skilled
operators and grouping processes is 60 Seconds, as shown in Figure 10,
which is twice the original TAKT time. This did not meet customer demand
or production plans. As calculated at the beginning TAKT time must be 30
Seconds. To overcome that, the researcher suggested constructing two
short assembly lines instead of the current lengthy one. This led to changing
the layout of the working area from one long assembly line with cycle time =
30 seconds, to be two short assembly line with cycle time equal 60
Seconds/ line.
Proceedings of the 16th Int. AMME Conference, 27-29 May, 2014
PT
32
Instead of 42 operators on the lengthy assembly line only 18 operators in
two groups are needed to perform the same tasks, those 18 operators are
multi-skilled operators. The benefits achieved out of this are:
• Increasing the ability of producing two models at the same time
• Reducing WIP quantities
• Reducing setup time
• Reducing total usage area
Improving performance
Figure 10 shows that cycle times of operations number 1, 4, 7, and 8 are greater
than 60 seconds. Thus the NNVA activities had to be eliminated in those processes
to achieve daily planned production. The researcher observed that each operator
had to transport materials and components needed for assembly process every 90
minutes. It was suggested adding two additional operators; one of them for
supporting assembly processes operators, and the other for supporting testing and
packing operators. Both of them were for supporting transportation and arrange
parts and components during assembly and packing operations. The following list
indicates some performed tasks to be done by the two additional operators:
1. Removing front cabinet from cartons and arranging them on table
2. Removing speakers from cartons and arranging them on carriage
3. Removing PCB from cartons and arranging them on table
4. Preparing Cables and arranging them in order on table
5. Assembly power cable, signal cable, and USB to TV before testing
6. Maintaining, checking, and self-calibration of test equipment's.
The Spagitti diagram in Figure 11 explains the motion done by the additional
operator to prepare components, release them from packing carton, and supply line
operators regularly by needed components. With the two additional operators, the
line operators did not waste their time in handling and bringing components any
more. By assigning the additional operators the total cycle time of each assembly
process was reduced. The additional two operators who handle and arrange parts
and components to be ready for assembly directly by multi-skilled operators actually
reduced total cycle time for all nine processes. Total reduction in Necessary-Non
value added activities was 46 seconds, Figure 12 shows processes cycle time after
introducing additional two operators.
However, it was observed that when one of a multi-skilled operator is absent,
troubles occur and the cycle time exceeds the 60seconds in addition to more
defects. The researcher suggested training the two additional operators on the
assembly operations to be multi-skilled operators also. Refresher training programs
were implemented, and the two additional operators for handling and arranging parts
or components became qualified to make up for any of the nine basic operators after
this training. Normally the additional operators perform all supervisions tasks and
write all needed reports related to production quantity, produced models, and quality.
The new level of unbalance is shown in Figure 13. The maximum operation cycle
time, (CT) longest, is 58 seconds for operation number 7. By adding up the
differences between (CT) longest and each operation cycle time (CT) i, the
unbalance index value calculated as following:
Proceedings of the 16th Int. AMME Conference, 27-29 May, 2014
Unbalance Index =
n
[(CT)Longest - (CT) i ]
PT
33
= 10.3%
i =1
((CT ) Longest ).(n)
Where: n is the number of operations which equal 9
The 10.3% are indicated by the black columns areas in Figure 13 below.
Utilizing Simulation
Simulation was used to handle the uncertainty and dynamic factors that could not be
captured using the VSM, Detty and Yingling [13]. Also it was used to establish
specific parameters of a lean manufacturing system (i.e. the number of kanban,
container size, batch size, and mixed-model sequencing approaches).
Why using simulation
It was observed that modified assembly line throughput is often below target. The
researcher collected data on daily throughput and the average short line output was
428 units, with standard deviation of 2 units. Given that the planned production rate
was 450 units. Throughput problem resulted from variation in operations cycle times.
In YAMAZUMI chart one draws the average cycle time but variation is not
considered. Thus a new YAMAZUMI chart (Figure 14) was prepared to present
variation in each operation cycle time, this variation in each operation was not
considered before, as shown in Figure 14, maximum value of cycle time in most
operations are greater than line targeted cycle time. This is the reason of daily
production shortage. The objective of using simulation in this paper is to consider
variation in operations cycle time while quantifying and estimating results of new
improved proposal.
Modeling of current assembly line
Operations within assembly and testing area were simulated. 40 readings were
collected in stable and normal conditions of performance; data was fitted in Arena
input analyzer, triangular distribution was used. Figure 15 shows the result of
operation number one distribution. The researcher accepted that triangular
distribution is accurately describes operations cycle time distribution, as
corresponding P-value is greater than 0.05 for obtained triangular distributions for all
operations, Table 7 describes triangular distribution parameters in seconds for all
current processes. Based on actual processes cycle time distribution shown in Table
7, the researcher constructed Arena model presented in Figure 16, with the following
assumptions:
• Working hours per day = 7.5 hours
• Assembly line failure rate = zero, "where actual assembly line failure rate =
0.00152”.
Model validation
The following methodology was implemented after constructing the model which
Proceedings of the 16th Int. AMME Conference, 27-29 May, 2014
PT
34
simulate current assembly line, to decide if this model valid or not before starting
modifying it.
• Collecting 30 reading and finding the average assembly line throughput and
the average work in process within it.
• Running the constructed model 35 replications and finding the predicted
assembly line throughput and the predicted work in process
• Performing 2-sample t-test to test if there are significant change between
actual collected throughput or WIP comparing with predicted values outcomes
after running the model
• If there is no significant change, it can be concluded that the developed model
is valid, and simulates current assembly line.
The model shown in Figure 16 was run for 35 replications, and the results for level of
output were compared to the output of actual system. Figure 17 "2-sample t test
results" indicates that the model is valid, and can be used to experiment with the
system. Since the P-value is greater than 0.05, there is no evidence for a difference
between simulation model output and actual line output. Figure 17 "2-sample t test
results" showed that there is no significant change between actual collected data for
current assembly line output and the output obtained from Arena model which
simulates current assembly line. The results for level of WIP also compared to the
actual system as shown in Figure 18, the comparison indicates that the model is
valid, and can be used to experiment the system.
First proposal for optimizing current assembly line
Each operation was splitted into small components. The researcher then suggested
adding two others operators one of them in assembly area and the other in the final
testing and packing area, Figure 19 shows the location of additional two operators.
Figure 20 presents the 11 operators cycle time, after rearranging activities. Figure 21
presents common variation in operations cycle time, after adding two operators, also
Table 8 shows the triangular distribution of operations cycle time. The researcher
modified the valid Arena model to simulate his new suggestion. After running
modified model the following results were obtained:
• WIP = 10±2 Units
• Line Output = 515±2 Units/day
However, the simulation results in previous model show that operator's utilizations
will be as shown in Figure 22.
As can be seen operators number 1, 2, 3, and 5 will be extremely utilized during the
working hours. Estimated utilizations can be more than 90%. Although it is estimated
that the researcher suggestion can increase the daily production rate, it is not
recommended to accept it, as utilizations of some operators can be more than 90%.
Second proposal for improving assembly line performance
In order to reduce utilizations of assembly operators the researcher suggested
adding another operator in the assembly area, before furnace, and rearranged
activities between operators in previous model, to allocate job for the additional
operator as shown in Figure 23. Variation in operations cycle time is considered as
shown in Figure 24 and triangular distribution is used to present operations cycle
Proceedings of the 16th Int. AMME Conference, 27-29 May, 2014
PT
35
time distribution (see Table 9). The following Arena model (Figure 25) is constructed
to simulate the effect of introducing seven operators in assembly area instead of six
operators. After running model shown in Figure 25, (35-Replications), the new
estimate for utilization of operators, if 515 units were produced per day is shown in
Figure 26. Maximum estimated utilization is 87%, which is below 90%. The previous
steps indicate the benefits of using simulation to investigate current problem causes
and to examine any proposed suggestions before implementation. This leads to
saving cost as a result of reducing number of trails.
CONCLUSION
A methodology to implement lean concepts in legacy assembly lines, have been
developed that is based on:
• Using the VSM to capture the current system status and identify the
opportunities for improvements
• Using the traditional IE tools of job and method design, time study, and
assembly line balancing, in addition to the other lean manufacturing tools
• Directing the use of simulation modeling to where other lean and IE tools are
not feasible
• Developing tailored periodic training programs on using the manufacturing
lean tools and to develop multi-skilled operators
A successful implementation of the lean manufacturing concepts has been
accomplished by which an assembly line in a leading Egyptian manufacturing firm
has been converted into a lean system with remarkably improved performance and
productivity. The Firm’s management had a strategic plan of increasing production
rate by 2014 and the directions in considerations were building a new assembly line
or increasing the current workforce. Both options were not feasible on time due to
lack of investments as well as lack of available floor space. The line is still suffers of
major forms of waste due to high levels of WIP, long model changeover times, and
unbalanced loadings.
As a lean production system, the lengthy assembly line was converted to two typical
assembly lines with the same capacity of the original line but without its associated
problems and using about half of the workforce. Converting the assembly line into a
lean production system led to:
•
•
•
•
•
•
•
Cutting WIP by about 82%; from 510,000 LE to 90,000 LE
Cutting the cycle time by about 30% (from 6.72 min to 4.68 min)
Cutting model changeover time by about 91%; from 127.5 min to 11.5 min.
Producing two different models concurrently.
Cutting the unbalance level by about 83%; from 60% to about 10.3%
Cutting the number of operators on the assembly line by 52%, from 42 to 20.
Remaining workers were assigned to the other assembly lines that led to
enhancing their production rate and eliminating the need for overtime on them
Cutting the opportunities for defects from 30,000 PPM to 1,100 PPM for the
TV panel; 23,000 PPM to 18,500 PPM for the PCB; and from 45,000 PPM to
zero for the plastic front cabinet
Simulation models have been built for the modified assembly line to account for the
variation in performance that could not be accounted for using the other Industrial
Proceedings of the 16th Int. AMME Conference, 27-29 May, 2014
PT
36
Engineering and lean tools. The simulation models offered efficient management
decision support tool for the analysis of the system response to suggested changes
in task designs and worker assignments. Although proven an effective manufacturing
system analysis tool, simulation is expensive and time consuming to build, which
supports our dissertation that simulations should be used for systems that have the
lean tools applied in order to experiment for further improvement. The common lean
manufacturing tools are relatively easy to learn by workers while simulation requires
highly skilled experts to develop and use. It can be stated that using simulation in
lean manufacturing is most suitable for studying the system after having applied the
other common lean manufacturing tools. The use of simulation model revealed the
potential of planning further increase in productivity for the targeted 480 units per
hour to 550 units per hour and virtually no new investments.
REFERENCES
[1]
[2]
[3]
[4]
[5]
[6]
[7]
[8]
[9]
[10]
[11]
[12]
[13]
Womack, J. and Jones, D. and Roos, D. "The machine that changed the
world", MacMillan Publishing company, pp. 4-7, (1990).
Bauch, C. “Lean Product Development making Waste Transparent”, Master's
thesis, University of Munich, pp. 10-21, (2004).
Ohlsson, F. “Lean manufacturing at Volvo Truck production Australia”,
Master's thesis, Lund institute of Technology, pp. 4-20, (2005).
Sahoo A.K., Singh N.K., Shankar R. and Tiwari M.K., "Lean philosophy:
implementation in a forging company", International Journal of Lean Thinking
Volume 2, Issue 1, (2011).
Reza, M. “The Relationship between Lean and TPM”, Master's thesis,
University of Boras, pp. 3-9, (2009).
Stephen, P. “Application of DMAIC to integrate Lean manufacturing and six
sigma”, Master's thesis, Blacksburg, Virginia, pp. 2-11, (2004).
Womack, J. and Jones. D. “Lean Thinking: Banish Waste and create wealth
in your corporation”, Free Press, pp. 8 – 97, (2000).
Naval, P. "Process Improvements in a material handling activity by applying
lean production techniques", Master's thesis, University of Catalunya, pp.537, (2008).
Hirano, H. "JIT Implementation manual: the complete guide to Just in time
manufacturing: 2nd edition Volume 2, WASTE and 5S's", CRC Press, pp151179, (2009).
Liker, J. "Toyota Way", USA: McGraw-Hill Professional Publishing, pp. 2833, (2003).
McClellan, J. "The Benefit of Using simulation to improve the implementation
of lean manufacturing case study: Quick changeovers to allow level loading
of the assembly line", Master's thesis, Brigham Young University, (2004).
Waldemar, G. "Assembly Line – Theory and Practice", Published by INTEC,
pp. 4-12, (2011).
Detty, R. and Yingling, J. "Quantifying Benefits of conversion to lean
manufacturing with discrete event simulation: A case study, International
Journal of production research, (2000).
Proceedings of the 16th Int. AMME Conference, 27-29 May, 2014
LIST OF TABLES
Table
: Assembly Skills Priority.
Table : Group A (I) - Before Training Skill Matrix.
PT
37
Proceedings of the 16th Int. AMME Conference, 27-29 May, 2014
Table
: Group A (II) - Before Training Skill Matrix.
Table
: Group A (I) - After Training Skill Matrix.
Table
: Group A (II) - After Training Skill Matrix.
PT
38
Proceedings of the 16th Int. AMME Conference, 27-29 May, 2014
Table
PT
: Reduction in Operation Cycle Times after Eliminating Abnormal Activities.
Table
: Triangular Distribution Parameters of Current Operations.
Table
Table
: Triangular Distribution Parameters of First Proposal.
: Triangular Distribution Parameters of Second Proposal.
39
Proceedings of the 16th Int. AMME Conference, 27-29 May, 2014
LIST OF FIGURES
Model Changeover time is equal 127.5 minutes
Fig. : Current Value Stream Map.
Fig. : YAMAZUMI Chart.
PT
40
Proceedings of the 16th Int. AMME Conference, 27-29 May, 2014
Fig. : Quantifying of Unbalanced Operations.
Fig. : Work Activities Classification.
PT
41
Proceedings of the 16th Int. AMME Conference, 27-29 May, 2014
Fig. : Yamazumi Chart after Work Activities Classification.
Fig. : Yamazumi Chart after Eliminating Abnormal and UNVA Activities.
PT
42
Proceedings of the 16th Int. AMME Conference, 27-29 May, 2014
Fig. : Yamazumi Chart after Bottleneck NNVA Activities.
TAKT Time = 30:00 Second
Fig. : Grouping Operations.
PT
43
Proceedings of the 16th Int. AMME Conference, 27-29 May, 2014
Fig. : Grouping of Activities Example.
Assembly Line Targeted Cycle Time
= 60:00 Second
Fig. 0: After Grouping Operations.
4
Fig.
: Spagitti diagram explains motion to handle materials.
PT
44
Proceedings of the 16th Int. AMME Conference, 27-29 May, 2014
Fig.
: Yamazumi Chart after Introducing Handling Material Operator.
Fig.
Fig.
: New Level of Unbalance in Line 1.
: Yamazumi Chart after Considering of Cycle Time Variation.
PT
45
Proceedings of the 16th Int. AMME Conference, 27-29 May, 2014
Fig.
Fig.
: Triangular Distribution of Operation 1.
: Arena Model which Describe Assembly line.
PT
46
Proceedings of the 16th Int. AMME Conference, 27-29 May, 2014
Fig.
: two-Sample t Test of Level of Output.
Fig.
: two-Sample t Test of WIP.
PT
47
Proceedings of the 16th Int. AMME Conference, 27-29 May, 2014
Fig.
: Location of Additional Operators.
Fig. 0: Yamazumi Chart of 11-Operators.
Fig.
: Yamazumi Chart Considering Variations.
PT
48
Proceedings of the 16th Int. AMME Conference, 27-29 May, 2014
Fig.
: The Second Proposal - Seven Operators in Assembly Area.
Fig.
: Operators Utilization in first Proposal.
PT
49
Proceedings of the 16th Int. AMME Conference, 27-29 May, 2014
Fig.
Fig.
Fig.
: The Second Proposal Cycle Time.
: The Second Proposal Arena Model.
: Operators Utilization in the Second Proposal.
PT
50