Q & As for the PMBOK® Guide Sixth Edition
4.5/5
()
Project Management
Knowledge Areas
Risk Management
Quality Management
Resource Management
Stakeholder Management
Cost Management
Organizational Process Assets
Schedule Management
Project Risk Management
About this ebook
Read more from Project Management Institute Project Management Institute
A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Seventh Edition and The Standard for Project Management (ENGLISH) Rating: 5 out of 5 stars5/5Agile Practice Guide Rating: 4 out of 5 stars4/5Managing Change in Organizations: A Practice Guide Rating: 5 out of 5 stars5/5Citizen Development: The Handbook for Creators and Change Makers Rating: 4 out of 5 stars4/5The PMI Guide to Business Analysis Rating: 4 out of 5 stars4/5Practice Standard for Work Breakdown Structures - Third Edition Rating: 4 out of 5 stars4/5The Standard for Portfolio Management Rating: 4 out of 5 stars4/5Implementing Organizational Project Management: A Practice Guide Rating: 5 out of 5 stars5/5Practice Standard for Scheduling - Third Edition Rating: 5 out of 5 stars5/5Project Manager Competency Development Framework – Third Edition Rating: 5 out of 5 stars5/5Governance of Portfolios, Programs, and Projects: A Practice Guide Rating: 5 out of 5 stars5/5The Standard for Earned Value Management Rating: 5 out of 5 stars5/5Requirements Management: A Practice Guide Rating: 4 out of 5 stars4/5Building Resilient Organizations: Best practices, tools and insights to thrive in ever-changing contexts Rating: 0 out of 5 stars0 ratingsGetting It Done: Project Management in Action Rating: 0 out of 5 stars0 ratingsThe Standard for Organizational Project Management (OPM) Rating: 5 out of 5 stars5/5Benefits Realization Management: A Practice Guide Rating: 5 out of 5 stars5/5Practice Standard for Project Estimating - Second Edition Rating: 5 out of 5 stars5/5Practice Standard for Project Configuration Management Rating: 0 out of 5 stars0 ratingsSoftware Extension to the PMBOK® Guide Fifth Edition Rating: 5 out of 5 stars5/5Navigating Complexity: A Practice Guide Rating: 0 out of 5 stars0 ratingsProject Management Casebook Rating: 4 out of 5 stars4/5Project Management Casebook: Instructor's Manual Rating: 0 out of 5 stars0 ratingsGovernment Extension to the PMBOK® Guide Third Edition Rating: 5 out of 5 stars5/5
Related to Q & As for the PMBOK® Guide Sixth Edition
Related ebooks
The PMP Notebook, 3rd Edition Rating: 5 out of 5 stars5/5Project Management Casebook Rating: 4 out of 5 stars4/5Governance of Portfolios, Programs, and Projects: A Practice Guide Rating: 5 out of 5 stars5/5Project Manager Competency Development Framework – Third Edition Rating: 5 out of 5 stars5/5PMP® Simplified Knowledge Areas: Artifacts and activities of the knowledge areas Rating: 0 out of 5 stars0 ratingsProject Planning and Scheduling Rating: 5 out of 5 stars5/5Learn PMP in 24 Hours Rating: 0 out of 5 stars0 ratingsThe New One-Page Project Manager: Communicate and Manage Any Project With A Single Sheet of Paper Rating: 3 out of 5 stars3/5The Fast Forward MBA in Project Management Rating: 4 out of 5 stars4/5Government Extension to the PMBOK® Guide Third Edition Rating: 5 out of 5 stars5/5Project Risk Management: A Practical Implementation Approach Rating: 4 out of 5 stars4/5PgMP® Study: Two Complete Exams Rating: 5 out of 5 stars5/5Project Management Fundamentals: Key Concepts and Methodology Rating: 5 out of 5 stars5/5Managing Projects With PMBOK 7: Connecting New Principles With Old Standards Rating: 5 out of 5 stars5/5Implementing Project Portfolio Management Rating: 5 out of 5 stars5/5Project Management For Dummies Rating: 4 out of 5 stars4/5Project Management for Small Projects, Third Edition Rating: 4 out of 5 stars4/5Fundamentals of Project Management, Sixth Edition Rating: 0 out of 5 stars0 ratingsProject Management Rating: 4 out of 5 stars4/5The Project Management Answer Book Rating: 3 out of 5 stars3/5Improving Your Project Management Skills Rating: 0 out of 5 stars0 ratingsCAPM Success Path : MCQs and Explanations for Prep Excellence Rating: 0 out of 5 stars0 ratingsEazy Pmp Rating: 0 out of 5 stars0 ratingsThe Project Management Tool Kit: 100 Tips and Techniques for Getting the Job Done Right Rating: 0 out of 5 stars0 ratingsPMP Project Management Professional Exam Study Guide: 2021 Exam Update Rating: 4 out of 5 stars4/5Project Management for Small Projects Rating: 0 out of 5 stars0 ratingsProject Estimating and Cost Management Rating: 5 out of 5 stars5/5
Management For You
The Hard Thing About Hard Things: Building a Business When There Are No Easy Answers Rating: 4 out of 5 stars4/5Never Split the Difference: Negotiating As If Your Life Depended On It Rating: 4 out of 5 stars4/5The Coaching Habit: Say Less, Ask More & Change the Way You Lead Forever Rating: 4 out of 5 stars4/5The 12 Week Year: Get More Done in 12 Weeks than Others Do in 12 Months Rating: 4 out of 5 stars4/5Peak: Secrets from the New Science of Expertise Rating: 4 out of 5 stars4/5Focus: The Hidden Driver of Excellence Rating: 4 out of 5 stars4/5Stillness is the Key: An Ancient Strategy for Modern Life Rating: 4 out of 5 stars4/5Principles: Life and Work Rating: 4 out of 5 stars4/5The 7 Habits of Highly Effective People: 30th Anniversary Edition Rating: 5 out of 5 stars5/5The Unfair Advantage: BUSINESS BOOK OF THE YEAR AWARD-WINNER: How You Already Have What It Takes to Succeed Rating: 5 out of 5 stars5/5Managing Oneself Rating: 4 out of 5 stars4/5Company Rules: Or Everything I Know About Business I Learned from the CIA Rating: 4 out of 5 stars4/5Difficult Conversations (HBR 20-Minute Manager Series) Rating: 4 out of 5 stars4/5Everybody Lies: Big Data, New Data, and What the Internet Can Tell Us About Who We Really Are Rating: 4 out of 5 stars4/5How to Be Everything: A Guide for Those Who (Still) Don't Know What They Want to Be When They Grow Up Rating: 4 out of 5 stars4/5Rewired: The McKinsey Guide to Outcompeting in the Age of Digital and AI Rating: 5 out of 5 stars5/5Crucial Conversations: Tools for Talking When Stakes are High, Third Edition Rating: 4 out of 5 stars4/5Strategy Skills: Techniques to Sharpen the Mind of the Strategist Rating: 4 out of 5 stars4/5What They Don't Teach You At Harvard Business School Rating: 5 out of 5 stars5/5Good to Great: Why Some Companies Make the Leap...And Others Don't Rating: 4 out of 5 stars4/5Summary of The Laws of Human Nature: by Robert Greene - A Comprehensive Summary Rating: 5 out of 5 stars5/5Out of Our Minds: Learning to be Creative Rating: 4 out of 5 stars4/5The Get Things Done Book: 41 Tools to Start, Stick With and Finish Things Rating: 3 out of 5 stars3/5MBA Notes: Course Notes from a Top MBA Program Rating: 5 out of 5 stars5/5Catalyst Rating: 4 out of 5 stars4/5Multipliers, Revised and Updated: How the Best Leaders Make Everyone Smarter Rating: 4 out of 5 stars4/5Crossing the Chasm, 3rd Edition: Marketing and Selling Disruptive Products to Mainstream Customers Rating: 5 out of 5 stars5/5
Reviews for Q & As for the PMBOK® Guide Sixth Edition
18 ratings3 reviews
What our readers think
Readers find this title to be a good book for preparing for the PMP exam. It is updated to the latest version of PMBok Guide 6th Ed and is highly recommended. The book is very comprehensive, although there are a few minor glitches in the answer options and question numbering at the end in the answer sheet.
- Rating: 3 out of 5 stars3/5good book to prepare for pmp exam and for practice
- Rating: 5 out of 5 stars5/5Very comprehensive. However there are a few minor glitches in answer options & question numbering at the end in the answer sheet.
1 person found this helpful
- Rating: 5 out of 5 stars5/5This is updated to the latest version of PMBok Guide 6th Ed and very good prep book for PMP and highly recommended.
1 person found this helpful
Book preview
Q & As for the PMBOK® Guide Sixth Edition - Project Management Institute Project Management Institute
Q & As
FOR THE
PMBOK®
GUIDE
SIXTH EDITION
Contributors:
Ray Alton, PMP
Frank T. Anbari, PhD, PMP
Nicholas Holdcraft, PMI-ACP, PMP, PgMP, PfMP
Jack Hseih, PMI-PBA, PMP, PgMP, PfMP
Anthony Johnson, PMP, PgMP, PfMP
Te Wu, PMP, PgMP, PfMP
Russel Souza, MBA, PMP
Library of Congress Cataloging-in-Publication Data has been applied for.
Q & As for the PMBOK® Guide Sixth Edition
ISBN: 978-1-62825-461-7
©2017 Project Management Institute, Inc. All rights reserved.
Our copyright content is protected by U.S. intellectual property law that is recognized by most countries. To republish or reproduce our content, you must obtain our permission. Please go to http://www.PMI.org/ permissions for details.
PMI, the PMI logo, PMBOK, OPM3, PMP, CAPM, PgMP, PfMP, PMI-RMP, PMI-SP, PMI-ACP, PMI-PBA, PROJECT MANAGEMENT JOURNAL, PM NETWORK, PMI TODAY, PULSE OF THE PROFESSION and the slogan MAKING PROJECT MANAGEMENT INDISPENSABLE FOR BUSINESS RESULTS. are all marks of Project Management Institute, Inc. For a comprehensive list of PMI trademarks, contact the PMI Legal Department. All other trademarks, service marks, trade names, trade dress, product names and logos appearing herein are the property of their respective owners. Any rights not expressly granted herein are reserved.
To inquire about discounts for resale or educational purposes, please contact the PMI Book Service Center.
PMI Book Service Center
P.O. Box 932683, Atlanta, GA 31193-2683 USA
Phone: + 1 866 276 4764 (within the U.S. or Canada) or
+ 1 770 280 4129 (globally)
Fax: + 1 770 280 4113
Email: [email protected]
Printed in the United States of America. No part of this work may be reproduced or transmitted in any form or by any means, electronic, manual, photocopying, recording, or by any information storage and retrieval system, without prior written permission of the publisher.
The paper used in this book complies with the Permanent Paper Standard issued by the National Information Standards Organization (Z39.48—1984).
10 9 8 7 6 5 4 3 2 1
Table of Contents
PREFACE
QUESTIONS
Section 1: Introduction
Section 2: The Environment in Which Projects Operate
Section 3: The Role of the Project Manager
Section 4: Project Integration Management
Section 5: Project Scope Management
Section 6: Project Schedule Management
Section 7: Project Cost Management
Section 8: Project Quality Management
Section 9: Project Resource Management
Section 10: Project Communications Management
Section 11: Project Risk Management
Section 12: Project Procurement Management
Section 13: Project Stakeholder Management
Appendix X3
Agile, Iterative, Adaptive, and Hybrid Project Environments
Appendix X4
Summary of Key Concepts for Knowledge Areas
Appendix X5
Summary of Tailoring Considerations for Knowledge Areas
Glossary
ANSWERS
Section 1: Introduction
Section 2: The Environment in Which Projects Operate
Section 3: The Role of the Project Manager
Section 4: Project Integration Management
Section 5: Project Scope Management
Section 6: Project Schedule Management
Section 7: Project Cost Management
Section 8: Project Quality Management
Section 9: Project Resource Management
Section 10: Project Communications Management
Section 11: Project Risk Management
Section 12: Project Procurement Management
Section 13: Project Stakeholder Management
Appendix X3
Agile, Iterative, Adaptive, and Hybrid Project Environments
Appendix X4
Summary of Key Concepts for Knowledge Areas
Appendix X5
Summary of Tailoring Considerations for Knowledge Areas
Glossary
Preface
In the rapidly growing, fast-changing, and highly competitive world of project management, more and more professionals are recognizing the importance of developing a deeper understanding of the generally accepted knowledge and practice of the project management profession. Q & As for the PMBOK® Guide Sixth Edition facilitates this goal by offering multiple-choice questions and answers that cover key themes and concepts of project management. This helpful book addresses the project management Knowledge Areas and processes of A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Sixth Edition, the Project Management Institute's (PMI) global standard and body of knowledge. Answers are provided in the back of the book and include references and excerpted text from the PMBOK® Guide – Sixth Edition to enhance the reader's breadth and depth of knowledge. The handy, pocket-size Q & As for the PMBOK® Guide Sixth Edition makes it convenient to refer to the information in The Guide anytime, anywhere.
Q & As
FOR THE
PMBOK® GUIDE
SIXTH EDITION
Questions
Introduction
(Section 1 of the PMBOK® Guide)
1.A project is:
A.A set of sequential activities performed in a process or system.
B.A revenue-generating activity that needs to be accomplished while achieving customer satisfaction.
C.An ongoing endeavor undertaken to meet customer or market requirements.
D.A temporary endeavor undertaken to create a unique product, service, or result.
2.Project management is:
A.The integration of the critical path method and the Earned Value Management system.
B.The application of knowledge, skills, tools, and techniques to project activities to meet the project requirements.
C.The application of knowledge, skills, wisdom, science, and art to organizational activities to achieve operational excellence.
D.A subset of most engineering and other technical disciplines.
3.Portfolio management refers to:
A.Managing various contents of the project file.
B.Managing the levels of financial authority to facilitate project decision making.
C.The centralized management of one or more portfolios to achieve strategic objectives.
D.Applying resource-leveling heuristics across all the organization's projects to achieve the organization's strategic objectives.
4.All of the following are questions that the key stakeholders and project managers should answer to develop the project success measures EXCEPT:
A.What does success look like for the project?
B.How will success be measured?
C.What are the communication requirements?
D.What factors may impact success?
5.A program is a:
A.Group of related tasks lasting one year or less.
B.Group of related projects, subsidiary programs, and program activities managed in a coordinated manner.
C.Large projects with significant cost and resource requirements.
DSequence of activities constituting a major project.
6.All of the following are true about projects and operations EXCEPT:
A.Operations are ongoing endeavors that produce repetitive outputs, with resources assigned to do basically the same set of tasks according to the standards institutionalized in a product life cycle, whereas projects are temporary endeavors.
B.Projects require project management activities and skill sets, whereas operations require business process management, operations management activities, and skill sets.
C.Projects can intersect with operations at various points during the product life cycle. At each point, deliverables and knowledge are transferred between the project and operations for implementation of the delivered work.
D.Because of their temporary nature, projects cannot help achieve an organization's long-term goals. Therefore, strategic activities in the organization can be generally addressed within the organization's normal operations.
7.Your job responsibility is to align components (projects, programs, or related operations) to the organizational strategy, organized into portfolios or subsidiary portfolios to optimize project or program objectives, dependencies, costs, timelines, benefits, resources, and risks. This is known as:
A.Components management.
B.Process management.
C.Program management.
D.Portfolio management.
8.The PMBOK® Guide is the standard for:
A.Managing all projects all of the time.
B.Managing all projects most of the time.
C.Managing most projects most of the time.
D.Managing some projects some of the time.
9.The collection of generally sequential and sometimes overlapping project phases, whose name and number are determined by the management and control needs of the organization or organizations involved in the project, is known as the:
A.Project waterfall.
B.Project life cycle.
C.Project life stages.
D.Project Management Process Groups.
10.All of the following are true about project phases and the project life cycle EXCEPT:
A.Stakeholder influences, risk, and uncertainty are greatest at the start of the project. These factors decrease over the life of the project.
B.The ability to influence the final characteristics of the project's product, without significantly impacting cost, is highest at the start of the project and decreases as the project progresses toward completion.
C.The cost of changes and correcting errors typically increases substantially as the project approaches completion.
D.Cost and staffing levels are generally steady throughout the project life cycle.
11.All of the following statements about the project life cycle and the product life cycle are true EXCEPT:
A.In the project predictive life cycle, the project scope and the time and cost required to deliver that scope are determined as early in the project life cycle as practically possible.
B.In the project iterative and incremental life cycles, project phases intentionally repeat one or more project activities as the project team's understanding of the product increases.
C.The product life cycle is the series of phases that represent the evolution of a product, from concept through delivery, growth, maturity, and to retirement.
D.The product life cycle is contained within the predictive project life cycle.
12.You are managing a project in which you intend to respond to high levels of change and ongoing stakeholder involvement. The most suitable project life cycle for your project is the:
A.Predictive life cycle.
B.Adaptive life cycle.
C.Waterfall life cycle.
D.Configuration management life cycle.
13.The five Project Management Process Groups are:
A.Planning, Checking, Directing, Monitoring, and Recording.
B.Initiating, Planning, Executing, Monitoring and Controlling, and Closing.
C.Planning, Executing, Directing, Closing, and Commissioning.
D.Initiating, Executing, Monitoring, Evaluating, and Closing.
14.Project Management Processes:
A.May be overlapping activities that occur throughout the project.
B.May be overlapping activities that generally occur at the same level of intensity within each phase of the project.
C.Are generally discrete, one-time events.
D.Are discrete, repetitive events that occur generally at the same level of intensity throughout each phase of the project.
15.The linkages between project management processes are best described by the following:
A.The work breakdown structure links processes.
B.Processes are linked by their planned objectives—the summary objective of one often becomes the detailed action plan for another within the project, subproject, or project phase.
C.Processes are linked by the outputs that are produced—the output of one process generally becomes an input to another process or is a deliverable of the project, subproject, or project phase.
D.There are no significant links between discrete processes.
16.For a project to be successful, the project should generally achieve all of the following EXCEPT:
A.Achieving stakeholder satisfaction.
B.Striving to obtain acceptable customer/end-user adoption.
C.Appling knowledge, skills, and processes within the Project Management Process Groups uniformly to meet the project objectives.
D.Fulfilling other agreed-upon success measures or criteria.
17.The project business case is all of the following EXCEPT:
A.Documented economic feasibility study used to establish the validity of the benefits of a selected component lacking sufficient definition and that is used as a basis for the authorization of further project management activities.
B.A document that lists the objectives and reasons for project initiation.
C.A document that serves as an important input to the project initiation and is seldom used after the project is approved.
D.An important document that may result in a go/no-go decision for the project.
18.The key elements of the benefits management plan are all of the following EXCEPT:
A.Work Breakdown Structure.
B.Benefits owner.
C.Assumptions.
D.Strategic alignment.
19.A significant amount of data is collected and analyzed throughout the project. All of the following are examples of project data and information EXCEPT:
A.Work performance data.
B.Work performance analysis.
C.Work performance information.
D.Work performance reports.
20.Project tailoring is an important consideration for most projects. Which of the following is the least likely project consideration?
A.Project manager's skills and competency.
B.Each project is unique.
C.Addressing competing constraints.
D.Level of project governance varies.
The Environment in Which Projects Operate
(Section 2 of the PMBOK® Guide)
21.Enterprise environmental factors refer to both internal and external environmental factors that surround or influence a project's success. All of the following are true about these factors EXCEPT:
A.Enterprise environmental factors include organizational culture, structure, and processes.
B.Enterprise environmental factors include government or industry standards, such as regulatory agency regulations, codes of conduct, product standards, quality standards, and workmanship standards.
C.Enterprise environmental factors include information technology software (e.g., an automated tool, such as a scheduling software tool, a configuration management system, an information collection and distribution system, or web interfaces to other online automated systems).
D.Enterprise environmental factors exclude personnel administration functions (e.g., staffing and retention guidelines, employee performance reviews and training records, and time tracking) because these are considered to be functions of the human resources department.
22.The types of project management office (PMO) structures in organizations include all of the following EXCEPT:
A.Supportive PMOs that provide a consultative role to projects by supplying templates, best practices, training, access to information, and lessons learned from other projects.
B.Controlling PMOs that provide support and require compliance through various means.
C.Harmonizing PMOs that strive to reduce conflict and improve harmony among project team members.
D.Directive PMOs that take control of the projects by directly managing the projects.
23.A primary function of a project management office (PMO) is to support project managers in a variety of ways, which may include all of the following EXCEPT:
A.Intervening in project execution directly and without involving the project manager.
B.Managing shared resources across all projects administered by the PMO.
C.Identifying and developing project management methodology, best practices, and standards.
D.Coaching, mentoring, training, and oversight.
24.All of the following are potential information in organizational knowledge repositories EXCEPT:
A.Metrics used to collect and make available measurement data on processes and products.
B.Configuration management.
C.Tacit knowledge of previous projects such as project performance data and lessons learned.
D.Issue and defect management data.
25.All of the following are external environmental factors EXCEPT:
A.Legal restrictions.
B.Organizational values and principles.
C.Competitive movements.
D.Economic conditions.
26.Organizational process assets (OPAs) influence the management of projects. Which one of the following best describes the important categories of OPAs?
A.Organizational knowledge bases and processes.
B.Processes, policies, procedures, tools, and techniques.
C.Organizational knowledge bases, processes, policies, and procedures.
D.Organizational knowledge bases, tools, and techniques.
27.The organization's processes and procedures for conducting project work during project initiation and planning include all of the following EXCEPT:
A.Preapproved supplier list.
B.Traceability matrices.
C.Tailoring guidelines for project management processes and procedures.
D.Product and project life cycles, and methods and procedures.
28.The organization's processes and procedures for conducting project work during Executing, Monitoring, and Controlling include all of the following EXCEPT:
A.Change control procedure.
B.Issue and defect management procedures.
C.Resource availability control and assignment management.
D.Project closing guidelines.
29.Projects operate within the constraints imposed by the organization through their structure and governance framework. The system factors include all of the following EXCEPT:
A.Management elements.
B.Governance framework.
C.Organizational structure types.
D.Project management processes.
30.The interaction of the various system components creates the organizational culture and capabilities that are important for projects. Which role is typically responsible for establishing the system?
A.Organization's management.
B.Project sponsor.
C.Project manager.
D.Project team.
31.Governance is the framework within which authority is exercised in organizations. This framework includes all of the following components EXCEPT:
A.Rules.
B.Policies.
C.Techniques.
D.Relationships.
32.Which of the following best describe management elements?
A.Management elements are the components that comprise the key functions or principles of general management in the organization.
B.Management elements are the project management principles that guide how projects are executed in the organization.
C.Management elements are established by PMOs to guide project implementation.
D.Management elements are influenced by the governance framework, established for effective implementation of projects.
The Role of the Project Manager
(Section 3 of the PMBOK® Guide)
33.All of the following are generally true about leadership in a project environment EXCEPT:
A.It involves focusing the efforts of a group of people toward a common goal and enabling them to work as a team.
BIt is the ability to get things done through others.
C.Respect and trust, rather than fear and submission, are the key elements of effective leadership.
D.Although important throughout all project phases, effective leadership is critical during the Closing phase of a project when the emphasis is on stakeholder acceptance of the project.
34.Project managers spend the majority of their time communicating with team members and other project stakeholders. To communicate effectively, the project manager should generally perform all of the following EXCEPT:
A.Calculating the potential number of communication channels accurately.
B.Developing finely tuned skills using multiple methods of communication.
C.Incorporating feedback channels.
D.Seeking to understand project stakeholders’ communication needs.
35.All of the following