Key challenges in crossborder interconnector finance
Kat Buchmann1, Aled Jones *1, Yiyun Zhang2, Johanna Schönecker1
1
Global Sustainability Institute, Anglia Ruskin University, East Road, Cambridge, UK
2
University of Cambridge, Cambridge, UK
* Corresponding author:
[email protected]
Abstract
This paper assesses causes for, and challenges related to, the funding gap in infrastructure required
for a large scale increase of renewable energy in the European energy mix, specifically crossborder
interconnectors to transport renewable electricity from areas with high renewable energy potential
and production to centres of energy consumption. We identify eight barriers that need to be
addressed in order to make investment in interconnectors more attractive. We delineate both
technological and governance/legislative barriers to investments in this area. Our analysis is based on
a scoping literature review and a workshop that was held in London involving finance and legal
experts.
Keywords
Energy transition; climate change; investment barriers; funding gap
1. Introduction
Investment needs for an extensive upscaling of renewable energy (RE) are not being met – we are
experiencing a green funding gap (Hafner et al., 2020; Jones, 2015; Jacobsson & Jacobsson, 2012;
Yoshino et al., 2019). Often attention to this funding gap has focused on investments required to
deploy RE power generation infrastructure itself (McCollum et al., 2018; Egli, Steffen & Schmidt, 2018;
Mazzucato & Semieniuk, 2018). However, due to intermittency and regionally disparate potential, as
well as significant changes to energy demand including through electric cars, large-scale addition to,
and upgrading of, the electricity network infrastructure will be required. Therefore, a large scale
expansion of grid reinforcement, storage and interconnectors is needed.
The European Union’s (EU) internal electricity interconnection target is 15% by 2030. That is by 2030
it was expected that 15% of all electricity production in the EU would be interconnected between
Member States. However, the 2030 target was agreed in a radically different situation – the EU wind
and solar energy share was 2%, while it is expected to make up 30% of the EU’s electricity in 2030 (EC,
2017). Financing for interconnectors alone would need to go up from between €0.9 to €1.5 billion
annually to €3.6 billion per year in moderate or high RE deployment scenarios (van Nuffel, 2017).
Member states are required since 2014 to inform the European Commission of any planned
infrastructure for the next five years. Based on this, the European Commission produces a report every
two years on the European energy systems and any gaps in infrastructure that may arise. However, in
the past the member state data provided has been of poor quality (van Nuffel et al., 2017).
Since 2013, the European Commission publishes a list every two years of Projects of Common Interest
(PCI). Energy infrastructure projects must lead to an energy market integration in at least two EU
member countries to qualify. Qualifying as a PCI, an infrastructure project can ask for financing from
several EU sources, such as the Connecting Europe Facility (CEF). A designated PCI project is supposed
to benefit from fast-tracked environmental impact assessment and overall permitting procedures,
which in theory are supposed to be granted a maximum of 3.5 years after the application. Overall, the
average time to get a permit to build a new high voltage line is 7 years, with one quarter of all permits
taking more than 15 years to be granted. Additionally, the PCI status conferment provides a signal
boost to investors. EU funding available to PCIs is however “increasingly shifting to repayable financial
instruments rather than grants” (Ammermann et al., 2016, p. 8).
In its 2015 progress report on the state of PCIs, the Agency for the Cooperation of Energy Regulators
(ACER) identified significant delays in many PCIs. A key reason for these delays in project completion
and delivery were issues relating to financing. The Ten-Year Network Development Plan 2018 reported
that of 329 projects, 120 projects were “delayed” or “rescheduled” investments.
The ITRE report (van Nuffel et al., 2017) concluded that “the financing gap to achieve the targets and
goals associated with the European energy transition is substantial (ca. 1% of EU-wide GDP on an
annual basis between 2021-2030)” and that “Currently, the vast majority of energy expenditure comes
from private investors, as well as (non-EU) public sources in Member States. The volume of EU finance
(i.e. from the EU Budget) is too small to close the financing gap alone; and there appears to be no
prospect of an increase of the order of magnitude likely to change this” (van Nuffel et al., 2017, p.55).
Puka and Szulecki (2014) call the investment gap, the difference between current finance and what is
needed for a renewable energy transition, the “grid-lock”, while Cepeda speaks of the “sub-optimality
of interconnection investments” (Cepeda, 2018, p. 31).
Given a financing gap has been highlighted there is a need to identify the barriers that contribute to
this gap so that solutions can be developed. This finance gap in cross border energy infrastructure is
likely to exist across all geographies, however, here we focus within the EU given its explicit
commitment to increase the interconnectedness of its electricity grid and therefore more specific
barriers (above and beyond geopolitical issues) can be understood.
This paper presents data from a scoping literature review and a stakeholder workshop. We identify
eight priority barriers to scaling up investments in crossborder transmission infrastructure, and two
overarching themes namely technological barriers and governance/legislative barriers.
2. Materials and Methods
A scoping literature review (Rumrill, Fitzgerald & Merchant, 2010; Pham et al., 2014; Peters et al.,
2015) of barriers in both academic and grey literature was conducted. The review identified articles
and reports published between 2010 and 2019. The earlier cut off date was chosen as this was post
the Copenhagen Conference of the Parties in 2009 which, by failing to agree a comprehensive
international framework for climate change action, changed the perception of investment risk within
the capital markets.
The scoping review was based on the use of keywords to identify and collect relevant papers and
reports. The keywords used were combinations of a) “electricity”, “renewable energy” and b)
“interconnector” or “interconnection” and c) “European” or “crossborder” or “transnational” and d)
“finance” or ”funding” or “Investment”. These papers and reports were then examined to identify
those of particular relevance to interconnector barriers within the European Union context which
resulted in a total of 98 papers and reports (see appendix A).
A thematic review (Braun & Clarke, 2006) of those articles was conducted. Code words were identified
and then collated together into themes. This was led by the lead and fourth authors and then checked
by the second author of the paper. This led to the identification of twelve emergent sub-themes which
highlighted a number of barriers to interconnector investment. These sub-themes were collected
together under three overall themes which were:
A) cross-border cost-benefit allocation
B) legal, jurisdictional and governance issues
C) barriers to financing projects that involve both EU and non-EU countries.
On November 30, 2018, a workshop on Cross-border Electricity Infrastructure Finance was held in
London. The workshop consisted of a presentation on the electricity infrastructure finance gap
emergent themes from the scoping review. Different cross-border infrastructure projects and their
financing and regulatory issues were presented as case studies. These case studies had been identified
during the scoping literature review as particularly salient to the barriers identified. The workshop was
run by the first and third author of the paper.
Participants for the workshop were sought from individuals with experience in securing financing or
influencing policies associated with interconnector projects. An initial list of invitees was drawn up
from the network of the authors and a search based on the case studies identified during the scoping
review. Further invitees were sought through a snowball sampling where initial confirmed participants
were asked to recommend others. Seventeen participants took part (see Table 1), including
representatives from transmission systems operators (TSOs), regulatory authorities, banks (both
European and third country), investment funds, engineering companies, electricity companies,
financial advisors, lawyers advising largescale electricity infrastructure projects, academics and
consultancies.
Table 1: Participant organisations represented at the workshop
Organisation type
Organisation name
TSO
Bank & Investment
Electricity company
Governmental think tank
Interconnector developer
Auditing and consultancies
Law
Academics
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
ENTSO-E
Ofgem
Tennet
MUFG
Triodos
EDF Renewables
Carbon Trust
Transmission Investment
ARUP
Baringa
Boston Consulting Group
FTI Consulting
KPMG
Pinsent Masons
Squire Boggs Patton
Diplomatic Academy Vienna
University of Cambridge
After the initial presentations and a group discussion, the participants were split up into three smaller
groups to discuss barriers further. The three overall emergent themes from the scoping review were
used as a prompt for these small group discussions. Each group discussed each of the three topics.
The workshop was held under the Chatham House rule (no attribution of comments to any individual).
Participants gave informed consent to take part in the workshop with formal ethics approval having
been sought under the University’s ethics approval process. The workshop was audio-recorded and
the small group and plenary discussions then transcribed. Notes were also taken throughout the
workshop by the facilitators. These notes and transcriptions were then thematically analysed (Pham
et al., 2014) allowing any new themes to emerge or be confirmed from those identified during the
scoping review. The themes gathered from the workshop were used to create a list of barriers which
were then refined to ensure as little overlap between the barriers as possible (Pham et al., 2014). This
was led by the two first authors of this paper. Two overall themes were identified with a number of
sub-themes.
The next section presents the data gathered at the workshop. The themes, sub-themes and policy
recommendations are then presented in the final section.
3. Results
Many issues impacting the financing for cross-border infrastructure are exactly the same as a national
project. Workshop participants estimated that only about a quarter of the financing risks stem from
its cross-border nature. It is therefore important to specify whether an issue is inherent irrespective
of whether it is cross-border or not. An example of this is construction risk which is the same
irrespective of whether a project is national or cross-border infrastructure. However, participants
highlighted the fact that the investment structure in an interconnection project follows the revenue
structure of the operational phase of the project. This revenue structure, and what is permitted or
not, will differ from country to country making an investment more complex.
A lawyer advising interconnection projects asserted that the major factor in cross-border projects is
political and regulatory uncertainty. This includes sudden political changes in member states. For this
reason, it is “nearly impossible to get financing externally for such projects” since investments are
perceived to be too high risk. There are then issues pertaining to which national laws apply to the
interconnector and who to sue in which forum in case of an issue.
The long lifespan of the project versus the regulatory uncertainty, especially given the lifespan of
regulation can be short, is a mismatch. Political changes in Bulgaria, capacity market remuneration in
the UK, and German renewable energy regimes changes have all contributed to a perception of
considerable regulatory risk. The more investments are being made, the more costs are generated
and with that also comes higher political pressure of managing those costs. The regulatory authority
faces public and political pressure so it cannot be ruled out that adjustments are made which then
conflict with the viability of the investment. However, it is of course possible to insure against political
risk and the risk can be shared between project partners. Other attendees did not rank regulatory risk
as highly. An investor would either like a regulator’s track record or see that there has been delays in
previous interconnections or projects due to regulatory issues and would then not invest in that
member state in the first place.
Another workshop participant pointed out that there was a cultural difference in inspection between
countries. In the UK, it is quite common to have a third party building an interconnector. That situation
is not the norm on the continent. This adds another layer of complexity when it comes to crossjurisdictional issues in interconnection. In a project, in which there are more UK investors, the
technological structure becomes a crucial element of the project because it is possible to get European
revenues in a tax-optimised way. The question is then “what do you structure as equity or as dead
financing so that you have deductible interest payments which are taxed more in a country where you
invest.”
One reason why some transmission line projects are predominantly financed by banks is that these
already possess certain environmental and social compliance principles needed. A representative
from a commercial bank explained three different finance sources. Firstly, on balance sheet
investment by utilities and TSOs on the Regulatory Asset Base (RAB) model. Secondly, the use of credit
facilities to take some of that debt off their own balance sheets. There is thirdly project finance, which
on the transmission side is mainly limited to the Offshore Transmission Owners (OFTO) regime in the
UK. The strong contractual arrangement in this regime is very attractive to equity participants and to
debt participants. This was thus deemed a great way to inject private financing into the regime. In
general, other interconnector revenue flow regimes are less clear and less attractive for banks. The
regulator also put in place an extensive information campaign and “Investor bridge” on the OFTO
regime.
One attendee pointed out the issuance of bonds for financing the construction as well as grid
acquisition. Another participant recalled their work on a merchant interconnector and the advantage
of arbitrage – whether regarding a price differential or a time differential price. The slow elimination
of these differentials and thus the self-eliminating nature and usage of an interconnector are difficult
to forecast. It also cannot be easily comparable to OFTO, where the revenue stream is more
straightforward to forecast. A bank representative highlighted the attractiveness of OFTO for investors
as an “availability payment” and advocated the expansion of the regime to areas other than offshore
wind. A regulatory agency participant stated that in the OFTO and its revenue stream – if it is seen as
a fixed revenue stream, then it is quite clear to investors what their revenue from the interconnector
is. The cost of debt on the asset is paid by the regulator and the regulatory asset base that is paid not
just from the gearing portion, but the whole RAB. This means that equity still gets a return in a worstcase scenario.
However, a representative from a bank emphasised the issue of temporality. The revenue stream
timeframe, which was definitely not “regularly (every) six months” was not as attractive for banks.
While the cost of debt and the return to equity may be clear, it is still not on a deep level of project
finance asset by asset basis. As a large utility with a very big portfolio this is easier to hedge against.
An attendee from a utility noted that price differentials, arbitrage, were becoming less important for
interconnection than in the past. This was now not as relevant anymore as future interconnection
would need to be much more about transmitting RES from the wind and solar power houses of Europe
to the urban centres of consumption and industry. One participant wished to highlight the distinction
between an interconnector between two large grids allowing electricity to flow in time of arbitrage
and an high-voltage direct current (HVDC) cable which connects a windfarm to a grid which is instead
a unidirectional flow of one connection asset. Often this is a regulated asset with a regulated rate of
return and thus different legally to an interconnector – those are two different types of assets.
For capital subsidies, especially in the case of the project cost that EU financial pots will be willing to
pay for a PCI, one participant felt that in order to qualify the project needed to basically be
“uneconomic” by default –“you need to be in the broader social interest of the EU, but you can't really
be particularly profitable or economic. […] but the difficulty is, in order for you to proceed as a project
you need regulatory approval on both sides of the link, which essentially provides for the revenue
model, be it exempt or capital flaw or tariff […] and that approval will very rarely be forthcoming if
you're not economic […]. So, there is a little bit of a mismatch from the national perspectives for the
regulatory approvals and how the support coming from the European level is forthcoming.”
Attendees also discussed German Feed-in-Tariffs (FiTs) and how they created arbitrage requiring
interconnections. Most attendees favoured auctions to FiTs. Of greater urgency, since auctions had to
be “won”, were long-term and day ahead ability for system operators to interrupt the pre-prescribed
plan of the interconnector owner and what level of compensations could be applied by whom. This
issue, of the day ahead markets was seen as a potential real risk to investors. It could potentially
require a redesign of the electricity markets in member countries. Market design is key to ease
congestion and interconnectors could even worsen this. The example of NorthConnect connecting
Scotland to Norway was given as an interconnector that could just as easily worsen or ease congestion.
An engineer emphasized that the amount of internal capacity within members states was considerably
higher in most countries than external capacity and then often interconnection has to be HVDC purely
from a technical standpoint.
Issues around the cap and floor regime as well as environmental consenting were also discussed.
3.1. Cost benefit allocation
Interconnector projects are assessed with regards the benefits of connecting to producers,
consumers, and markets. The ENTSO-E methodology uses information from all member states, TSOs
and projections to understand if a project would be in the best interest of the EU as a whole and then
additionally, each member state will assess the impact on their own country. If a project is beneficial
for one country, but not for the other a framework has to be put in place to allow the projects to
proceed if there is an overall benefit compared to the capital need to build the project.
There are certain differences between member states regarding the producer benefits and costs. For
example, countries in Northern Europe with large hydro potential and a large industry that relies on
cheap electricity, focus more on the potential financial impact of projects and tariffs on producers.
Countries with fuel poverty instead focus more on the consumer side and raising tariffs to finance an
interconnection is more sensitive. These different considerations and poverty/industry levels need to
be taken into account and need to be brought together into a coherent structure.
One participant cautioned that in the future, these cost-benefit allocations would become much more
complex due to the intermediate category of prosumer. Cost–benefit allocation processes of
interconnection or storage projects in the future will need to account for an expansion of this
intermediate category and while it is clear that this category will expand in the future, it is by no means
clear to what extent or in which ways or where geographically. All of this makes designing or improving
cost-benefit allocation mechanisms more complex. Large consumers or producers may have interests
diametrically opposed to those of future prosumers.
An expert from a regulatory agency agreed, both regarding prosumers and interconnector cost-benefit
analysis and around different member states’ preferences on whose interests to emphasise. If an
interconnector can benefit both consumers and producers in a given country then this is a simpler
model. However, price inflation benefitting producers is more difficult even within one country. It is
important to understand how different countries structure revenue returns. If there is sufficient
difference between them, the process to finding a solution might be onerous. It could be that a project
is identified as being beneficial to the EU as a whole, and then gets PCI status, but at member state
level the view could be different.
An academic argued that uncertainty of revenue streams and regulatory risk are what really kills a
project – and the consumer or producer focus is less relevant, as long as the revenue arrangements
are crystal clear and not likely to change.
A developer stated that this clarity, or lack thereof, of course determined the revenue stream. Another
major factor in financing is the timeframe of any approvals necessary. They pointed out that the TenYear Network Development Plan only being published every two years was problematic, as two year
old data was not particularly useful. However, it was being used by financiers as a key metric to
determine whether a project will proceed or not - although this had never been the plan’s intended
purpose. It would be beneficial from a developer’s perspective for a project to get all approvals
necessary already in the early PCI stage. While there are reasons this may be difficult including lack of
certainty regarding the overall costs of a project, for a developer it would be a major improvement.
Developers generally supported the EU moving away from an equal allocation of revenue and costs
for cross-border infrastructure and that this would also help a project to get funding from the market.
Nonetheless, in cases in which one state believed it should be equal, it was still complex and the
decision reached needed to also work for regulators, developers and other stakeholders. Equally,
there is the risk of member states not being prepared to accept less than 50%, be it ownership costs
or revenues, from a territorial sovereignty perspective or simply a perceived governance of project
perspective, which can cause some difficulties.
A representative of a regulating agency explained that there was not yet a structure in place to address
issues of practicality in terms of how finance prices future risk, e.g. how a force majeure would be
defined. Many states have different perceptions on what risks should be covered. These differences
again create greater risk and make the project less attractive for investors. There are furthermore
unaddressed issues surrounding reaching an acceptable income or what will happen if a fixed revenue
stream falls away. If all these issues cannot be solved in ways that provide sufficient clarity for
lenders/investors, then the projects will fail to attract the investments needed. One partner in an
interconnector explained that the issue was the proof or definition of force majeure and what was
outside of the other partners’ hands.
A developer underlined that there was also an issue of temporality creating difficulties and increased
risk for cross-border projects – if the countries involved had different timeframe preferences or a
differing sense of urgency and this could not be aligned, then investors would perceive this risk again
as too high. There are additionally differences in who is perceived to be a suitable, acceptable investor
in cross-border interconnection projects. On the European continent, project partners for critical
national infrastructure in this sector are almost exclusively the national monopoly TSOs who know
each other very well and frequently cooperate. Such trust will be more complex if the party providing
the funding, the equity participant or the project partners are, like is the case in the UK, not from that
country.
3.2. Legal, jurisdictional and governance issues
Coordination of different regimes is key. There is a need for cross-jurisdictional authority. On one
hand, in projects with two jurisdictions, project investors understand that it will be more difficult to
effect a change – positively or negatively. However in this case countries will be less likely to
fundamentally change the income factors of an electricity project in this case, which makes it less risky
from a finance perspective.
One key issue that the group discussed was the lack of regulatory certainty and how this makes
actually investing quite difficult, because since investors may not know what their return is going to
be in five years, ten years, fifteen years’ time and infrastructure investments require much larger sums
invested in single assets.
Arbitrage risks were another key point in discussion and that while this de-risks the project for the
investor, it moves it onto the consumer. Several attendees highlighted that regulators imposing
certain regulations on interconnector projects did not seem to fully understand how this meant that
the risk was moved from developer to consumer. There needs to be arbitrage coordination, but the
group could not agree on the parameters for that. Another key point that was made concerned the
EU’s opposition to merchant investments or the EU not allowing the use of transmission revenue for
anything other than to lower prices or to re-invest. This in and of itself deterred a lot of private capital,
especially from abroad.
Ultimately too many countries focus a lot on security of energy supply, but not on the positive role
interconnectors could play in this.
3.3. Projects between EU and non-EU countries
Since third countries are not covered by EU legislation, there are obvious jurisdictional issues and the
investors have to deal with national laws first. The European Commission in such a case would be
required to put in place a renewables recognition agreement, as ruled by the November 2014 ECJ case
“Green Network v Autorità per l’energia elettrica e il gas” (ECJ, 2014). In the case in question, the ECJ
was asked to rule about the Free Trade Agreement with Switzerland and renewable energy certificates
in Italy. The Italian Electricity and Gas Authority had fined the Italian Green Network company for
failing to purchase green certificates in an amount corresponding to the quantity of electricity which
that company had imported into Italy from Switzerland. Green Network argued that they had supplied
guarantees of origin proving the renewable energy characteristics of such electricity and thus
considered their obligation under Italian law to have a certain amount of renewable energy in their
energy supply mix to be met. Italian law provided that guarantees of origin from third countries, i.e.
outside the European Union [like Switzerland], would be eligible for meeting this obligation subject to
the existence of an international agreement to that end and Italy had such an agreement with
Switzerland (Fouquet, D. and Nysten, J. 2014). The European Court of Justice ruled that the EU enjoyed
“exclusive external competence relating to the promotion of electricity from renewable energy sources
through guarantees of origin in the Internal Market” – therefore Italy’s bilateral agreement with
Switzerland had been in conflict with European law.
Remaining in the area of legal issues, shareholder rights might change as the interconnector crosses
from the third party to the EU country. This would mean that it may be necessary to have a single
buyer to circumvent third party access issues. Nonetheless, some participants reasoned that arbitrage,
thus electricity price differences between the two countries, may give the third country a lower
incentive to adopt the EU norms.
One attendee reasoned that cost-benefit allocations would play a major role in the future in 3rd
country connections – since many of the countries wishing to export renewable energy to the EU are
less wealthy than the EU, e.g. Northern African states. In this case it is important that a transmission
line does not mean that the social or environmental cost of energy is exported. Another participant
added that this is not only an issue for 3rd countries, especially those with a lower purchasing power,
but also a dilemma even for UK-France interconnectors as the nuclear risk is borne predominantly by
France.
Regarding actual construction of infrastructure, while engineering standards drive for conformity of
equipment, there could be various construction contract issues e.g. delay damages, enforceability of
claims. Similarly, there is a large political risk for third countries, both for North Africa as well as
interconnections to get solar energy from Turkey. These concerns would make investment riskier and
thus potentially less attractive – especially for pension funds.
When the small group discussion turned to Brexit and infrastructure finance with the UK as a future
3rd country, participants expressed concerns about major investment delays and strong cost of capital
for electricity infrastructure and interconnections involving the UK. Construction costs themselves
would go up regardless, especially in a No Deal Brexit, due to British pound exchange rate issues and
necessary import of materials. In case of a No Deal Brexit, there would be major uncertainty and the
EU Renewable Energy Directive (2009) would no longer apply. The UK would have to put in place a
statutory instrument. The UK will also fall out of EU trade agreements with (other) 3rd countries and
would be hit with the GATT 97 tariff wall. Even trading electricity with Ireland without an EU deal
would be an issue.
4. Discussion
Through this analysis and the scoping review we have identified eight priority barriers (sub-themes)
under two overall themes – governance/legislative barriers and technological barriers. The following
summarise each of those two themes and sub-themes.
4.1 Technological barriers including cost of technology solutions
4.1.1. HVDC technology; converters; overland lines; transformers
Other than Spain and Poland, the areas furthest behind in interconnection are Malta, Cyprus and large
Greek and Italian islands (Crete, Sicily) (Puka, & Szulecki, 2014; Micallef, 2011; Silva et al., 2017). Some
studies also identify the “offshore triangle” of the British Isles, Norway and Germany as in need of
further interconnection. It has been designated by TEN-E (Trans-European Networks for Energy) as
one of four priority electricity infrastructure corridors (Sunila et al., 2019). Connecting the European
islands or any offshore wind farm to mainland Europe requires more expensive underwater HVDC
cables (Andersen, 2014). Since HVDC can only transmit 1000 MW, for bulk transmission many cables
have to be installed in parallel, increasing costs further. Additionally, there is a small number of
suppliers of HVDC cables. Andersen (2014) thus cautions that due to technical immaturity, financing
for HVDC is particularly challenging to find.
Offshore wind farms in Europe are often relatively close to several states and so it may be beneficial
to create connections with more than one country. Meshed offshore grids (MOGs) are such
“integrated offshore infrastructure where offshore wind power hubs are interconnected to several
countries as opposed to radial connection linking the wind farm to one single country and market”
(Sunila, et al., 2019; PROMOTION, 2019). However, the majority of undersea trading cables are linecommuted convertors (LCC), which cannot be cheaply upgraded to transnational wind-farms.
Voltage source convertors (VSCs) for this are costly and lead to a lower Energy Return on Investment
(EROI). There is, additionally to VSC immaturity, the technical issue of breakers for HVDC – these
currently do not exist. This means that if there is an outage in one windfarm, the entire meshed
offshore grid is taken out. This leads to energy companies’ and TSOs’ reluctance to invest in MOGs.
German windfarms use HVDC which lends itself to easier meshing and enables transmission of longer
distances, but UK, Danish and Dutch offshore windfarms mainly use cheaper HVAC transmission
systems, which cannot be connected. The reason that this approach was taken is that the windturbines
themselves use alternating current (AC) and German windfarms thus require expensive AC-DC
converters at sea - also prone to outage (Andersen, 2014).
More expensive DC underground cables are also needed for crossborder interconnections on land due
to poor public acceptance of overhead lines (Ciupuliga, & Cuppen, 2013; Menges, & Beyer, 2014). It
may be that the public would be even less inclined to accept lines for energy export (Ciupuliga, &
Cuppen, 2013; Devine-Wright, 2013). For example, the Baixas-Santa Llogaia interconnector, “Europe’s
first integrated onshore HVDC interconnection” (Francos et al., 2012), between France and Spain took
30 years to be approved and built. In order to cope with public protests against overhead lines, in 2006
France and Spain asked the European Commission to provide a European facilitator/mediator for the
project (Ciupuliga, & Cuppen, 2013).
Costly transformers are also needed to equalize voltage between different TSOs (Newman, 2015;
ENTSO-E, 2017).
4.1.2. Loop flows
A loop flow occurs when electricity generated in one place encounters congestion in the grid and
therefore flows through other (countries’) grids, to reach the consumer. Loop flows, unscheduled
flows, lead to free-riding, congestion and issues of cost-sharing. Currently only about 30% of physical
electricity infrastructure capacity is used for trade (European Parliament, 2019; Simon, 2018). TSOs
usually shut off cross-border trade in case of congestion due to loop flows.
4.2. Governance/legislative barriers
4.2.1. Finance model
Under the Regulated Asset Base (RAB) model, capital expenditures are usually passed on to
consumers. This is problematic as member states with some of the more significant interconnection
needs are former communist and poorer Mediterranean states already experiencing high energy
poverty (Bouzarovski & Tirado Herrero, 2017). Raising electricity prices to the level that would trigger
the required investment is thus politically too sensitive.
Merchant model financing is the norm in many locations outside the European Union, especially in
North America. In the EU, it is only allowed in very limited circumstances. Financial risk is higher under
the merchant model and thus investors expect a shorter payback period, making it in that sense more
attractive. EU opposition to the merchant model in and of itself deters a lot of private capital,
especially from abroad.
Due to longer payback periods under the RAB model, long term-oriented pension funds and insurance
companies would be natural investors. However, these often choose to invest in already operating
assets over planned projects. Pension funds are also regionally specific and predisposed to investment
in their national territories (OECD, 2015).
Additionally, many TSOs are restricted in their access to equity by their country’s regulatory
framework (European Commission, 2018). With the exception of Elia and TenneT, all TSOs are purely
national (de Clercq, Jewkes & Davies, 2013). Nonetheless, even TenneT placed transmission
restrictions on their Denmark – Germany connection, for which they were fined by the European
Commission as an antitrust breach (Eckert, 2018).
4.2.2. Electricity monopolies, unbundling
About one third of European TSOs are not unbundled, thus still own both power plants and the
transmission infrastructure (Council of European Energy Regulators, 2016, p.7). This represents
further perverse incentives to not expand transmission as additional electricity imports would create
competition for the power plants owned. National electricity companies are often close to
monopolistic in their respective nation states (van Nuffel et al., 2017) and thus have strong lobbying
power to thwart further interconnection.
Profit from interconnectors comes from price differences between two electricity zones and
congestion in the network. TSOs are the entities in charge of building additional interconnection and
yet gain from auctioning off capacity in times of grid congestion. This provides a perverse incentive.
To counter this issue, EU regulations stipulate that TSOs need to reinvest income from grid congestion
auctions either to build more interconnection – which however then would lower their future income
from congestion auctions – or to lower their tariffs. Neither of these options would incentivise
investment. Flynn argues that British wind investors are not interested in further crossborder
interconnection since “their core business model is selling wind electricity into the UK and gaining
premiums for that via CfD auctions” (Flynn, 2016). Engie, RWE, Scottish Power and EDF all argued
against interconnection in the case of the Greenlink project, stating that this would create unwanted
economic competition for them (Dutton & Lockwood, 2017).
4.2.3. Lack of harmonisation across Member States
Due to RE intermittency, several countries introduced capacity remuneration mechanisms (CRM) for
coal plants and other conventional power plants to provide continued capacity – even though this
otherwise could become uneconomic. CRMs are not harmonised. Foreign generators and
interconnection are not taken into account. This is a disincentive to further interconnection
investment. CRMs accord different participation rights to imported electricity/interconnectors: from
Spain and Portugal, where they cannot participate at all, to the UK (Höschle, Le Cadre, & Belmans,
2018), where from 2019/2020 onwards in theory interconnectors will be able to contribute 2900 MW,
a figure which will be deducted from installed capacity generation (Cepeda, 2018). While Hoeschle, Le
Cadre and Belmans (2018) believe inclusion of imported capacity provides a positive investment
signal, Mastropietro, Rodilla and Batlle (2015) caution that ”paradoxically [...] the presence of crossborder interconnection could increase the amount of capacity to be procured and could result in
overinvestment in the country implementing the CRM.” Meyer and Gore (2015) believe CRMs are
detrimental for consumers and producers. Grigorjeva (2015) instead recalls that the German
government has argued that France’s CRM will be good for German consumers, since due to
crossborder interconnection greater capacity in France will result in cheaper prices for German
consumers without further investments.
In the case of a crossborder interconnection transporting RE or connecting an offshore wind farm, a
project would likely be able to benefit from subsidies – but these are national. This has led to conflicts
and European Court of Justice (ECJ) cases. In the 2014 cases “Ålands Vindkraft vs. Swedish Energy
Agency” (C-573/12) and “Essent vs Flanders DSO” (C-204 to 208/12), the European Court of Justice
upheld member states’ rights to exclude foreign RE entities from accessing generation subsidies in
certain circumstances (Durand & Keay, 2014; Szydlo, 2015). This favours national electricity
production, the disparate geographical RE potential in Europe notwithstanding. However, the
subsequent C-492/14 case (2016), again involving energy company Essent importing Dutch RE to
Flanders, ruled preferential grid tariffs could not exclude electricity import (Pentinnen, 2018). Due to
the subsidies issues, the COBRA cable, a PCI by Dutch-German TenneT and Danish Energinet and going
through German waters, was not interconnected to Germany initially (Flynn, 2016).
Other harmonisation issues are the crossborder day-ahead market (PCR) and the intraday market
(XBID). Crossborder interconnection use improved for countries after joining the PCR (Gomez et al.,
2019). XBID, under the Target Model, allows for participants to order electricity in one market and for
that to automatically be met by capacity from another market if transmission capacity is available (Le,
Ilea & Bovo, 2019). Glachant (2016) nonetheless argues that the Target Model is deeply flawed as it
continues national TSO fiefdoms and pre-dates RE expansion, which the system cannot cope with well.
Whereas for PCR and XBID, pricing “is based on implicit auctions (uniform clearing price for energy
reflecting cross-zonal congestion)”, ”in the continuous trading mode [...] the associated cross-zonal
capacity [is] allocated for free […]” (Glachant, 2016). Balancing markets similarly have not been
harmonised yet and operating reserve types to be used need to be decided at European level (Gomez
et al., 2019).
Issues of harmonisation besieged the KriegersFlak project, the first “hybrid project” - offshore wind
energy project feeding electricity into more than one market. Initially, German, Danish and Swedish
TSOs did a cost-benefit analysis regarding a trinational project. However, regulatory differences meant
investment by Sweden would not make sense and the Swedish TSO withdrew from KriegersFlak in
2010 (Meeus, 2014; Mekonnen, Huang & de Vos, 2016). There are three competing régimes which
make cross-border cooperation complex - countries either apply deep connection, shallow connection
or supershallow connection charging policies. In the case of a deep connection charging policy, the
wind farm developers are responsible for the costs of connecting the windfarm to the main grid and
any reinforcement requirement. A shallow connection charging policy means that the generators are
only responsible for the costs of the wind farm connection to the main grid. Finally, in a supershallow
connection charging system the TSOs are instead responsible for the costs of the connection to the
main grid (van Nuffel et al., 2017).
The grid tariffs that a regulated electricity company is allowed to charge are also not harmonised – it
can be either “cost-plus”, “Incentive-based”, “performance-based” or “output-based”. In the cost-plus
remuneration system, the company is entitled to OPEX and an ‘allowed’ profit margin, which critics
argue means that one way for the company to make more money is to artificially increase ‘costs’
(Matschoss et al., 2019). The remuneration can furthermore depend on whether it is calculated based
on the grid congestion level or on physical capacity transmitted (van Nuffel et al., 2017; Mekonnen et
al., 2016).
4.2.4. Inter-TSO compensation (ITC)
A country may function primarily as transmission transit state and while interconnectors will be
physically on their soil, they will not benefit from the increased transmission. In the case of electricity
export demand from a country with higher electricity prices, the price may even go up. It is therefore
necessary to find ways to remunerate transit countries. To address this, the Inter-TSO Compensation
mechanism (ITC) was created. It is however in need of reform. The biggest issue is that the ITC treats
existing lines and planned lines in the same way – thus countries with existing lines can get the most
money (Neuhoff, Boyd & Glachant, 2012). Hadush, de Jonghe and Belmans (2015) in their assessment
find no strong correlation between actual transit and Inter-TSO compensation (ITC). Currently, the ITC
is too small to entice investment, too complex to be explained to potential private investors easily and
is not taken into account in investment decisions.
4.2.5. Investment volume needed surpasses TSOs’ capacity
Former communist and smaller island states’ TSOs are under greater financial pressure due to
previous lack of interconnection while often lacking knowledge of how to attract funding. Some TSOs
have little experience of outside finance and a PCI may have been the first time the TSO interacts with
outside finance (Ammermann et al., 2016).
4.2.6. Capital reserve requirements
The 3rd Basel Accord contains international banking regulations, to be implemented by 2019. Basel III
redefined assets that qualify as capital and increased the minimum amount capital a bank needs to
hold. Similar regulations exist for insurance companies and pension funds (European Commission
directive Solvency II, IORP II). Insurance companies are a major investor in interconnection projects.
These requirements mean a higher cost of capital for any infrastructure project (Narbel, 2013;
Breitschopf & Pudlik, 2013; Ang, Röttgers & Burli, 2017).
5. Conclusions
In this paper we have delineated key barriers to investment in crossborder interconnection in Europe
found after a scoping literature review and workshop with stakeholders in energy, law and finance.
While infrastructure risk remains even without crossborder connections to reduce the crossborder
specific risks further European harmonisation is tantamount. This includes the voltage that we use,
subsidies for renewable energy as well as CRMs and charging regimes. Unbundling of TSOs will need
to be completed to avoid internal disincentives to investment. Permitting has to become further
streamlined. To solve the systemic incongruences concerning meshed offgrid, Gorenstein-Dedecca et
al. (2018) and Sunila et al. (2019) urgently suggest the introduction of a European supranational TSO
responsible for all offshore windfarms.
In order to make projects more attractive to outside investors, the introduction of Offshore
Transmission Owner (OfTO) style licences to European projects other than offshore wind has been
suggested. In the British OfTO remuneration, the cost of the debt on the asset is paid across the whole
RAB and not just the particular invested asset lowering the risk on equity investments (Fitch-Roy, 2016;
Bhagwat & Lind, 2018; Meeus, 2014). Another suggestion has been the expansion of also
predominantly British YieldCo, where RE assets are bundled together to de-risk these energy
infrastructure projects. To tackle some TSOs’ unattractiveness for outside investment due to bad risk
ratings, Ammermann et al. (2016) suggest separating PCIs from the rest of the TSO’s work to de-risk
the PCI.
It likely that technological barriers can be overcome with more research and development as well as
more deployment of HVDC breakers and subsea cables so that the technology learning curve can help
drive prices to a more affordable level. Therefore, it is key that the EU prioritises this research
investment through programmes such as Horizon Europe. To address loop flows, the European
Commission Expert Group on Interconnection suggests that “the costs of remedial actions should be
shared based on the ‘polluter-pays principle’, where the unscheduled flows over the overloaded
network elements should be identified as ‘polluters’ and they should contribute to the costs in
proportion to their contribution to the overload” (EC, 2017, p.16).
These suggestions nonetheless do not address all underlying dilemmas concerning perverse incentives
stemming from the overall business model – intrinsic issues. This includes the lobbying power of the
almost monopoly companies, congestion rent and price differentials as driving force for
(non)investment. As long as there is no sensible price on carbon and regulatory questions of
crossborder interconnection projects, conservative investors like pension funds may still prefer fossil
fuels or national RE projects. However, the growing momentum towards zero carbon targets coupled
with campaigns for divestment from fossil fuels represents an opportunity for radical change within
the energy sector.
6. Acknowledgements
The research was funded by the European Union’s Horizon 2020 research and innovation program
under grant agreement No. 691287: MEDEAS – Modelling the Renewable Energy Transition in Europe.
7. Declaration of interests
The authors declare that they have no known competing financial interests or personal relationships
that could have appeared to influence the work reported in this paper.
8. References
Agency for the Cooperation of Energy Regulators, 2016. Consolidated Report on the progress of
electricity and gas Projects of Common Interest for the Year 2016.
Ammermann, H., Diederich, H., Janousch A., Krebs, M., Ruf, Y., 2016. Cost-Effective Financing
Structures for Mature Projects of Common Interest (PCIs) in Energy. Brussels: Roland Berger
Andersen, A., 2014. No transition without transmission: HVDC electricity infrastructure as an enabler
for renewable energy? Environmental Innovation and Societal Transitions, 13, 75-95
Ang, G., Röttgers, D., & Burli, P., 2017. The empirics of enabling investment and innovation in
renewable energy. Paris: OECD
Bhagwat, P. and Lind, L., 2018. Towards a more investment friendly economic incentive regime for
offshore infrastructure projects. Florence: European University Institute Florence School of Regulation
Policy Brief.
Bouzarovski, S. & Tirado Herrero, S., 2017. The energy divide: Integrating energy transitions, regional
inequalities and poverty trends in the European Union. European Urban and Regional Studies, 24 (1),
69-86
Braun, V. & Clarke, V., 2006. Using thematic analysis in psychology. Qualitative Research in Psychology,
3(2), 77-101
Breitschopf, B., & Pudlik, M., 2013. Basel III and Solvency II: Are the risk margins for investments in PV
and wind adequate?. Energy & Environment, 24(1-2), 171-194
Cepeda, M., 2018. Assessing cross-border integration of capacity mechanisms in coupled electricity
markets. Energy Policy, 119, 28-40
Ciupuliga, A.R. & Cuppen, E., 2013 The role of dialogue in fostering acceptance of transmission lines:
the case of a France–Spain interconnection project. Energy Policy, 60, 224-233
Council of European Energy Regulators, 2016. Status Review on the Implementation of Transmission
System Operators’ Unbundling Provisions of the 3rd Energy Package. Brussels: April 2016.
de Clercq, G., Jewkes, S. & Davies, A., 2017. “EU grid champion stuck in tangle of wires and pipes”,
Reuters, April 10, 2013. https://uk.reuters.com/article/uk-europe-grids-consolidation-eu/eu-gridchampion-stuck-in-tangle-of-wires-and-pipes-idUKBRE9390N520130410
Devine-Wright, P. 2013. Explaining “NIMBY” objections to a power line: The role of personal, place
attachment and project-related factors. Environment and Behavior, 45(6), 761-781
Durand, É. and Keay, M., 2014. National support for renewable electricity and the single market in
Europe: the Ålands Vindkraft case. Oxford Energy Comment. Oxford Institute for Energy Studies
Dutton, J. & Lockwood, M., 2017. Ideas, institutions and interests in the politics of cross-border
electricity interconnection: Greenlink, Britain and Ireland. Energy Policy, 105, 375-385
EC, 2017. European Commission DG ENER Expert Group on electricity interconnection targets,
November 2017. Towards a sustainable and integrated Europe.
https://ec.europa.eu/energy/sites/ener/files/documents/report_of_the_commission_expert_group
_on_electricity_interconnection_targets.pdf
Eckert, V., 2018. EU tells German grid operator TenneT to raise access for Nordic power. Reuters, 7
December
2018.
https://uk.reuters.com/article/uk-eu-antitrust-tennet/eu-tells-german-gridoperator-tennet-to-raise-access-for-nordic-power-idUKKBN1O619E
Egli, F., Steffen, B. & Schmidt, T.S., 2018. A dynamic analysis of financing conditions for renewable
energy technologies. Nature Energy, 3, 1084–1092.
ENTSO-E, 2017. For a list of European TSOs’ voltages see ENTSO-E, Overview of Transmission Tariffs in
Europe, June 2017, p. 37.
European Commission, 2018. European Commission Staff Working Document, Mid Term Evaluation
Connecting Europe Facility (CEF), https://ec.europa.eu/info/publications/mid-term-evaluationconnecting-europe-facility-cef_en
European Parliament, 2016. European Parliament legislative resolution of 26 March 2019 on the
proposal for a regulation of the European Parliament and of the Council on the internal market for
electricity (recast) (COM(2016)0861 – C8-0492/2016 – 2016/0379(COD)).
Fitch-Roy, O., 2016. An offshore wind union? Diversity and convergence in European offshore wind
governance. Climate Policy, 16(5), 586-605
Flynn, B., 2016. Marine wind energy and the North Sea Offshore Grid Initiative: A Multi-Level
Perspective on a stalled technology transition?. Energy Research & Social Science, 22, 36-51
Francos, P.L., Verdugo, S.S., Álvarez, H.F., Guyomarch, S. & Loncle, J., 2012. INELFE—Europe's first
integrated onshore HVDC interconnection. In 2012 IEEE power and energy society general meeting. 18.
Glachant, J.M., 2016. Tacking stock of the EU “Power Target Model”… and steering its future course.
Energy Policy, 96, 673-679
Gomez, T., Herrero, I., Rodilla, P., Escobar, R., Lanza, S., de la Fuente, I., Llorens, M.L. & Junco, P., 2019.
European Union electricity markets: Current practice and future view. IEEE Power and Energy
Magazine, 17(1), 24
Gorenstein-Dedecca, J., Lumbreras, S., Ramos, A., Hakvoort, R. and Herder, P., 2018. Expansion
planning of the North Sea offshore grid: Simulation of integrated governance constraints. Energy
Economics, 72, 376-392
Grigorjeva, J., 2015. Capacity Mechanisms in the EU: Nationalizing Energy Security?, Berlin: JacquesDelors-Institute.
Hadush, S., de Jonghe, C. & Belmans, R., 2015. The implication of the European inter-TSO
compensation mechanism for cross-border electricity transmission investments. International Journal
of Electrical Power & Energy Systems, 73, 674-683
Hafner, S., Jones, A., Anger, A., & Pohl, J., 2020, Closing the green finance gap: a systems perspective,
Environmental Innovation and Societal Transitions, 34, 26
Höschle, H., Le Cadre, H. & Belmans, R., 2018. Inefficiencies caused by non-harmonized capacity
mechanisms in an interconnected electricity market. Sustainable Energy, Grids and Networks, 13, 2941
Jacobsson, R. & Jacobsson, S., 2012. The emerging funding gap for the European Energy Sector—Will
the financial sector deliver? Environmental Innovation and Societal Transitions, 5, 49-59.
Jones, A.W., 2015. Perceived barriers and policy solutions in clean energy infrastructure investment.
Journal of Cleaner Production, 104, 297-304.
Le, H.L., Ilea, V. & Bovo, C., 2019. Integrated European intra-day electricity market: Rules, modeling
and analysis. Applied Energy, 238, 258-273
Mastropietro, P., Rodilla, P. & Batlle, C., 2015. National capacity mechanisms in the European internal
energy market: Opening the doors to neighbours. Energy Policy, 82, 38-47
Matschoss, P., Bayer, B., Thomas, H. & Marian, A., 2019. The German incentive regulation and its
practical impact on the grid integration of renewable energy systems. Renewable Energy, 134, 727738
Mazzucato, M., & Semieniuk, G., 2018. Financing renewable energy: Who is financing what and why
it matters. Technological Forecasting and Social Change, 127, 8-22.
McCollum, D.L., Zhou, W., Bertram, C., De Boer, H.S. et al., 2018. Energy investment needs for fulfilling
the Paris Agreement and achieving the Sustainable Development Goals. Nature Energy, 3, 589–599.
Meeus, L.., 2014. Offshore grids for renewables: do we need a particular regulatory framework?
Florence: European University Institute Robert Schuman Centre for Advanced Studies Florence School
of Regulation Working Paper, 24
Meeus, L. & Keyaerts, N., 2015. First series of cross-border cost allocation decisions for projects of
common interest: main lessons learned. Florence: European University Institute Robert Schuman
Centre for Advanced Studies Florence School of Regulation Policy Brief, February 2015.
Mekonnen, M., Huang, D. & de Vos, K., 2016. Governance Models for Future Grids. HVDC Grids: For
Offshore and Supergrid of the Future (eds. van Hertem, D., Gomis-Bellmunt, O. and Liang, J.) 193-212,
Hoboken, NJ: Wiley.
Menges, R. & Beyer, G., 2014. Underground cables versus overhead lines: Do cables increase social
acceptance of grid development? Results of a Contingent Valuation survey in Germany. International
Journal of Sustainable Energy Planning and Management, 3, 33-48
Meyer, R. & Gore, O., 2015. Cross-border effects of capacity mechanisms: Do uncoordinated market
design changes contradict the goals of the European market integration?. Energy Economics, 51, 9-20
Micallef, M., 2011. Power setback as energy link to Sicily is delayed. Times of Malta. (20 November
2011) https://www.timesofmalta.com/articles/view/20111120/local/Power-setback-as-energy-linkto-Sicily-is-delayed.394695
Narbel, P. A., 2013. The likely impact of Basel III on a bank's appetite for renewable energy financing.
Bergen: NHH [Norwegian School of Economics] Dept. of Business and Management Science Discussion
Paper
Neuhoff, K., Boyd, R. & Glachant, J.-M., 2012. European Electricity Infrastructure: Planning, Regulation,
and Financing. Workshop report, Berlin: Climate Policy Initiative & Florence: European University
Institute School of Regulation
Newman, N., 2015. The Challenges of Connecting up Europe. Elektor Magazine, August 5, 2015.
https://www.elektormagazine.com/news/the-challenges-of-connecting-up-europe
OECD, 2015. Mapping channels to mobilise institutional investment in sustainable energy – OECD
Report to G20 finance ministers and central bank governors (2015).
Penttinen, S.L., 2018. The Next Chapter in the Saga of Renewable Energy Support Schemes: Still a
Certain Degree of Mystery" after Essent Belgium II. European Law Review, 1, 106-119
Peters, M.D., Godfrey, C.M., Khalil, H., McInerney, P., Parker, D. & Soares, C.B., 2015. Guidance for
conducting systematic scoping reviews. International Journal of Evidence-based Healthcare, 13(3),
141-146
Pham, M.T., Rajić, A., Greig, J.D., Sargeant, J.M., Papadopoulos, A. & McEwen, S.A., 2014. A scoping
review of scoping reviews: advancing the approach and enhancing the consistency. Research Synthesis
Methods, 5(4), 371-385
PROMOTION, 2019. The H2020 meshed offshore grid project “PROMOTION” (January 2016December 2019) https://www.promotion-offshore.net/
Puka, L., & Szulecki, K., 2014. The politics and economics of cross-border electricity infrastructure: A
framework for analysis. Energy Research & Social Science, 4, 124-134
Rumrill, P.D., Fitzgerald, S.M. & Merchant, W.R., 2010. Using scoping literature reviews as a means of
understanding and interpreting existing literature. Work: A Journal of Prevention, Assessment &
Rehabilitation, 35(3), 399-404
Silva, V., Zulueta, M.L.B., Wang, Y., Fourment, P., Hinchliffe, T., Burtin, A. & Gatti-Bono, C., 2017.
Anticipating Some of the Challenges and Solutions for 60% Renewable Energy Sources in the European
Electricity System. Forecasting and Risk Management for Renewable Energy, (eds. Drobinski, P.,
Mougeot, M. & Picard, D.), 169-184
Simon, F., 2018. Nordics balk at EU plan to limit cross-border electricity trade. EurActiv. 4 December
2018.
https://www.euractiv.com/section/electricity/news/nordics-balk-at-eu-plan-to-limit-crossborder-electricity-trade/1296194/
Sunila, K., Bergaentzlé, C., Martin, B. & Ekroos, A., 2019. A supra-national TSO to enhance offshore
wind power development in the Baltic Sea? A legal and regulatory analysis. Energy Policy, 128, 775782
Szydło, M., 2015. How to reconcile national support for renewable energy with internal market
obligations? The task for the EU legislature after Ålands Vindkraft and Essent. Common Market Law
Review, 52 (2), 489-510
van Nuffel, L., et al., 2017. European Energy Industry Investments. Study for the European Parliament’s
Industry, Research and Energy (ITRE) Committee: Brussels.
Yoshino, N., Taghizadeh–Hesary, F. and Nakahigashi, M., 2019. Modelling the social funding and spillover tax for addressing the green energy financing gap. Economic Modelling, 77, 34-41.
9. Appendix A
List of papers and reports identified in the systematic review.
1) Abrell, J., and Rausch, S., 2016. Cross-country electricity trade, renewable energy and
European transmission infrastructure policy. Journal of Environmental Economics and
Management. 79 (1): 87-113.
2) ACER, October 2018. Report to the European Commission on the implementation of the ITC
mechanism in 2017.
3) Ammermann, H., Diederich, H., Janousch, A., Krebs, M., Ruf, Y. November 2016. Cost-Effective
Financing Structures for Mature Projects of Common Interest (PCIs) in Energy. Roland Berger.
https://publications.europa.eu/en/publication-detail/-/publication/4bcfb6f3-e13c-11e6ad7c-01aa75ed71a1
4) Andersen, A., 2014. No transition without transmission: HVDC electricity infrastructure as an
enabler for renewable energy? Environmental Innovation and Societal Transitions. 13:75-95.
5) Arcia-Garibaldi, G., Cruz-Romero, P. and A. Gómez-Expósito, 2018. Future power transmission:
Visions, technologies and challenges. Renewable and Sustainable Energy Reviews. 94: 285301.
6) Ardelean, M. and Minnebo, P., 2017. A China-EU electricity transmission link. Assessment of
potential connecting countries and routes. Luxembourg: Joint Research Centre, Publications
Office of the European Union.
7) Arezki, R., Bolton, P., Peters, S., Samama, F. and Stiglitz, J., February 2016. From Global Savings
Glut to Financing Infrastructure. IMF Working Paper.
8) Battaglini, A. and Lilliestam, J., 2010. On Transmission Grid Governance. Berlin: Heinrich Böll
Foundation.
9) Battaglini, A., Komendantova, N., Brtnik, P., & Patt, A. Perception of barriers for expansion of
electricity grids in the European Union. Energy Policy, 47, 254–259 (2012).
10) Bhagwat, P. and Lind, L. Towards a more investment friendly economic incentive regime for
offshore infrastructure projects. Florence: European University Institute Florence School of
Regulation Policy Brief (2018).
11) Bhagwat, P., Schittekatte, T., Keyaerts, N. and Meeus, L., October 2017. Assessment of CostBenefit Analysis for Offshore Electricity Infrastructure Development. Florence: Robert
Schuman Centre for Advanced Studies, Florence School of Regulation Research Paper, 53
(2017).
12) Blarke, M.B. and Jenkins, B.M., 2013. SuperGrid or SmartGrid: Competing strategies for largescale integration of intermittent renewables? Energy Policy. 58: 381-390.
13) Blyth, W., McCarthy, R. and Gross, R., 2015. Financing the UK power sector: Is the money
available? Energy Policy. 87: 607-622.
14) Buijs, P., Bekaert, D., Cole, S., Van Hertem, D. and Belmans, R., 2011. Transmission investment
problems in Europe: Going beyond standard solutions. Energy Policy, 39(3), 1794-1801 (2011).
15) Bürer, M.J. and Wüstenhagen, R., 2009. Which renewable energy policy is a venture
capitalist's best friend? Empirical evidence from a survey of international cleantech investors.
Energy Policy, 37 (12): 4997-5006.
16) Castaneda, M., Jimenez, M., Zapata, S., Franco, C. and Isaac Dyner, I., 2017. Myths and facts
of the utility death spiral. Energy Policy. 110: 105-116.
17) Cepeda, M., 2018. Assessing cross-border integration of capacity mechanisms in coupled
electricity markets. Energy Policy, 119, 28-40.
18) CEEP (Central Europe Energy Partners), Roland Berger, “Making it happen – Paving the way
for the Central European North-South Infrastructure Corridor”, Sept 2015
19) Child, M., Kemfert, C., Bogdanov, D. and Breyer, C., 2019. Flexible electricity generation, grid
exchange and storage for the transition to a 100% renewable energy system in Europe.
Renewable Energy. 139: 80-101.
20) Council of European Energy Regulators (CEER). Status Review on the Implementation of
Transmission System Operators’ Unbundling Provisions of the 3rd Energy Package. Brussels:
April 2016.
21) Coxe, R. and Meeus, L., 2010. Survey of non-traditional transmission development. Paper
presented at Institute of Electrical and Electronics Engineers (IEEE) Power & Energy Society
(PES) General Meeting in Minneapolis.
22) Durand, É. and Keay, M., August 2014. National support for renewable electricity and the
single market in Europe: the Ålands Vindkraft case. Oxford Energy Comment. Oxford Institute
for Energy Studies.
23) Dutton, J. and Lockwood, M., 2017. Ideas, institutions and interests in the politics of crossborder electricity interconnection: Greenlink, Britain and Ireland. Energy Policy. 105: 375-385.
24) European Commission Staff Working Document, Mid Term Evaluation Connecting Europe
Facility (CEF), 2018.
https://ec.europa.eu/info/publications/mid-term-evaluation-connecting-europe-facilitycef_en
25) European Commission DG ENER (2015), Study on comparative review of investment
conditions for electricity and gas Transmission System Operators (TSOs) in the EU.
26) European Commission DG ENER Expert Group on electricity interconnection targets,
November 2017. Towards a sustainable and integrated Europe.
27) European Parliament legislative resolution of 26 March 2019 on the proposal for a regulation
of the European Parliament and of the Council on the internal market for electricity (recast)
(COM(2016)0861 – C8-0492/2016 – 2016/0379(COD))
28) European Parliament press release, 12 December 2018. ACER: Agreement reached to open up
and better regulate the electricity market.
http://www.europarl.europa.eu/news/sv/press-room/20181212IPR21623/acer-agreementreached-to-open-up-and-better-regulate-the-electricity-market
29) Fitch-Roy, O. An offshore wind union? Diversity and convergence in European offshore wind
governance. Climate Policy, 16(5), 586-605 (2016).
30) Gärdfors, T. European energy infrastructure opportunities: Connecting the dots. Norton Rose
Fulbright. September 2015.
31) Geddes, A., Schmidt, T.S. and Steffen, B., 2018. The multiple roles of state investment banks
in low-carbon energy finance: An analysis of Australia, the UK and Germany. Energy Policy,
115, pp.158-170.
32) Gerbaulet, C. and Weber, A. (2014). Is there still a case for merchant interconnectors? Insights
from an analysis of welfare and distributional aspects of options for network expansion in the
Baltic Sea region. DIW Discussion Papers, No. 1404, Berlin: Deutsches Institut für
Wirtschaftsforschung (DIW – German Institute for Economic Research).
33) Glachant, J.M., Rossetto, N. and Vasconcelos, J., 2017. Moving the electricity transmission
system towards a decarbonised and integrated Europe: missing pillars and roadblocks
(Florence: European University Institute Florence School of Regulation).
34) Goldberg, S., 2018. “The future’s bright and interconnected”. Infrastructure Investor Annual
Review. 19-21.
35) Gorenstein-Dedecca, J., Lumbreras, S., Ramos, A., Hakvoort, R. and Herder, P., 2018.
Expansion planning of the North Sea offshore grid: Simulation of integrated governance
constraints. Energy Economics. 72: 376-392.
36) Hadush, S., de Jonghe, C. and Belmans, R., 2015. The implication of the European inter-TSO
compensation mechanism for cross-border electricity transmission investments. International
Journal of Electrical Power & Energy Systems. 73: 674-683.
37) Hall, S., Roelich, K., Davis, M. and Holstenkamp, L. "Finance and justice in low-carbon energy
transitions." Applied Energy 222 (2018): 772-780.
38) Hall, S., Foxon, T. and Bolton, R., 2017. Investing in low-carbon transitions: energy finance as
an adaptive market." Climate Policy. 17 (3): 280-298.
39) Haesen, E., Pieter Vingerhoets, Michèle Koper, Ivo Georgiev, Carsten Glenting, Minke Goes,
Charlotte Hussy (Ecofys). July 2017. Investment needs in Trans-European Energy Infrastructure
up to 2030 and beyond. Report to the European Commission.
40) Hawker, G., Bell, K. and Gill, S., 2017. Electricity security in the European Union—The conflict
between national Capacity Mechanisms and the Single Market. Energy Research & Social
Science 24: 51-58.
41) Henriot, A, 2013. Financing investment in the European electricity transmission network:
Consequences on long-term sustainability of the TSOs financial structure. Energy Policy. 62:
821-829.
42) Van Hertem, D., & Ghandhari, M. Multi-terminal VSC HVDC for the European supergrid:
Obstacles. Renewable and Sustainable Energy Reviews, 14(9), (2010) 3156-3163.
43) Hogan, W., Lindovska, M., Mann, J. and Pope, S., Embracing Merchant Transmission
Investment. October 15, 2018. Available at
https://sites.hks.harvard.edu/fs/whogan/Hogan_Lindovska_Mann_Pope_101518.pdf
44) Hogan, W., Rosellón, J. and Vogelsang, I. "Toward a combined merchant-regulatory
mechanism for electricity transmission expansion." Journal of Regulatory Economics 38, no. 2
(2010): 113-143.
45) Hojčková, K., Sandén, B. and H. Ahlborg. "Three electricity futures: Monitoring the emergence
of alternative system architectures." Futures (2017).
46) Holmes, I., Gaventa, J., Mabey, N. and Tomlinson, S., February 2012. Financing the
Decarbonisation of European Infrastructure. E3G.
47) Höschle, H., Le Cadre, H. and Belmans, R., 2018. Inefficiencies caused by non-harmonized
capacity mechanisms in an interconnected electricity market. Sustainable Energy, Grids and
Networks. 13: 29-41.
48) Hu, H., Shi, X., Wei, T. and Rong, J., 2017, November. Hellenic transnational interconnection:
Integrated scenario-based social-economic analysis. In 2017 IEEE Conference on Energy
Internet and Energy System Integration (EI2) (pp. 1-5). IEEE.
49) Huang, D., and van Hertem, D., 2018. Cross-Border Electricity Transmission Network
Investment: Perspective and Risk Framework of Third Party Investors. Energies. 11 (9): 1-13.
50) Huang, D., de Vos, K., van Hertem, D., Olmos, L., Rivier, M., van der Welle, A. and Sijm, J., 2016.
Mind the gap: Challenges and policy options for cross-border transmission network
investments. Paper presented at 13th International Conference on the European Energy
Market (EEM), Institute of Electrical and Electronics Engineers (IEEE).
51) Huter, M., Polfliet, A., Cummins-Tripodi, P. et al., May 2018. Revolving door and the fossil fuel
industry. Report for the Greens group in the European Parliament.
52) Johannesson Linden, A., Kalantzis, F., Maincent, E. and Pienkowski, J., 2014 Electricity Tariff
Deficit: Temporary or Permanent Problem in the EU?. Economic Papers 534
53) Jones, A., 2015. Perceived barriers and policy solutions in clean energy infrastructure
investment. Journal of Cleaner Production. 104: 297-304.
54) Kapff, L. and Pelkmans, J., 2010. Interconnector Investment for a Well-functioning Internal
Market: What EU regime of regulatory incentives? Bruges: College of Europe Department of
European Economic Studies, Bruges European Economic Research (BEER) Papers, n° 18
55) Konstantelos, I., Pudjianto, D., Strbac, G., De Decker, J., Joseph, P., Flament, A., Kreutzkamp,
P., Genoese, F., Rehfeldt, L., Wallasch, A., Gerdes, G., Jafar, M., Yang Y., Tidemand, N., Jansen,
J., Nieuwenhout, F., van der Welle, A., Veum, K., 2017, Integrated North Sea grids: The costs,
the benefits and their distribution between countries. Energy Policy. 101: 28-41.
56) Laws, Nicholas D., Brenden P. Epps, Steven O. Peterson, Mark S. Laser, and G. Kamau Wanjiru.
"On the utility death spiral and the impact of utility rate structures on the adoption of
residential solar photovoltaics and energy storage." Applied Energy. 185 (2017): 627-641.
57) Loureiro, M., Claro, J. and Fischbeck, P. "Coordinating cross-border electricity interconnection
investments and trade in market coupled regions." International Journal of Electrical Power &
Energy Systems 104 (2019): pp.194-204
58) Makovšek, D. and Veryard, D., February 2016. The Regulatory Asset Base and Project Finance
Models: An Analysis of Incentives for Efficiency. Paris: OECD International Transport Forum
Discussion Paper 1.
59) Marten, A.-K., Akmatov, V., Bentzon Sørensen, T., Stornowski, R., Westermann, D. and
Brosinsky, C., October 2018. KriegersFlak-combined grid solution: coordinated cross-border
control of a meshed HVAC/HVDC offshore wind power grid. Institution of Engineering and
Technology Power Generation. 12 (13): 1493 – 1499.
60) Mastropietro, P., Rodilla, P. and Batlle, C., 2015. National capacity mechanisms in the
European internal energy market: Opening the doors to neighbours. Energy Policy. 82: 38-47.
61) Matschoss, P., Benjamin Bayer, Heiko Thomas, and Adela Marian, 2019. "The German
incentive regulation and its practical impact on the grid integration of renewable energy
systems." Renewable Energy. 134: 727-738.
62) Mazzucato, M. and G. Semieniuk, G., 2017. Financing renewable energy: who is financing what
and why it matters. Technological Forecast and Societal Change. 127: 8-22.
63) Mekonnen, M., Huang, D. and de Vos, K., 2016. “Governance Models for Future Grids”. In van
Hertem, D., Gomis-Bellmunt, O. and Liang, J. (eds), HVDC Grids: For Offshore and Supergrid of
the Future. Hoboken, NJ: Wiley: 193-213.
64) Meeus, L., 2014. Offshore grids for renewables: do we need a particular regulatory
framework? Florence: European University Institute Robert Schuman Centre for Advanced
Studies. Florence School of Regulation Working Paper, No. 24.
65) Meeus, L. and Keyaerts, N., February 2015. First series of cross-border cost allocation
decisions for projects of common interest: main lessons learned. Florence: European
University Institute Robert Schuman Centre for Advanced Studies Florence School of
Regulation, Policy Brief.
66) Meyer, R. and Gore, O., 2015. Cross-border effects of capacity mechanisms: Do uncoordinated
market design changes contradict the goals of the European market integration? Energy
Economics, 51: 9-20.
67) Mulder, M., 2018. Merchant investments in interconnections in the European electricity
market: the AQUIND case. (CEER Policy Paper; No. 4). Groningen: Centre for Energy Economics
Research (CEER), University of Groningen.
68) Nelson, D. and Pierpont, B., March 2013. The Challenge of Institutional Investment in
Renewable Energy, Climate Policy Initiative Report.
69) Neuhoff, K., Boyd, R. and Glachant, J.-M., 2012. European Electricity Infrastructure: Planning,
Regulation, and Financing. Workshop report, Berlin: Climate Policy Initiative & Florence:
European University Institute School of Regulation.
70) de Nooij, M., 2011, Social cost-benefit analysis of electricity interconnector investment: A
critical appraisal. Energy Policy. 39: 3096-3105.
71) van Nuffel, L., Rademaekers, K., Yearwood, J., Graichen, V., López, M., Martin, J., Ludig, S. and
Marias, F. European Energy Industry Investments. Study for the European Parliament’s
Industry, Research and Energy (ITRE) Committee. Brussels: February 2017.
72) Odenberger, M., Unger, T. and Johnsson, F., May 08, 2015. Investment Requirements in the
EU electricity sector up to 2050. Division of Energy Technology. Chalmers University of
Technology, Göteborg.
73) OECD, 2015. Mapping channels to mobilise institutional investment in sustainable energy.
OECD Report to G20 finance ministers and central bank governors.
74) Pape, M., January 2019. European Parliament Briefing “EU Legislation in Progress - 2021-2027
MFF. Connecting Europe Facility 2021-2027- Financing key EU infrastructure network”,
European Parliamentary Research Service.
75) Pierri, E., Binder, O., Hemdan, N., and Kurrat, K., 2017. Challenges and opportunities for a
European HVDC grid. Renewable and Sustainable Energy Reviews 70: 427-456.
76) Poudineh, R. and Rubino, A., 2016. Business model for cross-border interconnections in the
Mediterranean basin. Oxford Institute for Energy Studies Working Paper, vol. 19.
77) Puka, L., and Szulecki, K., 2014. The politics and economics of cross-border electricity
infrastructure: A framework for analysis. Energy Research & Social Science 4: 124-134.
78) PriceWaterhouseCooper, Ad-hoc audit of the Marguerite Fund, 2014.
79) Rivron, G., 7 April 2016. Financing energy infrastructure with the Marguerite Fund.
Presentation at the 2016 CEF Energy Info Day.
80) Rubino, A. and Cuomo, M., 2015. A regulatory assessment of the Electricity Merchant
Transmission Investment in EU. Energy Policy. 85: 464-474.
81) Sanchis, G., November 2015. Europe’s future secure and sustainable electricity infrastructure:
e-Highway2050 project results.
82) Schill, W.-P., Egerer, J. and Rosellón, J., 2015. Testing regulatory regimes for power
transmission expansion with fluctuating demand and wind generation. Journal of Regulatory
Economics. 47 (1): 1-28.
83) Schmidt, P. and Lilliestam, J., 2015. Reducing or fostering public opposition? A critical
reflection on the neutrality of pan-European cost–benefit analysis in electricity transmission
planning. Energy Research & Social Science. 10: 114-122.
84) Schmitt, T., 2018. (Why) did Desertec fail? An interim analysis of a large-scale renewable
energy infrastructure project from a Social Studies of Technology perspective. Local
Environment, 23(7): 747-776.
85) Scheibe, A., 2018. Utilization of Scenarios in European Electricity Policy: The Ten-Year Network
Development Plan. Oxford Institute for Energy Studies Paper: EL 32, University of Oxford,
Oxford.
86) Schwieters, Norbert (ed). The road ahead: Gaining momentum from energy transformation.
Düsseldorf: PriceWaterhouseCooper, 2014.
https://www.pwc.com/gx/en/utilities/publications/assets/pwc-the-road-ahead.pdf
87) Silva, V., Zulueta, M.L.B., Wang, Y., Fourment, P., Hinchliffe, T., Burtin, A. and Gatti-Bono, C.,
June 2017. Anticipating Some of the Challenges and Solutions for 60% Renewable Energy
Sources in the European Electricity System. In Forecasting and Risk Management for
Renewable Energy, pp. 169-184.
88) Sovacool, B., Gilbert, A., and Nugent, D., 2014. An international comparative assessment of
construction cost overruns for electricity infrastructure. Energy Research & Social Science. 3:
152-160.
89) Spiecker, S., Vogel, P., Weber, C., 2013. Evaluating interconnector investments in the north
European electricity system considering fluctuating wind power penetration. Energy
Economics. 37: 114-127
90) Sunila, K., Bergaentzlé, C., Martin, B. and Ekroos, A., 2019. A supra-national TSO to enhance
offshore wind power development in the Baltic Sea? A legal and regulatory analysis. Energy
Policy, 128: 775-782.
91) Szydło, M., 2015. How to reconcile national support for renewable energy with internal
market obligations? The task for the EU legislature after Ålands Vindkraft and Essent. Common
Market Law Review. 52 (2): pp.489-510.
92) Tagliapietra, S., 2017. Energy Relations in the Euro-Mediterranean. Palgrave McMillan.
93) Tennbakk, B., Capros, P., Höschle, H., Jenssen, Å, Wolst, J., Zampara, M., Framework for crossborder participation in capacity mechanisms. Report to the European Commission, December
2016.
94) UK House of Commons Environmental Audit Committee, Green Finance, Twelfth Report of
Session 2013-14
95) Vasilakos, N. and Sikow-Magny, C., June 2018. Enhancing the public acceptance of crossborder electricity interconnection projects: a crucial step in the EU energy transition process.
Florence: Florence School of Regulation Robert Schuman Centre for Advanced Studies Policy
Brief.
96) Williams, R., Eichler, L., Gottmann, N., Förster, H. and Siemons, A. Energy and the Multiannual
Financial Framework. Report for the European Parliament’s ITRE Committee, February 2018.
97) Zakeri, B., Virasjoki, V., Syri, S., Connolly, D., Mathiesen, B.V. and Welsch, M., 2016. Impact of
Germany's energy transition on the Nordic power market–a market-based multi-region
energy system model. Energy. 115: 1640-1662.
98) Zafirakis, D., Chalvatzis, K.J. and Baiocchi, G., 2015. Embodied CO2 emissions and cross-border
electricity trade in Europe: Rebalancing burden sharing with energy storage. Applied Energy.
143: 283-300.