International Journal of Mechanical Dynamics & Analysis
Vol. 1: Issue 2
www.journalspub.com
Claim Simulation: A Case Study in Piping Projects
Saeed Raeisi, Morteza Bagherpour*
Department of Industrial Engineering, Iran University of Science and Technology, Iran
Abstract
Claims management is one of the most important challenges in mega projects and normally
included with many financial losses. Effects of probabilistic claims clearly state a need for a
comprehensive model to analyze claim risks in projects. In the present research, list of
frequent claims are identified in a piping project (from contractor point of view). Then based
on risk types, probabilistic claims are evaluated by questionnaire aimed at calculation of
probability percentage and also probability of success. The questionnaires were distributed
among experienced managers active in oil and gas piping project. In order to find out
reliability of the questionnaire, statistical test was successfully applied. Result of the present
study is to quantify claims in implementation phase of piping projects and finally by
analyzing cost effects and running claim simulation, practical and useful outcomes including
impact of claims on cost success rate of the project successfully obtained.
Keywords: claim, construction management, modeling, Monte-Carlo, risk management
*Corresponding Author
E-mail:
[email protected]
INTRODUCTION
Change has normally has significant
effects on the performance of a
construction project. Researches relevant
to quantitative impact are limited, incompleted,
and
in
some
cases
[1–8]
questionable.
Claim management is somehow similar to
risk management procedure and consists of
the following four processes:
(1) Claim Identification
(2) Claim Quantification
(3) Claim Prevention
(4) Claim Resolution.[14]
Significant numbers of disputes arising
from construction contracts. Even with
understanding of contract clauses and
considering risk-allocation regimes, claims
willing to present some problems if they
are not strongly managed in practice. [9–22]
Specifically, simulation models are
established to estimate the cost of the
operation as planned by the contractor at
bidding stage and to evaluate operational
costs. [1] Here, reliable prediction of
construction duration and consequently
budget control is consolidated in decision
making process and is an essential part of
a successful management. [3]
Management of claim in construction
projects is one of the important challenges
maybe happened with contractors.
Nowadays, due to high competition,
construction projects normally become at
risk due to a several risk factors which will
lead to extension of time and cost. [11]
THEORETICAL BACKGROUND
Risk Management
In this research, definition of the process
risk management as previously presented
by the Project Management Institute is
IJMDA (2015) 9–22 © JournalsPub 2015. All Rights Reserved
Page 9
Claim Simulation
Raeisi and Bagherpour
illustrated as: “the Project Risk
Management consists of the processes of
planning, identification, qualitative and
quantitative analysis, risk response
planning, and monitoring on a project”. [15]
The risk management loop according to
Figure 1 is a guideline for establishment of
a risk management system.
Phase 1
Identification
Phase 4
Phase 2
Monitoring
Analysis
Phase 3
Evaluation
Fig. 1. Schematic Risk Management Circle According to Ref. [20]
When risk identification and registration
completed, a probability of occurrence and
consequence are assigned to each task.
This assignment can be done through a
quantitative assessment or a qualitative
one or a mix combination of both. [19]
Monte-Carlo Simulation
Managerial decision analysis normally
incorporates probability distributions of
cost and schedule estimates, often using
Monte-Carlo simulation to expand cost
and schedule models. [23]
Monte-Carlo simulations incorporate
probabilistic conditions to provide the total
project cost and delivery date according to
the fitted distributions. [21] Main advantage
of using Monte-Carlo simulation is
applying a powerful model for quantifying
of the potential risk factors.
the various claims considered during a
project life cycle. [4]
Since there is no a unique terminology of
this matter in the literature, a claim can be
referred to “a request for compensation
and damages happened by the other
party”.[18]
“Claim” may be also described as
investigation of consideration or change by
one of the parties involved in the project
process. [17]
A claim happens when one party to the
contract has suffered a detriment by the
other party. [10]
Claim
Management
describes
the
processes required to eliminate, prevent or
reduction of construction claims when they
are expected to occur.
The Monte-Carlo simulation enables a
manager to quantify project reserves by
incorporating risk events during the project
life cycle. [12]
Claim management is an important process
in mega construction projects. [14]
Claim and Claim Management
Claim was initially proposed in 1978 as a
risk and probability and consequences of
Construction Claims
Construction claim can be named as
“request by a construction contractor for
compensation over and above the agreedupon contract amount for additional works
IJMDA (2015) 9–22 © JournalsPub 2015. All Rights Reserved
Page 10
International Journal of Mechanical Dynamics & Analysis
Vol. 1: Issue 2
www.journalspub.com
or damages probably resulting from items
were not included in the initial contract”.[2]
issues, weather conditions, change and
time extension assessment. [24]
Construction
claims
and
disputes
occurring in both public and private
sectors, and in projects. In fact, no project
can be considered isolated from a potential
claim. Also much kind of claims can lead
to financial damages.[5] Construction
claims are observed by many participants
as an unpleasant event in a project.[6]
Generally claims are considered a common
part in a construction project and may be
happened due to several reasons. On
schedule accomplishing of a project is
sometimes a difficult task to do in
uncertain, construction projects due to the
risks may be happened. [10]
On the other hand, the data collection was
performed to investigate the reasons
related to construction delay and overruns:
Contract planned duration
Actual completion date
Design changes
Disputes
Extra works
Delays
Conflicts observed between the
drawings and specifications
Time extensions
Late delivery of materials and
equipment[3]
Claims may arise on a construction project
due to number of reasons. Some wellknown ones include as given below:
Creep in scope of work (changes,
extras and errors)
Inadequate bid/tender information
Faulty and/or lately supply of
equipment and materials by owner
Low quality of drawings and/or
specifications
Insufficient time through biding
analysis
Interruptions through proceeding of the
operations due to lack of coordination,
design information, equipment or, etc.
Blocked work
Re-schedule of works ordered by
owner
Unbalanced bidding[9]
Claims of Piping Projects
Probabilistic claims in piping construction
projects may include, but not limited to:
In addition, based on investigations in 91
projects, it is summarized the most
influencing factors of claims are unclear
documentations,
weak
instructions,
variations
initiated
by
the
employer/engineer, measurement related
Material control: The shortage documents
due to lack of materials will be a cause of
loss for contractor or employer. Thus
presence of Non-Issues (NIS) documents
implies loss claims by contractor or
employer.
Organizational communications: Some
examples of communications among
groups in an executive project are include,
“Agendas for meeting” and “Technical
letters” and coordination procedures.
Documents and piping plans: Isometric
drawing is the most executive type of
piping plans. In case of any change
happens in any part of the plan, a new
revision will be issued and the last plan
will be voided. Change in any executive
stage could affect the cost and schedule of
project and will lead to claims (Figure
2).[16]
IJMDA (2015) 9–22 © JournalsPub 2015. All Rights Reserved
Page 11
Claim Simulation
Raeisi and Bagherpour
Fig. 2. Typical Isometric Drawing for Piping Operations [Author].
To find out the importance or magnitude
of a cause from a set of causes for
occurrence of claims, two factors entitled
“probability of occurrence” as well as
“chance of claim occurrence” were
examined and they evaluated the most
probabilistic causes of claims.
Thus, a questionnaire including 15
questions related to probabilistic claims in
oil and gas piping construction were
prepared. Contents of questions in
questionnaire have been designed by
experts with more than 10 years of
experience in this field.
According to 5-fold Likert scale (very low,
low, moderate, high, very high) rate of
each index for each claim was rolled up
and scored. [7] The statistical population’s
size was selected based on comments
made by project managers, piping
managers, planning and project control
managers, contract managers with high
executive experiences working in gas and
oil projects for several companies.
Selection of people was performed based
on communications and their involvements
in projects especially in piping and their
individual experiences and effective views
of oil and gas industry. Finally, about 20
answered questionnaires were collected for
claim analysis and monitoring stage.
Verification and Validation
In the present study, to check the
validation for questions of questionnaires,
Research Gap
In general, so far, Monte-Carlo simulation
has been presented under category of risk
management.
In claim management most studies
conducted about the roots and causes,
prevention, and settlement of claims,
however, claims management and
simulation by Monte-Carlo to obtain
project success rate have not been
discussed in the literature.
Main approach of this research is to
identify and study potential claims which
are discussed in oil and gas piping
construction projects and by prioritization
and ranking of the claims in a specialized
form, quantification of claims by MonteCarlo simulation is analyzed which never
been focused by the other researchers in
the literature.
SOLUTION PROCEDURE AND
METHODOLOGY
Methodology
The present research is an applied research
which attempts to examine the claims and
provides solutions for claim management
in oil, gas, and petrochemical construction
projects.
Two factors entitled “probability” and
“impact” had been evaluated by
questionnaire and required data were
collected.
IJMDA (2015) 9–22 © JournalsPub 2015. All Rights Reserved
Page 12
International Journal of Mechanical Dynamics & Analysis
Vol. 1: Issue 2
www.journalspub.com
present and past projects, potential claims
of the projects were evaluated.
The Cronbach’s alpha coefficient for
questions about probability was 0.766 and
for questions was 0.709 which are
acceptable measurements (Figure 3).
surface and content of questionnaire were
examined by independent interviews
conducted by 10 experts whom
experienced in the field of construction
projects in oil and gas industry and finally
by comparison among conditions of the
Modeling
Fig. 3. The Modeling Analysis of Claim [Author].
Deterministic Planning of Piping
Construction Project
First stage in project planning is to include
claim through deterministic planning. It is
implemented.
(WBS) for oil and gas piping construction
project is prepared and reviewed by the
relevant
experts.
The
dependency
relationships and resource assignment
should be then applied in order to finalize
the deterministic plan.
Before getting started with the computer
package, the Work Breakdown Structure
IJMDA (2015) 9–22 © JournalsPub 2015. All Rights Reserved
Page 13
Claim Simulation
Risk Planning for Claims in Piping
Construction Project
In a project plan along with risk analysis,
different outcomes and ways could be
examined for the given project. In this
project, by analyzing claims, different
outcomes and ways to complete the project
are examined and impacts of claim risks
on the project success are determined.
Risk Analysis for Cost and Time of
Project
Through running risk analysis, three
optimistic
(minimum),
the
most
probabilistic, and pessimistic (maximum)
scenarios have to be considered instead of
incorporating a deterministic cost and time
analysis. By applying project claim
analysis, more realistic scheduling is
obtained. Before a cost is allocated with a
risk, a resource should be defined so that
the cost could be allocated. Cost allocation
to an activity is the best cost estimation
approach for the activity definition. In
piping construction projects, once resource
for an activity is defined Cost, planned
cost for any activity is determined and then
triangular distribution has to be used to
estimate maximum and minimum costs for
any individual activity. For this project,
triangular distribution is used for cost risk
of activity and minimum and maximum
costs are assumed to be 90 and 110% of
the estimated cost for an activity,
respectively, according to comments made
by experts (Figure 4).
Raeisi and Bagherpour
Claims Identification and Screening
Process
Claims in piping construction sector were
identified by incorporating 10 experienced
managers in piping construction projects
for gas and oil industry at management
level by a check-list method. A check-list
of potential claims were prepared for
running a comparison between identified
potential claims in current and the projects
completed in the past. Outcome of this
stage was a list of potential claims for the
present project with a certain range of
influencing factors. Thus the claims
effective on objectives of the project in
EPC contracts of gas and oil industry
piping are identified, determined, and truly
documented.
Preparation and Distribution of
Questionnaire
To find the most important claims, two
factors “probability of occurrence” and
“claim’s chance of success” (intensity of
claim) were examined and evaluated by
questionnaire; descriptive terms for both
factors in questionnaire included: very
low, low, moderate, high, and very high
(Table 1).
Scoring the Claims
Variables used in scoring include:
(i) Claim’s probability of occurrence (P)
(ii) Claim’s impact or chance of
occurrence (I)
(iii)Claim’s degree of risk (C)
Table 1. Impact and Probability Scoring
Factors.
Natural language expression
Very low (VL)
Low (L)
Medium (M)
High(H)
Very high (VH)
Fig. 4. Triangular Distribution of
Resources. [13]
Numeric score
1
3
5
7
9
To rank and classify claim risks, once
average probability and impact of claim's
risk is calculated, by probability of
occurrence (P) multiplied by impact (I),
claim's degree of risk (C) is obtained:
IJMDA (2015) 9–22 © JournalsPub 2015. All Rights Reserved
Page 14
International Journal of Mechanical Dynamics & Analysis
Vol. 1: Issue 2
www.journalspub.com
C P*I
1–1
Registration of Claims on Computer
Package
According to prioritization of claims, 6
important claims that are likely to have the
highest effect on the project have entered
in the software.
Registration of Quantitative Information
of Claim
Quantitative values are entered to the
program. According to the data entry of
quantitative values for probability and
impact of claims, those could be scored
and finally ranked. Since it is possible that
available resources in organization are not
enough in order to deal with all claims
presented in the project, ranking the risks
based on the obtained scores could be very
helpful to identify important claims of the
project. Given the information about
probability and impacts of claims are
collected as a questionnaire and are made
quantitative and accurate by ranking and
scoring, registration of information on the
software is performed through a
quantitative basis.
A risk could have positive or negative
effects on the project. If it has a positive
effect on the project, it is called an
opportunity and if it has a negative effect
on the project, it is called a threat. Since
the claim could be either a positive risk or
a negative one, we consider opinions of
employer or contractor in claim risk
analysis.
Mapping the Claims on Project Activities
Claims could be mapped to an individual
activity in the project to run an integrate
analysis. Effect of claim on costs of
activities is found quantitatively by
questionnaire and based on the claim
scores (Table 2).
Table 2. Claims Quantitative Analysis on Activities. [13]
Preparation of Risk Matrix of Claim
Risk matrix allows evaluation of the
linguistic terms (very low, low, moderate,
etc.) which could improve quality of data
and ranking process of claims and it could
be used in other projects.
Once questionnaires collected, risk ranking
matrix may specify position of each claim
based on probability and its effect on
Probability-Impact Matrix (PI-Matrix). It
indicates importance of claims properly
(Table 3).
Table 3. Claims PI Matrix
IJMDA (2015) 9–22 © JournalsPub 2015. All Rights Reserved
Page 15
Claim Simulation
Raeisi and Bagherpour
The above figure indicates the importance
of the risks.
MONTE-CARLO SIMULATION FOR
CLAIMS OF PIPING
CONSTRUCTION PROJECT
An analysis includes a number of
repetitions and in each epoch, cost for each
activity changes according to the
distribution assigned. After the end of a
repetition when all costs revised, cost for
project completion is then registered. Each
repetition simulates the state a project
could be implemented in the real world by
Monte-Carlo method (Figure 5).
Fig. 5. Project Schedule Included Claims. [13]
Simulation in Uncertainty State
First, a distribution is applied in
scheduling some activities. In this project
triangular distribution is used to schedule
activities. Doing risk analysis by MonteCarlo simulation with 1000 times
repetition of simulation graphs in an
uncertainty state or before applying claim,
the schedules of activities are registered.
Then triangular distribution is selected and
applied for costs of resources. By doing
risk analysis of graphs before applying
claim, cost of the project can be registered.
Simulation of Claims
Simulation of claims and impact of claim
on the affected activities and performing
risk analysis is registered by implementing
Monte-Carlo technique for simulation
graphs at a state of claims.
Quantitative Analysis of Claim
After running Monte-Carlo simulation
through cost analysis of an uncertainty
state both before and after application of
claim (post-mitigation), the time schedule
will yield applied reports and graphs.
Distribution graphs could facilitate reply to
the following questions by application of
probabilistic project claims:
(i) What is the probability the project is
finished with a certain cost?
(ii) What is the probability a specific
activity completed with a certain cost?
(iii)How much does it cost to complete
95% of the project?
IJMDA (2015) 9–22 © JournalsPub 2015. All Rights Reserved
Page 16
International Journal of Mechanical Dynamics & Analysis
Vol. 1: Issue 2
www.journalspub.com
(iv) What activity could have more cost
sensitivity on the project cost?
(v) What is claim impact on rate of project
success?
RESULTS AND ANALYSIS OF
CLAIMS FOR PIPING
CONSTRUCTION PROJECT
Fifteen claims related to the most
important actionable claims in piping
construction projects for gas and oil
industry are given in appendix 1.
Now the claims could be examined and the
most probabilistic and effective causes
could be found and also considering index
of claim’s degree (combined effect of
probability of occurrence and impact), the
most important factors could be found.
Ranking the Most Important Claims of
Piping Construction Project
By ranking of associated risks, we could
prepare preferences for simulation and
specify the most important and effective
claims.
Since scores of claims are
determined in terms of probability and risk
impact, the ranking indicates the
importance of risks as compared to each
other properly. The most important claims
are given in Table 3 by preference
(Table 4).
Analysis of Claims’ Results
Any claim in the plan has a probability of
occurrence which is applied after
application of claim. If a claim is
considered a negative risk for a contractor,
the claim influencing the activities by
increasing or reducing costs. Outcomes of
an analysis model should be able to answer
questions proposed by decision makers
and managers.
Cost Distributions
Process of repetition for any activity
repeats several times and any repetition
simulates the state which could be faced
by a project and establishes a cost plan for
a project. After completion of analysis,
cost for any repetition is displayed on a
graph which illustrates distribution of
project cost (Figure 6).
Table 4. Piping Construction Claims.
Rank
Claim event
Factor
Average
score
Score
(I*P)100
1
2
Contractors’ claims, in case of issuance of material issue voucher (MIV)
and delay in delivery of material or non-issue (NIS)
Requirements for piping operations to be hold or not met
Probability
7.6
Impact
7.3
Probability
7.2
Impact
7.1
55.48
51.12
3
Client delays in delivering isometric drawings
Probability
6.6
42.9
4
Discrepancies and shortcomings in contract terms
Impact
Probability
6.5
6.7
42.88
5
TQ (Technical Query) due to failure, inadequacy and deficiencies
information plan
Impact
Probability
6.4
6.2
36.58
6
Delay in piping invoices payment
Impact
Probability
5.9
5.8
34.22
Impact
5.9
IJMDA (2015) 9–22 © JournalsPub 2015. All Rights Reserved
Page 17
Claim Simulation
Raeisi and Bagherpour
Fig. 6. Cost Distribution of Piping Construction Project in Uncertain Conditions. [13]
Outcomes of Monte-Carlo simulation in
claim risk analysis of piping construction
projects indicate frequencies of different
values due to occurrence of various states
of uncertainty. As can be seen from the
Figure 6, with a 90% confidence interval,
total cost of piping construction project is
$17,424,567 and the estimated probability
for completing the estimated cost equals to
$16,460,200 is only 51%.
Implementing claim risk analysis by the
Fig. 7. Cost Distribution of Piping Construction Project After Application of Claims (After
Preventive Action). [13]
application of claims after taking a
preventive (post-mitigation) action, below
distribution graph is registered. As could
be seen in Figure 7, there is 43%
probability the project is completed with
the initial estimation $16,460,200. Also,
this figure shows with an 80% confidence
the final cost of project could be
considered $17,185,148.
IJMDA (2015) 9–22 © JournalsPub 2015. All Rights Reserved
Page 18
International Journal of Mechanical Dynamics & Analysis
Vol. 1: Issue 2
www.journalspub.com
Table 4 shows statistical values including
minimum,
maximum,
mean,
90%
confidence level, and probability of
occurrence, and project costs for both
states before and after application of claim
(Table 5).
Table 5. Comparison of Costs Before and After Application of Claim.
Project cost with uncertainty
taken into account before
application of claim($)
Project cost with uncertainty
taken into account after
application of claim($)
Deterministic (%)
Minimum
Mean
Maximum
90% Confidence level
51
14,827,485
16,465,689
18,443,264
17,424,568
43
14,828,116
16,583,807
18,467,790
17,565,661
Analysis of Cost Distribution for Piping
Construction Project
If states before and after application of
claim are defined, two states could be
compared after performing the analysis.
Thus, with uncertainty and claim risk into
consideration, estimation rate of total
project cost with a 90% risk will be about
$141.094 more than the rate before
application of claim. Difference between
probability of final project cost before and
after application of claim indicates a more
accurate estimation of project cost given
portions of claims for project; impact of
claim on project success rate in this project
is 8%. In order to discover the importance
and relevancy of the activities to be further
performed, cost impact for an activity on
project budget has to be evaluated.
Sensitivity analysis here is a correlation
maybe occurred between cost of the
activity and project total costs. This index
indicates impact of cost for an activity on
cost and completion of the other activities
or whole project. Claims are graded in
terms of relative sensitivity on final cost of
the project. In this case, claims with the
highest degree could be focused.
The activity with highest cost sensitivity
may have more effect on increasing
project cost. Figure 8 illustrates rate of
sensitivity based on the correlation
between costs of the first 6 activities and
total cost of piping construction project.
Fig. 8. Analysis of Cost Sensitivity for Piping Construction Project. [13]
The graph shown in Figure 8 indicates
sensitivity analysis in percentage. As
shown, the correlation between cost of
welding activity and cost for project
completion is 95%. Therefore, claims
resulting from occurrence of uncertainty
associated with estimated costs of
activities with high percentage require
more accurate evaluations. Furthermore, it
is still possible to have a new
concentration on the sensitive items as
above detected.
IJMDA (2015) 9–22 © JournalsPub 2015. All Rights Reserved
Page 19
Claim Simulation
This study has important achievements for
oil and gas piping construction project and
the important results include:
(1) Identification of actionable claims in
piping construction projects and also
ranking and prioritization of the most
important claims
Raeisi and Bagherpour
(2) By simulation of claims,
project success rate is 8%
cost overrun
(3) Understanding
cost
indicates impact of cost of
on the total cost
impact on
for project
sensitivity
an activity
APPENDIX
Piping Construction Claims
Row
Claim event
1
Discrepancies and shortcomings in contract terms
2
Requirements for piping operations to be hold or
not met
3
Claims related to issuance of different permits
4
Contractors' claims, in case of issuance of material
issue voucher (MIV) and delay in delivery of
material or non-issue (NIS)
5
Client delays in delivering isometric drawings
6
7
8
9
Changes in drawings and isometric at different
times (revision)
Contractor claims related to the FIN(Field
Inspection Notification) various stages
Changes in project specification and ITP(Inspection
and Test Plan)
TQ (Technical Query) due to failure, inadequacy
and deficiencies information plan
10
Interferences with other contractors
11
Miscellaneous delay factors and costs of piping
project
12
Absence of executive supervisor Client
13
Technical writing letters and correspondence in
relation to the executive affairs
14
Delay in piping invoices payment
15
Test package and testing operations
CONCLUSION REMARK
This paper, identifying common claims in
oil and gas piping construction contract,
was
performed
by
questionnaire
distributed among senior experienced
managers and experts in this industry.
Once the most important claims were
determined by quantifying the claims and
by applying outcome of Monte-Carlo
simulation, project success rates before
and after applying the claim were found
and difference between the obtained values
indicated impact percentage of claim risk
Probability
Impact
Probability
Impact
Probability
Impact
Probability
Average
score
6.7
6.4
7.2
7.1
3.4
3.4
7.6
Impact
7.3
Probability
Impact
Probability
Impact
Probability
Impact
Probability
Impact
Probability
Impact
Probability
Impact
Probability
Impact
Probability
Impact
Probability
Impact
Probability
Impact
Probability
Impact
6.6
6.5
5.7
5.9
2.8
2.7
4.5
4
6.2
5.9
5.7
5.7
3.4
3.3
3.1
3.2
5.7
5.2
5.8
5.9
4.7
4.4
Factor
Score
100(I*P)
I&P
average
Rank
42.88
6.55
4
51.12
7.15
2
11.56
3.4
12
55.48
7.45
1
42.9
6.55
3
33.63
5.8
7
7.56
2.75
15
18
4.25
11
36.58
6.05
5
32.49
5.7
8
11.22
3.35
13
9.92
3.15
14
29.64
5.45
9
34.22
5.85
6
20.68
4.55
10
in
piping
construction
projects.
Furthermore, cost for project completion
with claim taken into account is one of the
other results of Monte-Carlo simulation
study. Research results indicate the values
obtained by probabilistic approach
indicates a range of numbers as a result of
cost estimation are close to reality. Finally,
using this information, the project could be
estimated and evaluated more accurately a
proper plan may be adopted to reduce
project cost. Similarly, claims affecting
aims of project are identified and
IJMDA (2015) 9–22 © JournalsPub 2015. All Rights Reserved
Page 20
International Journal of Mechanical Dynamics & Analysis
Vol. 1: Issue 2
www.journalspub.com
documented
judgments.
according
to
expert
Identifying common claims in gas and oil
piping construction project and also
application of outcome of Monte-Carlo
simulation for each claim of project
successfully applied and the obtained
results verified.
Further study can be made on applying
fuzzy modeling through project claim
management and combination of fuzzy–
simulation analysis also can be elaborated
through the case.
The authors have no funding and conflict
of interest.
REFERENCES
1. AbouRizk S., Dozzi P. Application of
computer simulation in resolving
construction disputes, J Constr Eng
Manage. 1993; 119(2): 355–73p.
2. Adrian J.J. Construction Claims: A
Quantitative Approach. Stipes Pub
Llc; 1993.
3. Al-Momani A.H. Construction delay: a
quantitative analysis, Int J Project
Manage. 2000; 18(1): 51–9p.
4. Bosche R.V. Identifying construction
claims, Trans Am Assoc Cost Eng.
1978; 320–9p.
5. Enshassi A., Sherif M., Said E.-G.
Problems associated with the process
of claim management in Palestine:
Contractors’ perspective, Eng Constr
Arch Manage. 2009; 16(1): 61–72p.
6. Ho S.P., Liang L.Y. Analytical model
for analyzing construction claims and
opportunistic bidding, J Constr Eng
Manage. 2004; 130(1): 94–104p.
7. Hwang C.-L., Yoon K. Multiple
Attribute Decision Making Methods
and Applications A State-of-the-Art
Survey. Springer Berlin Heidelberg;
1981.
8. Ibbs C.W. Quantitative impacts of
project change: size issues, J Constr
Eng Manage. 1997; 123(3): 308–11p.
9. Jergeas
G.F.,
Hartman
F.T.
Contractors’
construction‐claims
avoidance, J Constr Eng Manage.
1994; 120(3): 553–60p.
10. Kartam S. Generic methodology for
analyzing delay claims, J Constr Eng
Manage. 1999; 125(6): 409–19p.
11. Kululanga G., Kuotcha W., McCaffer
R., et al. Construction contractors'
claim process framework, J Constr
Eng Manage. 2001; 127(4): 309–14p.
12. Kwaka Y., Ingall L. Exploring Monte
Carlo simulation applications for
project management, Risk Manage.
2007; 44–57p.
13. Oracle, 2009, Pertmaster V 7.82 & V
8.0 Manual and Help.
14. PMI. Construction extension to the
PMBOK®
Guide.
Pennsylvania:
Project Management Institute, 2000.
15. PMI. A Guide to the Project
Management Body of Knowledge (
PMBOK® Guide ) (5th Edn.).
Pennsylvania: Project Management
Institute, 2013.
16. Sanati F. Piping Execution in
Industrial
Installations
Projects.
Tehran:
Jahad
Daneshgahi
Publications; 2006.
17. Scott K.L. The management of
contractual claims, Stud Contract
Claims. 1992; (14).
18. Simon M.S. Construction Contracts
and Claims. New York: McGraw-Hill;
1979.
19. Smith C.A. Integrated Scenario-Based
Methodology
for
Project
Risk
Management. University of Maryland,
2011.
20. Stempowski R. Risikomanagement–
Entwicklung von Bauprojekten. Graz:
Nausner
&
Nausner
Unternehmensberatung; 2002.
21. Stewart R.D. Cost Estimating. 2nd
Edn. Wiley-Interscience; 1991.
IJMDA (2015) 9–22 © JournalsPub 2015. All Rights Reserved
Page 21
Claim Simulation
22. Vidogah W., Ndekugri I. Improving
the management of claims on
construction contracts: consultant’s
perspective, J Manage Eng. 1998;
16(3): 363–72p.
23. Vose D. Risk Analysis: A Quantitative
Guide. John Wiley & Sons; 2008.
Raeisi and Bagherpour
24. Yogeswaran K., Kumaraswamy M.M.,
Miller D.R. Claims for extensions of
time in civil engineering projects,
Const Manage Econ. 1998; 16(3):
283–93p.
IJMDA (2015) 9–22 © JournalsPub 2015. All Rights Reserved
Page 22