http://dx.doi.org/10.5991/OPF.2014.40.0078
Water Reuse
Ryan R. Popko, PE, and Phillip J. Locke, PE, are
with McKim & Creed (www.mckimcreed.com),
Clearwater, Fla. Fred J. Greiner is with the city of
Palm Coast, Fla. (www.palmcoastgov.com).
Zero Liquid Discharge
Project Extends Potable
Water Supplies
Diminishing potable water supplies, increasing regulatory restraints, and
conservation initiatives have prompted utilities to evaluate and implement
the use of alternative water supply sources. One Florida utility implemented
a concentrate zero liquid discharge process to achieve water recovery
through concentrate treatment. BY RYAN R. POPKO, PHILLIP J. LOCKE, AND FRED J. GREINER
U
SING UNCONVENTIONAL
sources often requires
implementing new process
applications to meet potable
water treatment requirements and
demands. Effectively treating waste
streams can be an essential part of meeting
alternative water supply goals. Although
membrane treatments, specifically reverse
osmosis and nanofiltration, feature
significant benefits in treating water
to a consistently high level, managing
the treatment process by-product, or
concentrate, can be a challenge.
MEETING THE CHALLENGE
The city of Palm Coast, Fla., explored
methods to develop alternative water
supplies, recover and reuse water, and
reduce the utility’s environmental impact.
Because the city’s consumptive use permit limited source water supplies and
regulatory constraints required an alternative method of concentrate disposal, the
16 Opflow December 2014
city’s Water Treatment Plant (WTP) No. 2
membrane softening facility chose to treat
and recover its concentrate as an alternative water supply using a unique zero liquid discharge (ZLD) process.
The ZLD process currently treats
1.2 mgd of low-pressure reverse osmosis (RO) concentrate using lime/soda ash
softening, membrane filtration, and disinfection. The ZLD process allows the city
to treat and recover nearly 100 percent
of WTP-produced concentrate that previously had been discharged to a surface
water body. The ZLD process treats the
concentrate stream to a level at which,
when blended with the plant’s finished
water, complies with drinking water standards. The process increases the facility’s
capacity by 1.2 mgd without additional
source water supplies.
The ZLD process evolved after the
city’s most recent National Pollutant Discharge Elimination System concentrate
discharge permit renewal, as the US
2014 © American Water Works Association
Environmental Protection Agency
(USEPA) and Florida Department of Environmental Protection (FDEP) determined
the use of an extended mixing zone for
water quality compliance was no longer
feasible. The city then evaluated 12 alternative disposal methods of concentrate
based on treatability, feasibility, and economics. After bench-scale and pilot testing, it selected ZLD for its WTP No. 2. The
concentrate ZLD option provides for concentrate recovery as an alternative water
supply for potable use and for beneficial
reuse of solids removed from the concentrate stream. The local water management
district’s push for the use of alternative
water supplies was also a factor in ZLD
selection.
PROCESS DESIGN
Palm Coast WTP No. 2 has a permitted
capacity of 6.4 mgd, which includes 1.6
mgd of raw water bypass. The membrane softening system currently operates
www.awwa.org/opflow
PHOTOGRAPHS: CITY OF PALM COAST, FLA.
An aerial view of WTP No. 2 shows many of the facilities built to treat and recover
the plant’s concentrate as an alternative water supply using the ZLD process,
including (clockwise from top left) a sludge dewatering facility, a lime silo,
a post-treatment and ultrafiltration building, and solids contact clarifiers.
at approximately 80 percent recovery
and is designed to produce 4.8 mgd of
permeate, with a resultant 1.2-mgd flow
of concentrate. The ZLD treatment process uses the concentrate as its source
water supply, and the ZLD-treated water
is blended with the combined permeate
and raw water bypass water so the resulting blended water quality meets current
drinking water standards and city water
quality goals. Adding the ZLD process
increased WTP No. 2’s production capacity to 7.6 mgd (4.8 mgd permeate, 1.6mgd raw water bypass, and 1.2 mgd ZLD
treated water).
Primary components of the ZLD process include a softening system, sedimentation, an ultrafiltration (UF) feed system,
UF system components, a UF backwash/
cleaning system, a disinfection system, a
process recycle and recovery system, a
solids-handling system, a sludge dewatering system, process and yard piping,
electrical systems, and instrumentation
www.awwa.org/opflow
and control systems. The table on page
18 presents the water quality parameters used to design the concentrate ZLD
system.
As shown in the process flow diagram on page 19, the concentrate ZLD
process consists of softening by chemical
precipitation followed by UF to primarily
reduce carbonate and noncarbonate hardness as well as some total organic carbon
and color. Lime and soda ash are used
to precipitate carbonate and noncarbonate hardness in two solids contact clarifiers, and a polymer is added to enhance
settling. The pH of the softened water is
adjusted, and a scale inhibitor is added
before water is transferred to the UF feed
tank. The UF feed pumps transfer the softened water through automatic backwash
strainers and a pressurized vertical UF
system that removes most of the remaining suspended solids. The UF system
was designed to provide for 100 percent
treatment capacity when one of the
2014 © American Water Works Association
plant’s four trains is off-line for cleaning, maintenance, or repair. The UF elements are cleaned through chemically
enhanced backwash and clean-in-place
(CIP) operations.
The chemically enhanced backwash
uses sulfuric acid, sodium hydroxide,
or sodium hypochlorite. CIP operations
use citric acid, sodium hydroxide, or
sodium hypochlorite. The UF system is
housed in a pre-engineered metal building designed to accommodate additional
UF membranes and other components to
allow for a future expansion of the ZLD
process to 1.8 mgd. The UF filtrate then
is conveyed to the UF filtrate/backwash
tanks. The filtrate from the UF filtrate/
backwash tanks is disinfected before
blending with the combined permeate
and raw water bypass water directly
upstream of the existing ground storage tank.
In addition to the main ZLD process
stream, two additional process streams
December 2014 Opflow 17
Water Reuse
Water Quality Data and Goals
The ZLD treatment process uses the concentrate as its source water supply. The ZLD-treated water is blended with the combined permeate
and raw water bypass water so the resulting blended water quality meets current drinking water standards and city water quality goals.
RO Permeate
Raw Water
Bypass
RO
Concentrate
ZLD Treated Water
Goal
Total Blended Water
Goal*
Total Hardness (mg/L as CaCO3)
4.1
349
1,650
<155
100
Calcium Hardness (mg/L as
CaCO3)
2.7
321
1,470
<100
85
True Color
0
23
53
<65
<15
Total Dissolved
Solids (mg/L)
54
469
2,500
<2,320
<500
Iron (mg/L)
0.02
0.43
1.7
<1.25
<0.3
Chloride (mg/L)
11.1
115
600
<1,380
<250
Turbidity (NTU)
0.10
0.82
8.8
<0.40
<0.3
Water Quality Parameter
*Total Blended Water Goal meets or exceeds USEPA and FDEP drinking water requirements.
are associated with the concentrate ZLD
process: a solids stream and a recycle
stream. The system recovers 98.5 percent
of the concentrate, and the remaining 1.5
percent is lost through water contained
in the dewatered lime sludge and water
used in the CIP operations. To achieve
the required concentrate recovery, five
recycle/recovery streams combine in the
The UF elements are cleaned through
chemically enhanced backwash and
clean-in-place operations.
18 Opflow December 2014
equalization tank where they’re recycled
to the head of the ZLD process. The recycle streams include solids-laden softened
water from the UF feed tank, UF pretreatment automatic backwash strainer waste,
UF-neutralized chemically enhanced
backwash water, gravity sludge thickener
supernatant, and belt filter press filtrate.
The recovery and recirculation of the various streams within the concentrate ZLD
process are key to successful implementation. The ZLD system was designed to
produce lime sludge with approximately
50 percent dry solids.
Sludge removed from the solids contact clarifiers is transferred to a gravity
sludge thickener. Solids removed from
the gravity sludge thickener are conveyed to the solids-handling and dewatering system. Sludge is dewatered with
two belt filter presses, which allow for
100 percent redundancy. The dewatered
solids are hauled from WTP No. 2 by
the city’s contract hauler, and they’re
mixed with shell and sand for use as
road base.
The ZLD process is integrated into
WTP No. 2 so the overall plant operates as a single facility. The concentrate
ZLD system is located on the plant’s
site to minimize the site and carbon
2014 © American Water Works Association
footprints, reduce environmental
impacts, and allow for ease of operation and maintenance.
PROJECT CHALLENGES
Recycle Streams. One of the project’s
biggest challenges was handling all of
the recycle streams, which increase the
recovery to approximately 98.5 percent. Because of each stream’s varying volume, duration, and frequency,
an equalization tank with a capacity
of approximately 80,000 gallons was
designed and sized to provide ample
capacity for the flows. In addition to
providing the requisite storage for the
recycle flows, the equalization tank was
also fitted with a mixing system that
includes jet-type mixing eductors and
a pumping system to keep solids from
settling in the tank.
Three recycle pumps are included
for the equalization tank to transfer the
various recycle flows back to the head
of the ZLD process, directly upstream
of the solids contact clarifiers, where
the flows are mixed with the influent
concentrate. However, with the equalization tank’s fairly large capacity,
flow control of the recycle stream is
required to avoid surges and upsets to
www.awwa.org/opflow
The ZLD process provides an environmentally responsible
solution for concentrate management by eliminating a
wasteful discharge and extending potable water supplies.
the ZLD treatment process. As a result
of the recycle flows, the process units
are designed to treat flows higher than
the 1.2-mgd concentrate flow to accommodate the recycle streams. For the
1.2-mgd concentrate, the treatment process is designed to handle an additional
0.65 mgd of recycle flow.
The equalization tank was installed
below-grade to allow for gravity flows to
it, so self-priming pumps were selected
instead of submersible pumps in large
part because of the potentially corrosive equalization tank water. Submersible
pumps would need to be fully constructed
of stainless steel to withstand the environment, which wasn’t economically feasible.
Flow control evaluations considered variable frequency drives, motorized v-port
discharge ball valves, and multiple pumps.
Variable frequency drives were eliminated from consideration because of concerns about keeping the pumps primed
at low motor speeds. Three pumps,
along with a flow-controlled v-port ball
valve on the common recycle line, were
chosen.
Disinfection. Another significant challenge for the project was how to disinfect
the ZLD-treated water without exceeding
disinfection by-product limitations. The
city currently provides 4-log virus treatment in accordance with the Ground Water
Rule through free chlorine addition to the
blended permeate and raw water bypass
in the clearwell before chloramination.
The project’s original concept was
to combine the ZLD-treated water with
the permeate and the raw water bypass
streams in the clearwell, but higher TOC
concentrations in the ZLD-treated water
were a concern. Because the lime/soda
ash softening combined with membrane
filtration can provide 2-log virus inactivation, the ZLD-treated water was disinfected
separately with free chlorine to provide
the remaining 2-log virus treatment before
chloramination.
After the formation of chloramines, the
ZLD-treated and disinfected water is combined with the facility’s finished water. The
separate disinfection operation minimizes
impacts to the existing clearwell, transfer
pumping, and piping systems, allowing for
future plant expansion capacity as well as
minimizing DBP formation potential.
INTEGRATION WITH THE EXISTING FACILITY
The concentrate ZLD process is complex,
and it needed to be fully integrated with
Process Flow Diagram
The ZLD process was integrated into WTP No. 2 so the plant operates as a single facility.
14
(8) Floridan Aquifer
Limestone
Production Wells
19
21
23
30
Degasifier Removes
Hydrogen Sulfide and
Carbon Dioxide
Sand Separator
Pretreatment
Filtration
(4) Feed
Antiscalant Pumps
Low-Pressure
RO Stage 1
Low-Pressure
RO Stage 2
(4) Booster
Pumps
Caustic Soda and
Corrosion Inhibitor
Sodium
Hypochlorite
Ammonia
Chlorine
Contact
Chamber (3) Transfer
Pumps
Ammonia
31
32
Concentrate
Raw Water
Bypass (33%)
Lime / Soda Ash / Polymer
Sodium
Hypochlorite
2 Million Gallon
Ground Storage
Tank
(6) HighService
Pumps
Sodium
Hypochlorite
Sulfuric Acid and Antiscalant
49
(2) Solids Contact
Clarifiers
(4) Feed
Pumps
(4)
Ultrafiltration
(3) Transfer
Pumps
(1) Equalization Tank
(1) Sludge
Thickener Sludge Dewatering and Contract Hauling
Concentrate Zero Liquid Discharge Process
www.awwa.org/opflow
2014 © American Water Works Association
December 2014 Opflow 19
Water Reuse
P RO J E CT BE NE F I T S CH E CKLIST
ZERO LIQUID DISCHARGE REINFORCES
SUSTAINABILITY
The zero liquid discharge (ZLD) project implemented by the city of Palm Coast, Fla., has
accomplished several objectives and provided multiple environmental benefits, including
the following:
■ Brought the city into regulatory com■ Delays the costs of potential wellfield
pliance by eliminating the use of an
and water treatment plant expansions
■ Conserves water by recovering the conextended mixing zone
■ Eliminated the discharge of concentrate,
centrate and an alternative water supply,
the need for a National Pollutant Dismeeting the local water management
charge Elimination System concentrate
district’s requirements
discharge permit, and associated moni- ■ Provided an environmentally responsible
solution for concentrate management
toring and sampling costs
■ Meets the city’s green initiative goals for
by eliminating a wasteful discharge
water conservation and waste recovery
and maximizing the use of groundwater
■ Integrated the ZLD system into the existwithdrawals
ing treatment plant so the plant oper- ■ Produces high-quality drinking water
that meets US Environmental Protection
ates as one facility
■ Increased the plant’s capacity by approxAgency and Florida Department of Enviimately 1.2 mgd without the need for
ronmental Protection primary and secdeveloping additional source water
ondary standards as well as city water
supplies
quality goals
its respective components. Additionally,
the entire ZLD process needed to be integrated into the existing plant so the plant
operates as a single facility. This operational approach complies with the operating permit that was issued to incorporate
the concentrate ZLD process and increase
the plant’s overall capacity. Integrating
the ZLD process into the existing plant
included several critical considerations,
including electrical, instrumentation, and
SCADA improvements.
The design intent for the concentrate
ZLD project was to provide operators with
the ability to observe, monitor, and control
the entire facility’s operations, including
the ZLD process, from the existing operations room as well as additional control
from the new UF building. The ZLD process was automated to minimize maintenance by operations staff.
The instrumentation and SCADA system
associated with the ZLD process was integrated into the facility’s existing SCADA
20 Opflow December 2014
system to provide for seamless and automated operations, monitoring, and control.
The electrical system for the ZLD process
was integrated into the existing facility’s
electrical system and includes emergency
power for the overall facility to comply
with regulatory requirements.
OPERATIONAL CONSIDERATIONS
Instrumentation and Electrical. The exist-
ing instrumentation and SCADA system
at WTP No. 2 consists of a centralized
plant control system, providing monitoring and operating capability from a centralized computer system. Plant operations
have been directly wired into the control
room’s programmable logic control cabinet. The existing system was expanded
to incorporate and completely integrate
all of the ZLD processes into the modified SCADA system. This integration allows
the operators to monitor and control all of
the plant’s operations and processes from
a single location.
2014 © American Water Works Association
Electrical and Standby Power. The
electrical system for the existing facility
was expanded and upgraded to include
the ZLD process. The existing emergency generator was rehabilitated and
used for the concentrate ZLD process. A
new emergency generator was installed
to reinforce the plant’s reliability. This
approach was more cost-effective than
replacing the emergency power system
with a larger system to safeguard plant
operations, including the ZLD process.
Yard Piping and Underground Utilities.
The in-place raw water bypass piping
was relocated to accommodate the new
UF building. A significant amount of
piping and other underground utilities
exist on-site. As a result, new piping
and other underground utilities’ placement was challenging—a common issue
when improving a facility. The keys to
success were identifying existing piping
and utilities early in the project through
the use of record drawings, subsurface
utilities excavations, and staff knowledge of previous plant improvements.
PROJECT SUMMARY
The concentrate ZLD project includes a
softening process with sedimentation,
chemical treatment, membrane filtration,
and disinfection. The ZLD-treated water
is blended with finished water from WTP
No. 2, increasing the plant’s capacity by
approximately 1.2 mgd without the need
to obtain additional source water supplies while eliminating the use of an
extended mixing zone to achieve regulatory compliance.
To achieve 98.5 percent recovery
of concentrate for potable use, several process streams that would normally be disposed of are treated and
recycled to the head of the process for
additional treatment. Overall, the ZLD
process provides an environmentally
responsible solution for concentrate
management by eliminating a wasteful
discharge and extending potable water
supplies.
www.awwa.org/opflow