(MEC-J) Management and Economics Journal
E-ISSN: 2598-9537 P-ISSN: 2599-3402
Journal Home Page: http://ejournal.uin-malang.ac.id/index.php/mec
Volume 6 Number 2, August 2022
Extension of Time In Construction Projects
ABSTRACT
Madan Sharma
A.K. Mishra*
Janani Selvam
Lincoln University College
Malaysia
*Corresponding author
[email protected]
Timely complementation of project is highly focused. With an aim to
assess the consequences of time extension in terms of project’s
performance i.e time and cost based on cases of Nepal. The
questionnaire contained statements on practices adopted of Eot in
construction field, consequences of Eot in the project’s cost and time
and impacts of Eot in the project’s performance through literature
review. Also, the impacts of Eot in the project’s performance were
tested through Hypothesis test method. Total of four statements
from practices adopted in construction, seventeen statements from
the consequences of Eot and Four statements from the impacts of
Eot in projects performance were established and administrated on
twelve projects for collecting the information. The identified results
were analyzed with Relative Importance Index (RII) and Ranking.
The significant impacts of cost, time and quality were tested on
project performance by Regression as set Hypothesis. Overall RII of
practices adopted of Eot in construction field as timing of Eot claim
varied from maximum 0.813 to minimum 0.74. The RII of
consequences of Eot varied from maximum 0.920 to minimum
0.600. Architect too busy with other tasks attend the bottom position
based on overall RII rank value.
Keywords:
Construction,
Consequences, RII index
Extension
of
Time,
Impact,
| Received June 2022 | Accepted August 2022 | Available online August 2022 |
| DOI: http://dx.doi.org 10.18860/mec-j.v6i2.16659
INTRODUCTION
Projects have become more time-constrained in recent decades, and the capacity to
complete on time has become an increasingly crucial factor in projects. There is a focus
on time performance, often with heavy liquidated damages (LADs) for lateness, by
leveraging main contractor try to push delay risk onto the down line contractor
(Williams, 2003).
Delays are a common issue of disputes leading as one of the most prevalent and
expensive sources of issues in most of construction projects. There are several factors
that might create delays in the construction sector, some of which are unavoidable
157
Extension of Time In Construction .....
(Alkass et.al, 1995, Othman et.al, 2006, Ahuja et.al, 1994). As a result, it would be good to
produce a guideline to explain which events are eligible for EOT and which are not.
As a result, it is critical, especially when dealing with client delays, to determine his
eligibility for EOT and right to appropriate EOT within contract finish date. The
contractor may be susceptible to Liquidated Damages (LAD) for causes outside his
control, but within the control of the customer. As a result, EOT exists, they are
extremely difficult to prepare for, both theoretically and practically (Williams, 2003).
On a project, planning strategies are frequently utilized to anticipate the risk of EOT.
There are numerous issues with it (Alkass et.al, 1995). The issues may have arisen as a
result of the techniques' incapacity to do retroactive analysis, as well as the use of
incorrect techniques. As a result, a more scientific way to analyzing the EOT in a plausible
model is required. It can assist avoid unwanted disputes or contract breaches caused by
a skepticism in the process of requesting a time extension.
Furthermore, local practice in Nepal is doubtful when it comes to seeking and judging
time extensions. For both, there is no set technique or protocol Clients and contractors.
As a result, it is critical to disclose local EOT practice before recommending measures to
reduce EOT claims. This study aims to assess the consequences of time extension in
terms of project’s performance i.e time and cost based on cases of Nepal.
LITERATURE REVIEW
Empirical Reviews of Delays and Extension of Time
Bayissa, (2018) concluded that the weighted RII of elements uncovered that: delay to
convey the site (Right of way issue), monetary issues inspections, equipment
accessibility and failure, suspension of work by proprietor or contractor furthermore,
climate conditions were the most delay causing components of road construction
projects in Oromia, relevant to ORA street projects. Impacts of construction delay have
been likewise being researched in similar way and the outcomes were determined
utilizing RII. Consequently, Time and Budget invade have been discovered to be the two
most predominant impacts brought about by delays in Oromia streets development
projects appropriate to ORA road projects.
In Nepal, Mishra and Bhandari, (2018) in their study had stated that the main
considerations that influence the execution of the project as indicated by the positioning
based on RII for the apparent perspective on the owner, consultant, the contractor on
elements influencing the exhibition are based on design issues, materials deficiency,
quality issues, time consuming decision process, construction approach, supply of
skilled and unskilled labour, payment issues, ineffective site management, lack of
consistency in contract documents, organizational instruction flaws, productivity issue,
change orders, unexpected site situation, climate issue, administrative updates that
influence the execution of project. 28 distinct elements influencing the execution of the
work were found.
Mishra et al. (2018) expressed that material related factor was the main elements among
different categories for the delay in development projects, since the worth of relative
158 MEC-J (Management and Economics Journal)
Vol 6 (2) August 2022
Sharma, Mishra, Selvam
importance index was most noteworthy in material related variables followed by
different factors. This reality without a doubt remains constant for the development
projects as the short of material stock would consistently have a lot of attribution for
delays in development despite of having great planning and coordination guaranteed.
The second significant factor being the consultant, client and contractor related factor,
and so on in this investigation. Regarding the apparent impacts of the delay in the
development projects held by the respondents, the likely impact of the project delay
was cost overrun followed by arbitration, etc. Undoubtedly, the increment of the
expense was most significant impact of any deferred projects. Clearly, long the project
extends, more prominent the expense required for the activity of the task. All projects
under investigation had been provided with expansion of time dependent on the Public
Procurement Act (PPA) 2063 and Public Procurement Regulations (PPR) 2064. As per
the information accessible, all activities in this examination were discovered to be
postponed because of Natural Catastrophes (Rain, Wind, Earthquake and Flood), Land
issue, Strikes, Scarcity of the materials and design changes.
Hanif et al, (2014) stated that with the use of these questionnaires and reviews, the
causes of delays have been discovered and ranked. For the sake of evaluation, a variety
of techniques have been used. The major goal of this study was to investigate the
extension of time claims as a result, to examine various techniques that are employed in
Pakistan Hydropower, as well as to look into the reasons for the assessment's delay
submitting an EOT. Research uncovered that the defer in break installment
endorsements, land procurement issues, postpone in issuance of development
drawings, absence of standard timetable and unfortunate plan were among the main
contributing elements prompting Extension of Time Claims.
Alnass et al, (2014), expressed in the subject Guideline for planning exhaustive expansion
of time (EoT) guarantee that on the grounds that the undertaking group is constantly
bustling managing site issues and other task requests, it turns out to be more
challenging for them to enough report the postponements and disturbance occasions as
the venture turns out to be more convoluted. A period expansion guarantee or
disturbance guarantee ought to satisfactorily show causality and responsibility, as well
as help in exhibiting the degree of time-related harms experienced as an immediate
consequence of the defer occasions depended on, for the workers for hire to find true
success. The recording of deferrals and interruptions is a unique interaction that requires
progressing support from the arranging group, as well as help from any remaining
divisions.
In Malaysia, Lian et al, (2012) in The Assessment of Applications for Extension of Time
Claims in Malaysian Construction Industry had expressed that expansion of time (EOT)
has turned into a normal development movement in many tasks, particularly when
standard types of agreement are utilized, and it is perceived as a passable postpone in
customary development contracts. The worker for hire and managing engineer every
now and again spend a significant amount of time verifying and assessing the delays. For
such evaluations, a variety of methodologies have been used. However, the efficacy of
the approaches used has been a key element in encouraging foreign companies to invest
in Malaysia's building industry.
MEC-J (Management and Economics Journal)
Vol 6 (2) August 2022
159
Extension of Time In Construction .....
Consequences of time extension in terms of projects time and cost
The defer in development projects colossally affected time and cost overwhelm. It
likewise causes dangerous circumstance among proprietor and worker for hire like
debate, case, discretion, and some of the time absolute relinquishment of the task
(Assaf & Al-Hejji, 2006). Be that as it may, cost overwhelm was considered as the main
impact which may suspended or even end the venture before fulfillment.
Kikwasi (2012) expressed that the effects of deferral were differing concerning the
gatherings' view for instance proprietor thought postpone implies loss of income and
absence of administrations, on the other hand worker for hire thought about it as
deficiency of cash.
An examination led by Bayissa, (2018) showed the impacts of the deferral in the
construction business of projects delays in Oromia Roads Authority (ORA). Researcher
found eight potential normal impacts which emerging in many nations because of
deferral. These impacts were Cost overrun, Time overrun, Disputes, Total abandonment
of project, sub-graded quality project and poor public relations.
Mishra & Aithal (2020) contemplated that every one of the projects of water supply
chosen for the study were time overrun as the impacts of delay factors in construction.
Because of the active coordination and inclusion of respective Users' Committee, the
time overrun of the projects were found not exactly the government exclusively carried
out project. Variety, Social issues like Bandhs, strikes and debates, Delay in choice, site
ownership and regular cataclysms were tracked down the central point in delay the
execution of water supply projects.
Approval of EOT
If the reasons stated in the application are proven to be true after a thorough
examination, the EOT can be approved (PPMO, 2019) as: The Officer who approved the
Procurement can approve an EOT of up to 15% of the initial Project length. The
Departmental Chief can approve EOTs that are greater than 15% and up to 25% of the
initial Project Duration. The Secretariat of the Concerned Ministry/Entity can approve
EOTs of more than 25% but less than 50% of the initial Project Duration. There can be no
EOT that exceeds 50% of the initial Project Duration. The Contract should be cancelled
due to such requirements.
Following hypothesis was tested to analyze the impact of time extension on project
(Mishra, 2019):
Ho: There is no impact of time extension on projects.
H1: There is an impact of time extension on projects.
These hypotheses were tested by using regression analysis followed by ANOVA test,
which w signified whether the impact exists between independent and dependent
variable.
160 MEC-J (Management and Economics Journal)
Vol 6 (2) August 2022
Sharma, Mishra, Selvam
METHODOLOGY
Research Design
The action was carried to develop possible solution of the highly observed problem of
delay in construction projects and the research questions was oriented to investigate
the Practices adopted in extension of time in construction industries in Nepal.
Literatures reviews, of delays on construction projects and time extension,
consequences of extension of time and impact of time extension on projects and other
relevant journals had been studied in this process.
This study was carried out through a detailed questionnaire scheduled. This study was an
action research type. Concerning the study approach, two kinds of procedures was
utilized in study: quantitative and qualitative approach. Quantitative examination was
picked to know respondent's views towards time extension techniques and its
consequences and impacts and rank them in construction projects Likewise; qualitative
data were additionally added for a top to bottom clarification of the consequences of
Eot, the impacts of delay.
Projects Selection for collecting data
Based on accessibility considering convenience and representation of all over the Nepal ,
15 projects from high priority projects were selected for the study viz: 1.Sikta Irrigation
Project, 2.Babai Irrigation Project, 3.Ranijamara Kulaiya Irrigation Project, 4.Bheri Babai
Diversion Multipurpose Project, 5.Upper Tamakoshi Hydropower Project, 6.Budi Gandaki
Hydropower Project, 7.West Seti Hydropower Project, 8. Gautam Buddha International
Airport, 9.Pokhara Regional International Airport, 10. Lumbini Area Development
Project, 11.PushpaLal Mid Hill Highway, 12. North South Koshi Highway Project, 13.North
South Karnali Highway Project, 14.Kathmandu Terai Fast Track Project, and 15.Melamchi
Water Supply Project
Sample collection and Sample Size
It was tough to access the concerned stakeholder from already completed projects
however; it was easy to reach ongoing projects. So, 5 number of client, consultant and
contractor representatives were accessed from each project. Altogether, it became 225
responses.
Data Collection
The primary data was obtained through scheduled questionnaires along with personal
interviews with people involved. Field observations: chosen construction projects was
visited once to check whether the development of these projects was in smooth speed
or not. In like manner likewise be checked, regardless of whether what timings in the Eot
claim were done. The consequences from extension of time were checked over actual
factor that causes extension of time with the Earned value analysis. The impacts of
extension of time were tested by hypothesis testing. Questionnaires:
Questionnaire
Survey was finished by visiting individuals legitimately and filling without anyone else's
input. Interviews: Interview Survey was done by visiting individuals legitimately and
MEC-J (Management and Economics Journal)
Vol 6 (2) August 2022
161
Extension of Time In Construction .....
asking each individual perception. The secondary data collection was obtained through:
Contract Document and agreement paper of projects, Running Bills, Document
of
Infrastructure office advancement, Department of Roads,
Other distributed and
unpublished writing, reports and diaries papers, Internet and sites.
Validity and Reliability
For the validity the content validity method was used. The questionnaire prepared was
evaluated by experts as senior engineers, supervisors as pilot study and also compared
with different literatures. The opinion from different groups was collected and the
questions that should be administered for the study of extension time was chosen
among the many questions in the questionnaire survey. For the reliability test the
Cronbach alpha method was used (Ritter, 2010).
Data Analysis
Time Extension Practices Adopted
The first step of this research was to analyze practices of extension of time adopted in
construction projects under selected projects. To assess the types of techniques or
practices adopted of extension of types; monthly reports, quarterly reports, trimester
reports of projects progress and contract documents and claims for extension of time
and other relevant documents related to the project was reviewed at the time of desk
study. The practices adopted in time extension in construction industries was listed and
individual reactions to the poll which were then appointed with a numerical code were
carried out.
The positioning of variables in every classification depended on the RII to decide the
level of connection on positioning the components among the gatherings. This area
identified with inquiries on the variables that cause delays in ventures. The 5point Likerttype semantic rating scale was utilized to rate their discernments as 5 highest marks to
strong agreement and 1 lowest mark to show strong disagreement (Preedy and Watson,
2015).
This research had fulfilled the stated objectives of the study which can be shown in
matrix in the Table 1.
162 MEC-J (Management and Economics Journal)
Vol 6 (2) August 2022
Sharma, Mishra, Selvam
Table 1. Research Methodology Summary
Research
Objective
Data Required
Data Collection
Tools
Data Analysis
Tools
Reliability
To analyze the
time
extension of
project
practices
adopted
in
construction
field
Timing of Eot
adopted
in
construction
a.
Within a
sensible time from
the
date
of
accommodation
of subtleties of
guarantee by the
project workers
b.
21 days of
the finish of the
reason for delay
(Clause 120 of PPA
2007)
c.
Within 21
days from the
date
of
the
postpone
occasions
d.
At
the
finish
of
development
period
Types
of
consequences of
extension of time
Schedule
consequences
Financial
consequences
Contract
Documents,
monthly reports,
quarterly
reports,
trimester reports
letter of claims
evidence of delay
and
other
relevant
documents
related to the
project delay
Relative
importance
index
(RII),
Ranking
The Cronbach alpha for
Questionnaire was found as
0.8287 which is greater that
0.8.
The techniques
adopted could be ranked on
main basis.
Site Observation
Checklist
Questionnaire
Interview
Relative
importance
index
(RII),
Ranking
To assess the
consequences
of
time
extension in
terms
of
project’s time
and cost.
To analyze the Hypothesis:
Observations
impacts
of H01: No impact of
extension of time extension on
time (EOT) on projects.
performance.
Ha1: There is an
impact of time
extension
on
projects.
The Cronbach alpha of the
questionnaire
for
contractor was found as
0.8052, for consultant was
found to be 0.8103 and for
client was found to be
0.8046. Alpha value of all
the three parties more than
0.8,
showing
internal
consistency.
a. regression The Cronbach alpha for
analysis and impact
of
Eot
on
ANOVA test
performance was found as
0.8031. Alpha value more
than 0.8, showing internal
consistency.
MEC-J (Management and Economics Journal)
Vol 6 (2) August 2022
163
Extension of Time In Construction .....
RESULTS
Time extension practices adopted in construction field
The response of survey can be analyzed as given in Figure 1.
70%
60%
50%
40%
30%
20%
10%
0%
Within 21days
21 days of the end
Within a
from the date of
of the cause of
reasonable time
delay (Clause 120 the delay events
from the date of
of new
submission of
amendment of
details of claim by
Strongly Agree(%)PPA 2007)
Agree(%)
Undecided(%)
the contractors
At the end of the
construction
period
Disagree(%)
Strongly Disagree(%)
Figure 1. Bar graph for timing of assessment in evaluating Eot claim
Figure 1 shows that 27% of respondents emphatically concurred, 60% of respondents
concurred, 7% of respondent uncertain and 7% of respondents differ that the client
finishes the assessment inside a reasonable time from the date of accommodation of a
detail guarantee by the worker for hire. Though 27% of respondents firmly concurred,
60% of respondents concurred, 7% of respondents uncertain and 7% of respondents differ
that the Eot in Construction Projects of Nepal for the most part embraced were in 21
days of the finish of the reason for delay (Clause 120 of PPA 2007).Similarly, 40% of
respondents unequivocally concurred, 33% of respondents concurred, 13% of
respondents unsure, 7% of respondents differ and 7% of respondents emphatically differ
that the client completes the evaluation in somewhere around 21 days from the date of
the postpone occasions and 13% of respondents firmly concurred, 63% of respondents
concurred, 7% of respondents unsure, 13% of respondents differ and 3% of respondents
emphatically differ that the client does the appraisal of Eot toward the finish of the
development time frame.
In the vast majority of the cases, the client does the evaluation inside a sensible time
from the date of accommodation of a detail guarantee by the worker for hire had RII of
0.81333. This is like Malaysian development projects, where a concentrate by Yusuwan
164 MEC-J (Management and Economics Journal)
Vol 6 (2) August 2022
Sharma, Mishra, Selvam
and Adnan (2013). The Eot in Nepal generally embraced were in 21 days of the finish of
the reason for delay (Clause 120of PPA 2007) conveyed RII 0.81333, in somewhere
around 21 days from the date of the defer occasions had RII 0.78667 and toward the
finish of the development time frame had RII 0.74000.
Consequences of time extension in terms of project’s time and cost
Seventeen reasons for Eot were identified from literature review. The 45 questionnaires
were administered and the result from the analysis based on RII is shown in Table 2. The
reasons for Eot were computed and ranked based on RII value.
S.N.
1
2
3
4
5
6
7
Causes for Eot
Table 2. RII of reasons for Eot claim
RII and Rank
Client
Rank Consultant Rank Contractor Rank Overall Overall
RII
Rank
After date claim
0.82667
Submission
Ineffectively
0.82667
submission with
absence of
subtleties and
specifics
Assortment of
0.81333
pertinent realities
from site records to
lay out the
standard of the
case and
evaluation/tedious
to actually take a
look at records
Delay examination 0.80000
strategies utilized
by contractor
different with the
technique utilized
by the Architect
Delay in approval
0.77333
by employer
Contractor submits 0.74667
global claim
Hold on for the rest 0.85333
of occupation on
the grounds that
genuine deferral
still up in the air
until end of delay
or construction
4
0.6933
14
0.7867
8
0.769
9
4
0.627
16
0.7200
11
0.724
13
6
0.800
4
0.8667
4
0.827
3
7
0.733
10
0.8000
7
0.778
7
9
0.800
4
0.7733
9
0.782
6
12
0.840
2
0.6133
15
0.733
12
2
0.7733333
8
0.8667
4
0.831
2
MEC-J (Management and Economics Journal)
Vol 6 (2) August 2022
165
Extension of Time In Construction .....
S.N.
Causes for Eot
Client
8
9
10
11
12
13
14
15
16
17
Employers
attitude/interfernce
from employers
As persuasive
elements to project
worker
(nonappearance of
EOT might come
down on project
worker to perform
more effective)
The impacts are not
known/couldn't
predict that an
occasion would
create a setback
until the delay
happened
No reasonable
rule/pre-contract
arrangement for
surveying EOT
claim
Deficient Personnel
to aid appraisal
process/absence of
encounters
Designer new to
delay investigation
strategies
Architect too busy
with other tasks
Delay in approval
of contractors,
consultant,
materails suppliers
by client
Delay in providing
required evidence
for the claim of eot
by contractors
Resolvement of Eot
claim within 15 days
by employer after
the claim of Eot
RII and Rank
Rank Consultant Rank Contractor Rank Overall Overall
RII
Rank
0.69333
13
0.68
15
0.6400
13
0.671
15
0.85333
2
0.8133333
3
0.7067
12
0.791
5
0.96000
1
0.8
4
1.0000
1
0.920
1
0.80000
7
0.8666667
1
0.5733
16
0.747
11
0.60000
17
0.7066667
13
0.4933
17
0.600
17
0.62667
16
0.7866667
7
0.7333
10
0.716
14
0.64000
14
0.6266667
16
0.6400
13
0.636
16
0.76000
11
0.76
9
0.8800
3
0.800
4
0.77333
9
0.7333333
10
0.8267
6
0.778
7
0.64000
14
0.7333333
10
0.9333
2
0.769
9
166 MEC-J (Management and Economics Journal)
Vol 6 (2) August 2022
Sharma, Mishra, Selvam
RII examination and positioning in Table 1 showed the primary reasons of Eot as the
impacts are not known/couldn't predict that an occasion would create a setback until
the postponement happened was found. Additionally, hold on for the rest of occupation
on the grounds that genuine deferral not entirely set in stone until end of postponement
or development and assortment of applicable realities from site records to lay out the
guideline of the case and measurement/tedious to check records procured second
significant reasons. Similarly, defer in endorsement of project workers, expert, as
persuasive elements to worker for hire (nonattendance of EOT might come down on
project worker to perform more proficient), were the vitally top five reasons for Eot as
the results.
This is conversely, with what had been drilled in Malaysian development projects, where
a concentrate by Yusuwan and Adnan (2013), found that inadequately accommodation
by worker for hire/absence of subtleties and specifics, Late Submission of guarantee by
the worker for hire, Collection of significant realities from site records to lay out the rule
of the case and evaluation/tedious to check records, Delay examination strategies
utilized by worker for hire different with the technique utilized by the Architect, Delay in
endorsement by Employer were the primary drivers of Eot guarantee. The consequences
on the project’s cost and time were from causes of extension of time and also from the
factors that delays the projects.
Impacts of extension of time (EOT) on project performance
To test this hypothesis, Regression was used to find out if there is impact exists between
Eot and Project performance.
Table 3. Regression to Find Cost Impact of Eot on Project Performance
Regression Statistics
Multiple R
0.82
R Square
0.67
Adjusted R Square
0.66
Standard Error
0.30
Observations
30.00
Anova
Regression
Residual
Total
Intercept
Mean Respon of
Project
Performance
Df
1.00
28.00
29.00
coef
1.12
0.77
SS
5.01
2.46
7.47
Std.
error
0.45
0.10
MS
5.02
0.09
F
57.05
Sig. F
0.000
t stat
P value
Lower 95%
Upper 95%
2.51
7.55
0.02
0.00
0.20
0.56
2.03
0.97
MEC-J (Management and Economics Journal)
Vol 6 (2) August 2022
167
Extension of Time In Construction .....
The Examined (F) esteem was equivalent to (57.05) with plausibility esteem (0.00) and it
is lower than the particular worth (0.05), and that shows there is a critical effect exists
between cost effect and Project execution. Thus, the invalid speculation was not
acknowledged: There is an effect of cost on Project execution because of Eot.
Comparatively for time and quality, test has been finished as displayed in Table 3.
S.N
1
2
3
Table 4. Results of hypothesis testing
Hypothesis
F
Sig. F
Impact of cost on Project
57.05
0.00
performance
Impact of time on Project
65.27
0.00
performance
Impact of quality on Project
123.09
0.00
performance
Impact
Impact Exists
Impact Exists
Impact Exists
The calculated F value is higher than the significant f value. Therefore, all the null
hypotheses are rejected and alternative hypothesis were selected i.e. There was impact
of cost, Time and quality on project performance during EoT in given below the Table 4.
DISCUSSION
The results obtained from study were compared with different literature. For the
objective of practices of Eot adopted in Nepalese construction industries Within a
reasonable time from the date of submission of details of claim by the contractors and 21
days of the end of the cause of delay (Clause 120 of PPA 2007 were the main practices
adopted followed by Within 21 days from the date of the delay events and at the end of
the construction period.
Yusuwan & Adnan (2013), led concentrate on Assessing Extension of Time Application in
Malaysian Construction Industry: Views from experts, communicated that the
respondents of the study were next mentioned to express the planning of appraisal of
EoT claims in light of four recognized timings regarding PAM 2006 arrangements.
Apparently, generally speaking, the planner does the evaluation inside a sensible time
from the date of accommodation of a detail guarantee by worker for hire. The
respondents were then approached to express their favored strategy in assessing EoT
claims.
Azad et al. (2019), performed research on Influence Factors in Extension of Time Claims
and stated that incomplete documents/drawing, financial difficulties of client, lack of
skilled labour, defective works, shortage of manpower, poor site management and
supervision, mistakes during construction, change order, labour injuries/accident in site,
changes in drawings/specifications, improper planning, conflict between parties, poor
subcontractor performance were the main factors for extension of time. The findings in
this study were in similar to the findings of Yusuwan & Adnan (2013) and also with Azad
et al. (2019).
168 MEC-J (Management and Economics Journal)
Vol 6 (2) August 2022
Sharma, Mishra, Selvam
RII examination and positioning in Table 1 showed the primary reasons of Eot as the
impacts are not known/couldn't predict that an occasion would create a setback until
the postponement happened was found. Additionally, hold on for the rest of occupation
on the grounds that genuine deferral not entirely set in stone until end of postponement
or development and assortment of applicable realities from site records to lay out the
guideline of the case and measurement/tedious to check records procured second
significant reasons. Similarly, defer in endorsement of project workers, expert, as
persuasive elements to worker for hire (nonattendance of EOT might come down on
project worker to perform more proficient), were the vitally top five reasons for Eot as
the results.
This is conversely, with what had been drilled in Malaysian development projects, where
a concentrate by Yusuwan & Adnan (2013), found that inadequately accommodation by
worker for hire/absence of subtleties and specifics, Late Submission of guarantee by the
worker for hire, Collection of significant realities from site records to lay out the rule of
the case and evaluation/tedious to check records, Delay examination strategies utilized
by worker for hire different with the technique utilized by the Architect, Delay in
endorsement by Employer were the primary drivers of Eot guarantee. The consequences
on the project’s cost and time were from causes of extension of time and also from the
factors that delays the projects.
The outcomes acquired from study were contrasted and different writing. For the target
of outcomes of time expansion as far as undertaking's time and cost the impacts are not
known/couldn't predict that an occasion would create a setback until the postponement
happened was found the high level for example rank one. Likewise, hold on for the rest
of occupation on the grounds that genuine deferral still up in the air until end of
postponement or development and assortment of significant realities from site records
to lay out the standard of the case and measurement/tedious to check records gained
the second and third position. In like manner, postpone in endorsement of workers for
hire, expert, as persuasive variables to worker for hire (nonattendance of EOT might
come down on project worker to perform more effective) were the principal bunch
factors got from results.
Yusuwan & Adnan (2013), led concentrate on Assessing Extension of Time Application in
Malaysian Construction Industry: Views from experts, communicated that unfortunate
accommodation of cases by the worker for hire (e.g., missing subtleties and data), late
accommodation of cases by the worker for hire, and assembling significant realities from
field records to lay out the standard of the case were positioned most elevated by
respondents as explanations behind late assessment of Eot claims. These outcomes
propose that the fundamental reasons that might delay the assessment interaction are
firmly related with the administration of activities records. It recommends the viable
agreement organization with coordinated record keeping prompts fruitful undertaking
the executives, yet in addition expands the possibilities of an effective legally binding
case. While there is no assurance of getting everything, at any rate, appropriate
verifiable proof and satisfactory supporting documentation will work with claims the
MEC-J (Management and Economics Journal) 169
Vol 6 (2) August 2022
Extension of Time In Construction .....
executives, assisting with decreasing struggles and questions that outcome from
unacceptable cases goal.
This is conversely, of the concentrate in Nepalese development enterprises with what
had been drilled in Malaysian development projects, where a concentrate by Yusuwan &
Adnan (2013), found that inadequately accommodation by worker for hire/absence of
subtleties and specifics, Late Submission of guarantee by the project worker, Collection
of significant realities from site records to lay out the standard of the case and
evaluation/tedious to check records, Delay examination techniques utilized by project
worker different with the strategy utilized by the Architect, Delay in endorsement by
Employer were the primary drivers of Eot guarantee.
Mishra et al. (2020), drove focus on Dispute of the Contracts: A Case from Sikta Irrigation
Project, Banke, Nepal, and saw that as: Major factors impacting the undertaking
execution recognized were Normal Catastrophes, Rainfall and Pre-storm, Land Issue,
Blockade, Shortage of the materials, Configuration change and Coronavirus Lock down.
Things (1), (2), and (3) above are viewed as power majeure under their individual
agreement records. Thing (4) is likewise delay-related occasions that are the sole liability
of the Customer. Thing (5) is likewise a postpone related occasion because of the Covid 19 Covid and lockdown. So for the above occasions, the project worker is all liable for
time expansions. Right now, it ought to be noticed that all undertakings surveyed
followed the General Contract Conditions of the Office of Government Oversight
Standard Bid Document for Schedules and Time Extensions. EOT1, EOT2, EoT3 for all
tasks were conceded as per Section 56 of the Public Procurement Act and Section 120 of
the Public Procurement Rules. Likewise, the study had identified the causes that leads to
the claims of extension of time as natural catastrophe, land issue, scarcity of materials,
Covid-19 lockdown etc., similarly, this study also identified almost similar results.
The results obtained from study were compared with different literature. For the
objective of impacts of extension of time (EOT) on project performance the hypothesis
test was done and all the null hypotheses are rejected. In the case of construction
projects in Nepal, time overrun was the norm rather than the exception. Cost excess
arose from the time overrun. All of the projects chosen for study were time overrun
(Mishra & Aithal, 2020). Likewise, the study had identified the impacts due to time
extension in time overrun, cost overrun, similarly, this study also identified almost similar
results.
Mishra et al. (2020), concentrated on in appraisal of time-cost model of general
wellbeing structures in Nepal and expressed that the undertaking time and cost of the
Public Health Buildings projects in Nepal were considerably related (p = 0.599. For the
expectation of time and cost parts of comparative undertakings, a condition was
created: Time = 487.5 (C/79.96)0.293 (time is addressed in days and cost in million NRs.).
By combining the immediate and indirect expenditure esteems, the venture's total timecost relationship could be determined which showed that due to time extension there is
impact on time, cost and quality. Stated in the study it had identified the impacts due to
170 MEC-J (Management and Economics Journal)
Vol 6 (2) August 2022
Sharma, Mishra, Selvam
time extension in time overrun, cost overrun, similarly, this study also identified almost
similar results.
CONCLUSION
Thus, from this study, it can be concluded that overall construction projects face delays
due to delay factors and extension of time is required. The study identified the practices
of extension of time adopted in construction filed. Inside a sensible time from the date
of accommodation of subtleties of guarantee by the workers for hire and 21 days of the
finish of the reason for delay (Clause 120 of PPA 2007 were the main practices off
extension of time adopted in Nepal followed by Within 21 days from the date of the
delay events and at the end of the construction period. The results of Eot as the impacts
are not known/couldn't predict that an occasion would create a setback until the
postponement happened were found. Similarly, hold on for the rest of job on the
grounds that genuine delay not entirely settled until end of delay and assortment of
important realities from site records to lay out the rule of the case and
evaluation/tedious to actually look at records acquired second major reasons. Likewise,
delay in approval of contractors, consultant, As persuasive elements to project worker
(nonappearance of EOT might come down on project worker to perform more
effective), were the main top five causes of Eot as the consequences.
The consequences on the project’s cost and time were from all factors of extension of
time and also from the factors that delays the projects. The impacts of extension of time
(EOT) on project performance, hypothesis test was done and all the null hypotheses are
rejected and alternative hypothesis were selected: There is impact of time, cost and
quality on project performance during extension of time.
REFERENCES
Ahuja, H.N., Dozzi, S.P., Abourizk, S.M. (1994). Project management: techniques in
planning and controlling construction projects. New York: Wiley.
Alkass, M. Mazerolle, E. Tribaldos., F. Harris. (1995). Computer aided construction delay
analysis and claims preparation. Construction Management and Economics, 13(4),
335-352.
Alnaas, K.A.A., Khalil, A.H.H., Nassar, G. E. (2014). Guideline for preparing comprehensive
extension of time (EoT) claim. DOI: http://dx.doi.org/10.1016/j.hbrcj.2014.01.005
Assaf, S A and Al-Heiji. (2006). Causes of Delays in Large Construction Projects.
International Journal of Project Management, 24, 349 -357.
Azad- Al N, Enegbuma I W, Bamgbade A J, Ohueri C.C. (2019). Influence Factors in
Extension of Time Claims.
Bayissa F. Yadeta. (2018). Causes and Effects of Delay in Oromia Roads Construction
Projects Pertinent to Oromia Roads Authority Road Projects. In Partial Fulfillment of
the Requirement of the Master’s Degree of Business Administration in
Construction Management.
MEC-J (Management and Economics Journal)
Vol 6 (2) August 2022
171
Extension of Time In Construction .....
Hanif H, Saleem Y, Shahid Z A, Hanif A, Zeb A. (2014). Assessment of Extension of Time
Claims in Hydropower Projects of Pakistan. International Journal of Engineering and
Advanced
Technology
(IJEAT),
-4(2),
https://www.designingbuildings.co.uk/wiki/Extension_of_time_EOT_in_constructi
on_contracts
Kikwasi, G J. (2012). Causes and effects of delays and disruptions in construction projects
in Tanzania. Australasian Journal of Construction Economics and Building,
Conference Series, 1 (2) 52-59.
Lim, S. & M. Z. Mohamed. (1999). Criteria of project success: an exploratory reexamination. International Journal of Project Management. 17(4), 243-248.
Mishra, A.K. & Aithal, P. S. (2020). Financial Impact Assessment of Time Overrun:A Case
of Second Small Towns Water Supply and Sanitation Sector Project,
NepalInternational Journal of Applied Engineering and Management Letters
(IJAEML), 4(2), 159-173. DOI: http://doi.org/10.5281/zenodo.4074715.
Mishra, A.K. (2019). Assessment of project performance in terms of time cost and
quality. (Doctoraldissertation, Ph.D. Thesis. Institute of Business Management,
Chhatrapati
Shahu
Ji
Maharaj
University
Kanpur,
India).
DOI:
10.13140/RG.2.2.15038.84809.
Mishra A K. (2019). Safety Management Practice Impact on Project Performance. Solid
State Technology, 62(3), 42-52. Archives Available @ www.solidstatetechnology.us
Mishra A K, Bhandari S. (2018). Performance Assessment of ongoing Construction
projects under Town Development Fund, Nepal. Int J Adv Res Civil Stru Engr; 1(1&2),
27-39.
Mishra A K, Bhandari S, Jha T. (2018). Factors Affecting Performance and Time Extension
of ongoing Construction Projects under Town Development Fund, Nepal. J Adv Res
Const Urban Arch, 3(4), 7-25.
Mishra, A. K., Sudarsan, J. S. & Nithiyanantham, S. (2020). Assessment of time–cost
model of public health buildings in Nepal. Asian J. Civ Eng. 1-10.
https://doi.org/10.1007/s42107-020- 00294-4.
Othman, J. V. Torrance, and M. A. Hamid (2006). Factors influencing the construction
time of civil engineering projects in Malaysia. Journal of Engineering, Construction
and Architectural Management. 13(5), 481-501.
Preedy V R, Watson R R. (2015). Handbook of Disease Burdens and Quality of Life
Measures. New York: Springer. DOI.org/10.1007/978-0-387-78665-0_6363.
Ritter L N. (2010). Understanding a Widely Misunderstood Statistic: Cronbach’s α. Paper
presented at the annual meeting of the Southwest Educational Research Association,
New Orleans.
Williams, T. (2003). Assessing extension of time delays on major projects. International
Journal of Project Management, 21, 19-26.
Yusuwan N.M, Adnan H. (2013). Assessing Extension of Time Application in Malaysian
Construction Industry: Views from professionals. Available online at
www.sciencedirect.com. Doi: 10.1016/j.sbspro.2013.11.007.
172 MEC-J (Management and Economics Journal)
Vol 6 (2) August 2022